From Casetext: Smarter Legal Research

Harlem Suites Llc v. 231 Norman Ave. Llc

Supreme Court, Appellate Division, First Department, New York.
Oct 18, 2011
88 A.D.3d 532 (N.Y. App. Div. 2011)

Opinion

2011-10-18

HARLEM SUITES, LLC, Plaintiff–Respondent,v.231 NORMAN AVE., LLC, et al., Defendants–Appellants.

Law Offices of Annette G. Hasapidis, South Salem (Annette G. Hasapidis of counsel), for appellants.Cole, Schotz, Meisel, Forman & Leonard, P.A., New York (Jed M. Weiss of counsel), for respondent.


Law Offices of Annette G. Hasapidis, South Salem (Annette G. Hasapidis of counsel), for appellants.Cole, Schotz, Meisel, Forman & Leonard, P.A., New York (Jed M. Weiss of counsel), for respondent.

Order, Supreme Court, New York County (Joan A. Madden, J.), entered July 16, 2010, which, insofar as appealed from as limited by the briefs, granted plaintiff's cross motion for summary judgment, unanimously modified, on the law, to deny summary judgment as against defendant DCI

USA, Inc. (DCIU), and otherwise affirmed, without costs.

All defendants except DCIU guaranteed that plaintiff would be repaid $1,750,000 plus interest no later than March 4, 2009. Their argument that two agreements entered into in September 2007 (the Refinancing Agreements) constituted a novation of the 2005 operating agreement, construction agreement, and guaranty (the Original Agreements) is without merit ( see Water St. Dev. Corp. v. City of New York, 220 A.D.2d 289, 290, 632 N.Y.S.2d 544 [1995], lv. denied 88 N.Y.2d 809, 647 N.Y.S.2d 714, 670 N.E.2d 1346 [1996] ). Far from expressing an intent to supersede the Original Agreements, one of the Refinancing Agreements states, “[A]ll of the obligations and guarantees currently existing between the parties undersigned shall continue after the refinance with North Fork Bank per the terms of the operative agreements ... Specifically, the guarantee of [plaintiff's] equity investment and the indemnifications for the loans remain in place per the Construction Agreement and the Personal Guarantees.”

Defendants' argument that there was an oral agreement to relieve them of their guarantees is also unavailing. The supposed partial performance was not “unequivocally referable to the modification” ( Rose v. Spa Realty Assoc., 42 N.Y.2d 338, 341, 397 N.Y.S.2d 922, 366 N.E.2d 1279 [1977] ), and the conduct relied upon to establish estoppel was compatible with the Original Agreements ( id. at 344, 397 N.Y.S.2d 922, 366 N.E.2d 1279).

Defendants' reliance on the original complaint is misplaced, since the amended complaint superseded the original complaint ( see Thompson v. Cooper, 24 A.D.3d 203, 205, 24 A.D.3d 203, 806 N.Y.S.2d 32 [2005] ). In any event, the original complaint said nothing about extinguishing defendants' guarantees.

Since there is no evidence in the record that DCIU gave a guarantee, and since plaintiff neither requested summary judgment against it nor explained why it was liable, we deny summary judgment as against DCIU.


Summaries of

Harlem Suites Llc v. 231 Norman Ave. Llc

Supreme Court, Appellate Division, First Department, New York.
Oct 18, 2011
88 A.D.3d 532 (N.Y. App. Div. 2011)
Case details for

Harlem Suites Llc v. 231 Norman Ave. Llc

Case Details

Full title:HARLEM SUITES, LLC, Plaintiff–Respondent,v.231 NORMAN AVE., LLC, et al.…

Court:Supreme Court, Appellate Division, First Department, New York.

Date published: Oct 18, 2011

Citations

88 A.D.3d 532 (N.Y. App. Div. 2011)
88 A.D.3d 532
2011 N.Y. Slip Op. 7273

Citing Cases

PJ Hanley's Corp. v. Esposito

Although this provision requires a writing, partial performance by the parties which is unequivocally…

Nat'l Cmty. Reinvestment Coal. v. Micro Office Mgmt.

The stipulation's operative terms clearly and unambiguously continued the sublease in full effect except as…