Innovation Assocs., Inc. v. Filbin Painting, Inc.

Supreme Court, Appellate Division, Third Department, New York.
Dec 20, 2018
167 A.D.3d 1291 (N.Y. App. Div. 2018)

Opinion

526279

12-20-2018

INNOVATION ASSOCIATES, INC., Respondent, v. FILBIN PAINTING, INC., Appellant. (And a Third–Party Action.)

Pope, Schrader & Pope, LLP, Binghamton (Alan J. Pope of counsel), for appellant. Law Offices of Theresa J. Puleo, Syracuse (Michelle M. Davoli of counsel), for respondent.


Pope, Schrader & Pope, LLP, Binghamton (Alan J. Pope of counsel), for appellant.

Law Offices of Theresa J. Puleo, Syracuse (Michelle M. Davoli of counsel), for respondent.

Before: McCarthy, J.P., Lynch, Clark, Mulvey and Rumsey, JJ.

MEMORANDUM AND ORDER

Clark, J.Appeal from an order of the Supreme Court (Lebous, J.), entered October 23, 2017 in Broome County, which, among other things, granted plaintiff's motion for partial summary judgment on the issue of liability.

In early 2012, plaintiff and third-party defendant BAE Systems separately leased and occupied commercial space in a large, single-floor building on the Huron Campus in the Village of Endicott, Broome County. Plaintiff's space, situated in the northwest quadrant of the building, was separated from the remainder of the building by a wall that ran from the floor to the ceiling along the southern border of its space and another wall that ran along the eastern side of its space, but which did not fully extend to the ceiling. BAE Systems leased the remaining portion of the building and, at some point, sought to renovate its space. To that end, BAE Systems hired third-party defendant PJF Enterprises, Inc. as the general contractor of the project, and PJF thereafter subcontracted with defendant to provide painting services.

In the overnight hours of April 26, 2012 into April 27, 2012, defendant's employees painted the ceiling in the southeast quadrant of the building using dry fog paint – a type of paint that is applied with an airless paint sprayer and which is specifically designed so that any excess paint falls several feet from the wall and turns into powder for easy cleanup. Several hours after defendant's employees finished painting the ceiling, plaintiff discovered paint particles inside its space, which it used to design and develop automated dispensing systems for drug dispensing. As a result, plaintiff commenced this negligence action against defendant seeking to recover for, among other things, damage caused to its property by the paint particles. Defendant answered and, thereafter, commenced a third-party action against BAE Systems and PJF Enterprises, which, in turn, answered and asserted counterclaims against defendant. Following discovery, plaintiff moved for partial summary judgment on the issue of liability, and defendant cross-moved for summary judgment dismissing the complaint as a matter of law. Supreme Court granted plaintiff's motion and denied defendant's cross motion, prompting this appeal by defendant.

Defendant also named Huron Real Estate Associates, LLC as a third-party defendant. However, by stipulation, the third-party action against Huron has been discontinued.

BAE Systems also asserted a cross claim against PJF Enterprises.
--------

"[O]rdinarily, breach of a contractual obligation will not be sufficient in and of itself to impose tort liability to noncontracting third parties upon the promisor" ( Church v. Callanan Indus., 99 N.Y.2d 104, 111, 752 N.Y.S.2d 254, 782 N.E.2d 50 [2002] ; see Espinal v. Melville Snow Contrs., 98 N.Y.2d 136, 138, 746 N.Y.S.2d 120, 773 N.E.2d 485 [2002] ; Kelley v. Schneck, 106 A.D.3d 1175, 1179, 964 N.Y.S.2d 301 [2013], lv dismissed 21 N.Y.3d 1069, 974 N.Y.S.2d 315, 997 N.E.2d 140 [2013] ). However, as relevant here, "a party who enters into a contract to render services may be said to have assumed a duty of care – and thus be potentially liable in tort – to third persons ... where the contracting party, in failing to exercise reasonable care in the performance of [its] duties, launches a force or instrument of harm" ( Espinal v. Melville Snow Contractors, Inc., 98 N.Y.2d at 140, 746 N.Y.S.2d 120, 773 N.E.2d 485 [internal quotation marks, brackets and citation omitted]; see Stiver v. Good & Fair Carting & Moving, Inc., 9 N.Y.3d 253, 257, 848 N.Y.S.2d 585, 878 N.E.2d 1001 [2007] ; Church v. Callanan Indus., 99 N.Y.2d at 111, 752 N.Y.S.2d 254, 782 N.E.2d 50 ).

Contrary to Supreme Court's conclusion, plaintiff's submissions – which included defendant's subcontract with PJF and deposition testimony from, among others, defendant's and PJF's principals and employees – failed to demonstrate its prima facie entitlement to summary judgment on the issue of liability (see Billera v. Merritt Constr., Inc., 139 A.D.3d 52, 59, 29 N.Y.S.3d 562 [2016] ). The deposition testimony did not establish the exact manner in which the paint particles migrated from the southeast quadrant of the building, where defendant was painting, to the northwest quadrant of the building, where plaintiff operated its business. Plaintiff's submissions provided some evidence to support its theory that the paint particles traveled into its space due to the absence of sealed floor-to-ceiling barriers separating the southeast and northeast quadrants and the northeast and northwest quadrants, as well as the operation of the HVAC system, which had not been covered or turned off prior to the painting. However, conflicting deposition testimony, together with the subcontract, raised numerous triable issues of fact as to, among other things, the scope of defendant's and PJF's respective duties and responsibilities under the subcontract and prevailing industry standards (see generally Hahn v. Tops Mkts., LLC, 94 A.D.3d 1546, 1547–1548, 943 N.Y.S.2d 361 [2012] ), particularly given the evidence that the dry fog paint process required a positive air flow, that there were no HVAC ducts in the area that was painted on the dates in question and that the HVAC system was in the process of being deconstructed and removed. In short, questions of fact persisted as to whether defendant failed to exercise reasonable care in the performance of its painting duties and, if so, whether such failure caused the paint particles – the force or instrument of harm alleged here – to enter plaintiff's space (see Karydas v. Ferrara–Ruurds, 142 A.D.3d 771, 772, 37 N.Y.S.3d 16 [2016] ; Billera v. Merritt Constr., Inc., 139 A.D.3d at 59, 29 N.Y.S.3d 562 ; Greater N.Y. Mut. Ins. Co. v. ERE LLP, 125 A.D.3d 417, 418, 3 N.Y.S.3d 19 [2015] ; Wade v. Bovis Lend Lease LMB, Inc., 102 A.D.3d 476, 477, 958 N.Y.S.2d 344 [2013] ; Grady v. Hoffman, 63 A.D.3d 1266, 1267, 879 N.Y.S.2d 837 [2009] ). Accordingly, Supreme Court erred in granting plaintiff's motion for partial summary judgment on the issue of liability and, for the same reasons, defendant was not entitled to summary judgment dismissing the complaint.

McCarthy, J.P., Lynch, Mulvey and Rumsey, JJ., concur.

ORDERED that the order is modified, on the law, without costs, by reversing so much thereof as granted plaintiff's motion for partial summary judgment on the issue of liability; said motion denied; and, as so modified, affirmed.


Summaries of

Innovation Assocs., Inc. v. Filbin Painting, Inc.

Supreme Court, Appellate Division, Third Department, New York.
Dec 20, 2018
167 A.D.3d 1291 (N.Y. App. Div. 2018)
Case details for

Innovation Assocs., Inc. v. Filbin Painting, Inc.

Case Details

Full title:INNOVATION ASSOCIATES, INC., Respondent, v. FILBIN PAINTING, INC.…

Court:Supreme Court, Appellate Division, Third Department, New York.

Date published: Dec 20, 2018

Citations

167 A.D.3d 1291 (N.Y. App. Div. 2018)
90 N.Y.S.3d 344
2018 N.Y. Slip Op. 8730

Citing Cases

Morales v. Digesare Mech., Inc.

A contracting party generally does not owe a duty of care to a noncontracting third party (seeStiver v. Good…

Cribbs v. Corp. Woods 11 Co., L.P.

The Court of Appeals has recognized three exceptions to this general rule: "(1) where the contracting party,…