From Casetext: Smarter Legal Research

JH Kelly, LLC v. AECOM Tech. Servs.

United States District Court, Northern District of California
Jan 21, 2022
20-cv-05381-HSG (N.D. Cal. Jan. 21, 2022)

Opinion

20-cv-05381-HSG

01-21-2022

JH KELLY, LLC, Plaintiff, v. AECOM TECHNICAL SERVICES, INC.., et al., Defendants.


ORDER GRANTING IN PART AND DENYING IN PART MOTION TO DISMISS JH KELLY, LLC'S SECOND AMENDED COMPLAINT

RE: DKT. NO. 98

HAYWOOD S. GILLIAM, JR. UNITED STATES DISTRICT JUDGE

Before the Court is Defendant and Counter-Claimant AECOM Technical Services, Inc.'s (“AECOM”) motion to dismiss certain claims in JH Kelly LLC's (“JH Kelly”) Second Amended Complaint. Dkt. No. 98 (“Mot.”). The motion is fully briefed. See Dkt. Nos. 105 (“Opp.”) and 110 (“Reply”). The Court finds this matter appropriate for disposition without oral argument and the matter is deemed submitted. See Civil L.R. 7-1(b). For the following reasons, the motion is GRANTED IN PART and DENIED IN PART.

I. BACKGROUND

This construction dispute arises out of the Burney K2 Replacement Project (“Project”), which involved the replacement of a natural gas compressor unit and various upgrades at the compressor station near Burnley, California. Dkt. No. 102 (JH Kelly's Second Amended Complaint or “SAC”) ¶ 1. The Burney Compressor Station is part of Pacific Gas & Electric Company's (“PG&E”) natural gas distribution system. Id. ¶ 11. That system supplies natural gas to the surrounding area and allows compressed gas to travel through pipelines from Oregon to consumers in California. Id. In all, PG&E's natural gas distribution system provides service to around 4.2 million customers from Bakersfield, California to the Oregon border. Id. 1

On February 11, 2016, AECOM entered into an agreement (the “EPC Agreement”) with PG&E for the Project. Id. ¶ 19. Under the EPC Agreement, AECOM agreed to act as the designbuilder and prime contractor for the Project. Id. On October 21, 2016, AECOM and Kelly entered into an agreement (the “Subcontract”) for the construction portion of the work. Id. ¶¶ 2527.

Various issues on the Project led to disputes between JH Kelly, AECOM and PG&E, and JH Kelly filed the First Amended Complaint on January 29, 2021. Dkt. No. 18. PG&E moved to dismiss JH Kelly's First Amended Complaint and prevailed as to JH Kelly's first claim for foreclosure of mechanic's lien. Dkt Nos. 24, 56. On March 8, 2021, AECOM filed its First Amended Counterclaim against PG&E and JH Kelly. Dkt. No. 38. PG&E moved to dismiss AECOM's First Amended Counterclaim, including AECOM's quantum meruit claim based on an abandonment theory. Dkt. No. 48. On June 28, 2021, the Court granted PG&E's Motion to Dismiss as to AECOM's quantum meruit claim based on an abandonment theory but gave AECOM leave to amend its claim. See Dkt. No. 64. AECOM then filed its Second Amended Counterclaim on July 19, 2021. Dkt. No. 65. AECOM and PG&E reached a settlement on October 18, 2021 and ultimately agreed to dismiss their claims against one another with prejudice. See Dkt. Nos. 93, 127.

In light of the Court's order dismissing AECOM's original quantum meruit claim based on an abandonment theory, JH Kelly sought and was granted leave to also amend its First Amended Complaint, which also stated a quantum meruit abandonment claim. See Dkt. Nos. 82, 100. JH Kelly then filed the operative SAC, which is the subject of AECOM's present motion to dismiss. Dkt. No. 102.

II. LEGAL STANDARD

Federal Rule of Civil Procedure 8(a) requires that a complaint contain “a short and plain statement of the claim showing that the pleader is entitled to relief.” Fed.R.Civ.P. 8(a)(2). A defendant may move to dismiss a complaint for failing to state a claim upon which relief can be granted under Rule 12(b)(6). “Dismissal under Rule 12(b)(6) is appropriate only where the complaint lacks a cognizable legal theory or sufficient facts to support a cognizable legal theory.” 2

Mendiondo v. Centinela Hosp. Med. Ctr., 521 F.3d 1097, 1104 (9th Cir. 2008). To survive a Rule 12(b)(6) motion, a plaintiff need only plead “enough facts to state a claim to relief that is plausible on its face.” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007). A claim is facially plausible when a plaintiff pleads “factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009).

In reviewing the plausibility of a complaint, courts “accept factual allegations in the complaint as true and construe the pleadings in the light most favorable to the nonmoving party.” Manzarek v. St. Paul Fire & Marine Ins. Co., 519 F.3d 1025, 1031 (9th Cir. 2008). Nevertheless, courts do not “accept as true allegations that are merely conclusory, unwarranted deductions of fact, or unreasonable inferences.” In re Gilead Scis. Secs. Litig., 536 F.3d 1049, 1055 (9th Cir. 2008) (quoting Sprewell v. Golden State Warriors, 266 F.3d 979, 988 (9th Cir. 2001)).

If the court concludes that a 12(b)(6) motion should be granted, the “court should grant leave to amend even if no request to amend the pleading was made, unless it determines that the pleading could not possibly be cured by the allegation of other facts.” Lopez v. Smith, 203 F.3d 1122, 1127 (9th Cir. 2000) (en banc) (quotation omitted).

III. DISCUSSION

JH Kelly's SAC alleges eight causes of action against AECOM. Dkt. No. 102. AECOM moves to dismiss the SAC's (1) Fifth Claim for Breach of the Implied Covenant of Good Faith and Fair Dealing; (2) Sixth Claim for Quantum Meruit/Abandonment of Contract; and (3) Eighth Claim for Quantum Meruit/Reasonable Value. See Mot. at 6.

As an initial matter, JH Kelly contends that the Court should deny AECOM's motion to dismiss its claim for breach of the implied covenant of good faith and fair dealing as untimely. Opp. at 19-20. JH Kelly argues that AECOM raised its motion after the dispositive motion deadline even though the claim is “materially unchanged” from previous versions of JH Kelly's complaint. Id. The Court agrees that AECOM waived its right to bring a 12(b)(6) challenge to JH Kelly's claims for implied covenant of good faith and fair dealing and quantum meruit for reasonable value because AECOM previously answered JH Kelly's First Amended Complaint, which contained identical claims. See Dkt. Nos. 18 ¶¶ 73-76, 88-90; 23; see also Fed.R.Civ.P. 12(b)(6); 3 Elvig v. Calvin Presbyterian Church, 375 F.3d 951, 954 (9th Cir. 2004) (“A Rule 12(b)(6) motion must be made before the responsive pleading ....Here, the Defendants filed their motion to dismiss after filing their answer.”) (emphases added).

Perhaps recognizing this waiver, AECOM asks the Court to consider its Motion as a motion for judgment on the pleadings. Mot. at 15. Such a motion may be brought after the pleadings are closed but only if it is “early enough not to delay trial[.]” Fed.R.Civ.P. 12(c). Because AECOM's motion may narrow the issues for trial, and because it can be addressed without delaying trial, the Court construes it as a motion for judgment on the pleadings and finds good cause to address its merits.

Oddly, AECOM asks the Court for judgment with respect to JH Kelly's First Amended Complaint. See Mot. at 15. The Court finds no basis for doing so because that complaint is no longer the operative complaint in this action.

A. Implied Covenant of Good Faith and Fair Dealing

AECOM first moves to dismiss JH Kelly's claim for breach of the covenant of good faith and fair dealing on the ground that it is duplicative of the breach of contract claim. See Mot. at 1314. The Court agrees that JH Kelly's implied covenant claim, at least as currently pled, is superfluous.

Every contract contains an implied-in-law covenant that imposes on each party a “duty of good faith and fair dealing” in the performance and enforcement of the contract. Foley v. Interactive Data Corp., 47 Cal.3d 654, 683, 765 P.2d 373, 389 (1988). The California Supreme Court has held that “where breach of an actual term [of the contract] is alleged, a separate implied covenant claim, based on the same breach, is superfluous.” Guz v. Bechtel Nat. Inc., 24 Cal.4th 317, 327, 8 P.3d 1089, 1095 (2000). At the same time, however, the Supreme Court explained that an implied covenant claim may not allege a breach of obligations beyond the contract's express terms. Id.

At least one California state court has read the California Supreme Court's decision in Guz to preclude any possibility of considering breach of contract and implied covenant of good dealing claims as separate and distinct. See Smith v. Int'l Bhd. of Elec. Workers, 109 Cal.App.4th 1637, 1645 n. 3, 1 Cal.Rptr.3d 374, 378 (2003). 4 But several federal district courts have read Guz to allow simultaneous breach of contract and implied covenant claims when the plaintiff alleges that the defendant exercised a right under the contract in bad faith to frustrate the contract's benefits. See, e.g., Daly v. United Healthcare Ins. Co., No. 10-CV-03032-LHK, 2010 WL 4510911, at *5 (N.D. Cal. Nov. 1, 2010); Celador Intern. Ltd. v. Walt Disney Co., 347 F.Supp.2d 846, 853 (C.D. Cal. 2004); Lamke v. Sunstate Equip. Co., LLC, 387 F.Supp.2d 1044, 1048 (N.D. Cal. 2004); see also Guz, 24 Cal.4th at 318 n.18 (“We do not suggest the covenant of good faith and fair dealing has no function whatever in the interpretation and enforcement of employment contracts . . . . [T]he covenant prevents a party from acting in bad faith to frustrate the contract's actual benefits.”) (alterations omitted).

AECOM argues that JH Kelly's claim for breach of the implied covenant should be disregarded as superfluous because it “relies on the same alleged facts and seeks the same damages claimed in a contract claim.” Mot. at 14. The Court is not entirely convinced by AECOM's argument. As the Celador court noted, courts analyzing whether a claim for breach of the implied covenant is duplicative of a breach of contract claim “should not mechanically inquire whether the same facts are alleged and whether the same remedy is sought” because only a limited set of circumstances can give rise to a contract lawsuit, and the same remedies are available for both claims. Celador, 347 F.Supp.2d at 853. In other words, a finding that the claims involve the same set of facts and seek the same remedy is a necessary but not sufficient condition of a superfluous implied covenant claim.

Rather, the fundamental problem with JH Kelly's SAC is that it does not sufficiently distinguish its implied covenant claim from its breach of contract claim. The SAC does little more than allege that AECOM breached the implied covenant by the same course of conduct that underlies JH Kelly's claim for breach of contract. Compare SAC ¶ 55 with ¶ 70. These 5 allegations “do not go beyond the statement of a mere contract breach and, relying on the same alleged acts, simply seek the same damages or other relief already claimed in a companion contract cause of action.” Careau & Co. v. Sec. Pac. Bus. Credit, Inc., 222 Cal.App.3d 1371, 1377, 272 Cal.Rptr. 387 (1990). The Court accordingly finds that JH Kelly's fifth claim for breach of the implied covenant “may be disregarded as superfluous” and GRANTS AECOM's motion to dismiss as to that claim. Id.

Specifically, the SAC alleges the following:

As alleged herein, AECOM breached the covenant of good faith and fair dealing by, among other things, its failure and refusal to timely and properly manage and administer the Project; its failure to address and respond to design issues; its refusal to properly and timely respond to CORs; its refusal to pay Kelly for both its original and extra work that was directed by AECOM; its refusal to provide Kelly with timely updates regarding changes to the Project Schedule, including, but not limited to, changes to the delivery dates for the IFC drawings, and the delivery dates for materials; its failure to pay even undisputed amounts owing to Kelly in an effort to financially burden Kelly and in an attempt to interfere with Kelly's relationships with its subcontractors; and its general failure and refusal to negotiate or deal in good faith with Kelly.
SAC ¶ 70.

B. Quantum Meruit/Abandonment of Contract

AECOM moves to dismiss JH Kelly's Sixth Claim for Quantum Meruit, which is based on allegations that AECOM abandoned the Subcontract by subsequently demanding a materially different scope of work. See SAC ¶¶ 74-8. AECOM similarly alleged in its counterclaim that PG&E abandoned the EPC Agreement by demanding excessive changes to the Project. See Dkt. No. 38 ¶¶ 135-143. The Court dismissed AECOM's quantum meruit claim because AECOM failed to allege, as required, that both parties agreed that the contract was terminated and of no further force and effect. See Dkt. No. 64 at 6; Amelco Elec. v. City of Thousand Oaks, 27 Cal.4th 228, 236 (2002) (“[A]bandonment requires a finding that both parties intended to disregard the contract.”) (alteration and emphasis in original). AECOM now contends that JH Kelly's Sixth Claim for Quantum Meruit fails for the same reason. See Mot. at 9-10. The Court disagrees.

Under the abandonment doctrine, a construction contract is deemed “abandoned” once the parties (1) fail to follow the contract's change order process, and (2) when the final project is “materially different” from the terms of the original contract. Amelco Elec., 27 Cal.4th at 235, 239. 6 “Abandonment requires a finding that both parties intended to disregard the contract.” Id. at 236 (citations and internal punctuation omitted). That is, abandonment occurs “only where both contracting parties agree that the contract is terminated and of no further force and effect.” Ben-Zvi v. Edmar Co., 40 Cal.App.4th 468, 474 (1995) (internal punctuation omitted).

A construction contract with a firm price often includes a “change order” provision, which creates a process for compensation for work performed beyond the scope of the contract. See Haskell Corp. v. Conoco Phillips Co., No. A124446, 2012 WL 845398, at *8 (Cal.Ct.App. Mar. 14, 2012)

There is no dispute that JH Kelly's SAC at least alleges that the final project was “materially different” from the terms of the Subcontract. See SAC ¶ 43 (detailing how “Kelly was forced to perform massive additional, changed and re-sequenced work, forced to work for a far longer period than planned, and forced to incur substantial damages as a result.”). The only question is whether the SAC plausibly alleges that both parties intended to abandon the Subcontract's change order process.

As to AECOM, the SAC alleges that of 273 total change order requests ultimately issued by JH Kelly to AECOM, there are 199-valued at over $9.5 million-that are “unresolved” by AECOM and are “still pending years after the Project was completed.” SAC ¶ 44. The SAC further alleges that AECOM never responded to $7,073,527 worth of requests. Id. Accepting these factual allegations as true and construing them in the light most favorable to JH Kelly, as the Court must at this stage, the Court can reasonably infer that AECOM never resolved millions of dollars' worth of change order requests because it ultimately abandoned the Subcontract's change order process. Manzarek, 519 F.3d at 1031.

AECOM's primary argument to the contrary is that the SAC itself acknowledges that AECOM provided a response to 205 of JH Kelly's 273 requests-96 that AECOM reduced in value, 9 that AECOM rejected, and 26 that AECOM approved (but did not pay). See Mot. at 8-9. If AECOM intended to abandon the contract, it argues, it would make no sense for it to address over 200 requests. See Reply at 9. But the fact that AECOM responded to or executed some change order requests does not render JH Kelly's quantum meruit claim under the abandonment theory fundamentally implausible as a matter of law at the pleading stage-particularly since the SAC alleges that AECOM ultimately never responded to several million dollars' worth of 7 requests. SAC ¶ 44; see also C. Norman Peterson Co. v. Container Corp. of Am., 172 Cal.App.3d 628, 641, 218 Cal.Rptr. 592, 599 (1985) (finding abandonment where the requirement for written change orders was only “completely abandoned” during the project's critical shutdown stage). While evidence that AECOM addressed over 200 requests may undermine Plaintiff's abandonment theory at trial, the Court does not weigh the evidence at this stage in the litigation. See Starr v. Baca, 652 F.3d 1202, 1216 (9th Cir. 2011) (“If there are two alternative explanations, one advanced by defendant and the other advanced by plaintiff, both of which are plausible, plaintiff's complaint survives a motion to dismiss under Rule 12(b)(6).”). The Court therefore finds that the SAC plausibly alleges that AECOM abandoned the Subcontract's change order process.

As to JH Kelly, the SAC alleges that, as a result of AECOM's abandonment, JH Kelly was also forced to abandon the Subcontract's change order process. SAC ¶¶ 77-78. The SAC further alleges that, based on JH Kelly's understanding that the Project, as materially changed, would necessarily proceed on a quantum meruit basis, JH Kelly nevertheless completed the work despite the lack of payment. Id.

AECOM contends that these allegations are inconsistent with other parts of the SAC where JH Kelly alleges that it “performed all conditions, covenants, and promises required on its part to be performed in accordance with the terms and conditions of the Subcontract, ” “timely submitted CORs for all of the foregoing additional work, changed work, and resulting damages, ” and complied with its obligations to ensure that the project was completed. Mot. at 11.

But the Court does not find these allegations inherently contradictory. To begin with, JH Kelly's allegation that it timely submitted change order requests is entirely consistent with its allegation that, due to AECOM's failure to resolve those requests, JH Kelly subsequently abandoned the Subcontract's change order process and completed the work despite the lack of payment. See SAC ¶¶ 77-78.

Nor is it inconsistent for JH Kelly to maintain that it both ultimately abandoned the change order process and complied with its obligations under the Subcontract to ensure that the project was completed. Id. California courts have made clear that even when a construction contract is 8 deemed abandoned, the contractor may properly opt to complete the work and recover in quantum meruit afterwards. Peterson, 172 Cal.App.3d at 640; see also Daugherty Co. v. Kimberly-Clark Corp., 14 Cal.App.3d 151, 156-57, 92 Cal.Rptr. 120, 123 (1971) (“Performing the work prescribed by the contract and the changes does not preclude the possibility that the labor and materials furnished were outside the contemplation of the parties when the bid was made and the contract signed.”). Under these circumstances, the terms of the written contract are deemed abandoned, but the work is not. Peterson, 172 Cal.App.3d at 640. JH Kelly's SAC advances this theory and therefore plausibly alleges that JH Kelly abandoned the Subcontract's change order process. See SAC ¶¶ 77-78.

Because the SAC plausibly alleges that both parties ultimately failed to follow the Subcontract's change order process, and that the final project is “materially different” from the terms of the original contract, the Court finds that JH Kelly has plausibly stated a quantum meruit abandonment claim and DENIES AECOM's motion to dismiss as to that claim.

C. Quantum Meruit/Reasonable Value

Finally, AECOM contends that JH Kelly's Eighth Claim for Quantum Meruit for Reasonable Value should be dismissed because it is unavailable as a matter of law where, as here, a valid agreement exists between the parties. See Mot. at 12. The Court agrees.

Quantum meruit is an equitable theory which supplies, by implication and in furtherance of equity, “implicitly missing contractual terms.” Hedging Concepts, Inc. v. First All. Mortg. Co., 41 Cal.App.4th 1410, 1419, 49 Cal.Rptr.2d 191 (1996). But contractual terms are not “implicitly missing” when the parties have agreed on express terms regarding that subject. Id. Put differently, “[a] quantum meruit analysis cannot supply ‘missing' terms that are not missing.” Id. It is therefore “well settled” that there is “no equitable basis for an implied-in-law promise to pay reasonable value when the parties have an actual agreement covering compensation.” Id.; see also Mosier v. Stonefield Josephson, Inc., 815 F.3d 1161, 1172 (9th Cir. 2001) (“[A]s a matter of law, a quasi-contract action for unjust enrichment does not lie where . . . express binding agreements exist and define the parties' rights.”) (quoting Cal. Med. Ass'n, Inc. v. Aetna U.S. Healthcare of Cal., Inc., 94 Cal.App.4th 151, 172 (2001)). 9

AECOM contends that because the Subcontract specifically contains provisions under which JH Kelly can seek additional compensation for additional work, changed work, and resulting damages, JH Kelly's claim to seek such compensation through quasi-contract fails to state a claim upon which relief can be granted. See Mot. at 13. In response, JH Kelly points to California case law holding that a party “can pursue and even recover on both claims for breach of contract and for quantum meruit on an abandonment theory.” Opp. at 16 (emphasis added).

That is true, but irrelevant. JH Kelly's claim for quantum meruit based on an abandonment theory is its sixth cause of action. SAC ¶¶ 72-78. JH Kelly's rebuttal does not address AECOM's argument that JH Kelly cannot maintain its eighth cause of action, which is a claim for quantum meruit for reasonable value. Id. ¶¶ 83-85.

See Amelco Elec., 27 Cal.4th at 237 (“[W]e conclude the trial court could properly find both a breach of the contract and a subsequent abandonment of the contract brought about by the breach.”).

The Court agrees with AECOM that the Subcontract governs JH Kelly's claims for compensation against AECOM. See, e.g., SAC ¶¶ 25, 33, 39, 44. And while California law authorizes quantum meruit despite the existence of an applicable contractual provision when the underlying contract was procured by fraud or is otherwise unenforceable, ineffective, or expired, see McBride v. Boughton, 123 Cal.App.4th 379, 388, 20 Cal.Rptr.3d 115, 121-22 (2004); Lectrodryer v. SeoulBank, 77 Cal.App.4th 723, 726, 91 Cal.Rptr.2d 881, 883 (2000), the SAC does not allege that any of those exceptions apply here. See SAC ¶¶ 83-85. Accordingly, the Court GRANTS AECOM's motion to dismiss as to JH Kelly's Eighth Claim for Quantum Meruit for Reasonable Value.

IV. CONCLUSION

The Court GRANTS IN PART and DENIES IN PART AECOM's motion to dismiss JH Kelly's SAC. Specifically, the motion is granted as to JH Kelly's Fifth Claim for Breach of the Implied Covenant of Good Faith and Fair Dealing and Eighth Claim for Quantum Meruit/Reasonable Value. The Court will address whether JH Kelly will be given leave to amend these claims at the Pretrial Conference. The motion is denied as to JH Kelly's Sixth Claim for 10 Quantum Meruit for Abandonment of Contract.

IT IS SO ORDERED. 11


Summaries of

JH Kelly, LLC v. AECOM Tech. Servs.

United States District Court, Northern District of California
Jan 21, 2022
20-cv-05381-HSG (N.D. Cal. Jan. 21, 2022)
Case details for

JH Kelly, LLC v. AECOM Tech. Servs.

Case Details

Full title:JH KELLY, LLC, Plaintiff, v. AECOM TECHNICAL SERVICES, INC.., et al.…

Court:United States District Court, Northern District of California

Date published: Jan 21, 2022

Citations

20-cv-05381-HSG (N.D. Cal. Jan. 21, 2022)

Citing Cases

KJ-Park, LLC v. Match Grp.

“[S]everal federal district courts have read Guz to allow simultaneous breach of contract and implied…

HotSpot Therapeutics, Inc. v. Nurix Therapeutics, Inc.

Shaterian v. Wells Fargo Bank, N.A., 829 F.Supp.2d 873, 884 (N.D. Cal. 2011). See also JH Kelly, LLC v. AECOM…