Opinion
CIVIL NO. 1:17cv54-HSO-JCG
02-02-2018
FINAL JUDGMENT
This matter came on to be heard upon the Motion [5] to Compel Arbitration and to Stay Proceedings filed by Defendant McClain Contracting Company, Inc. The Court, after a full review and consideration of the pleadings on file, the record as a whole, and relevant legal authority, finds that in accord with its Memorandum Opinion and Order entered this date,
IT IS, THEREFORE, ORDERED AND ADJUDGED, that Plaintiff Hancock Mechanical, LLC, must submit its claims to arbitration, and this civil action is DISMISSED.
SO ORDERED AND ADJUDGED, this the 2nd day of February, 2017.
/s/_________
HALIL SULEYMAN OZERDEN