Hallmon v. C. Raymond Davis Sons, Inc.

Superior Court of Delaware for New Castle County
Mar 30, 2006
C.A. No. 02C-05-317 MJB (Del. Super. Ct. Mar. 30, 2006)

Opinion

C.A. No. 02C-05-317 MJB.

Submitted: March 17, 2006.

Decided: March 30, 2006.

On Motion for Summary Judgment by Defendant Shelly's Building Supply, Inc., DENIED.

Mark L. Reardon, Esquire, Elzufon, Austin, Reardon, Tarlov Mondell, P.A., Wilmington, Delaware, Attorney for Defendant Shelly's Building Supply, Inc.

Brian E. Lutness, Esquire, Silverman, McDonald Friedman, Wilmington, Delaware, Attorney for Third Party Defendant Brescia Construction, Inc.


OPINION AND ORDER


Procedural History

This is a Motion for Summary Judgment, or in the alternative, a Motion In Limine to exclude expert testimony filed by Defendant Shelly's Building Supply, Inc. ("Shelly's) against Third Party Defendant Brescia Construction, Inc. ("Brescia"). Two actions arising from the incident in this case were filed. Both were consolidated into the current action before the Court.

Facts

The instant dispute arises from a construction incident occurring at what is now known as the Brandywine Baptist Church on Mount Lebanon Road in Wilmington, Delaware on August 29, 2000. At the time of the incident, Brescia Construction, Inc. was working as a subcontractor to the general contractor C. Raymond Davis Sons ("C. Raymond"). Brescia rented a crane and an operator (Robert Wyatt) from Summit to lift roof trusses to their proper position before being secured by Brescia employees to the truss bracing.

Following the bracing of nearly all the roof trusses, Brescia determined that one of the roof trusses was in the wrong position and had to be moved. The crane was hooked to one of the trusses and the bracing on the truss was removed. At this point many of the trusses collapsed, injuring Daniel Paylor and Steve Hallmon. Daniel Paylor sustained severe injuries as a result. Mr. Paylor died days later in the hospital. Steve $$$$Hallmon was also injured in the incident and the cases have been consolidated for that reason.

Defendant Shelly's has filed the instant Motion for Summary Judgment/Motion In Limine against Third Party Defendant Brescia alleging insufficient facts in the record to proceed against Shelly's and insufficiencies of Brescia's expert opinion.

Standard of Review

The standard for granting summary judgment is high. Summary judgment may be granted where the record shows that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law. "In determining whether there is a genuine issue of material fact, the evidence must be viewed in a light most favorable to the non-moving party." When taking all of the facts in a light most favorable to the non-moving party, if there remains a genuine issue of material fact requiring trial, summary judgment may not be granted. Applicable Law Motion In Limine

Mumford Miller Concrete, Inc. v. Burns, 682 A.2d 627 (Del. 1996).

Super.Ct.Civ.R. 56(c).

Muggleworth v. Fierro, 877 A.2d 81, 83-84 (Del.Super.Ct. 2005).

Gutridge v. Iffland, 889 A.2d 283 (Del. 2005).

Shelly's argues that if the Motion for Summary Judgment is denied, the expert report should be excluded under a motion in limine mechanism. Shelly's argues the expert report lacks the proper methodology, has no factual basis, and establishes no proximate cause that could be attributed to Shelly's.

Brescia argues the Motion In Limine is without merit and premature. In addition, Shelly's has not served expert interrogatories for Mr. Haglid or issued a notice for his deposition.

The Court agrees with Brescia that the Motion In Limine is premature. The Haglid report was produced on November 4, 2005, before the deadline set in the applicable case scheduling order. The scheduling order for this litigation sets the deadline for expert depositions at May 19, 2006. Time remains to explore the opinions of Mr. Haglid and if his testimony is not sufficient at that time, a Motion In Limine may be appropriate. Granting a Motion In Limine based only on Mr. Haglid's preliminary report when the time to take his deposition has not expired is premature.

There was some confusion at the hearing on these motions regarding which case scheduling order currently applied to this case. It was agreed by all parties present that the October 27, 2005 order issued by Judge Slights is the effective order.

At oral argument Counsel for Shelly's agreed the May 19, 2006 date in the current case scheduling order governs the deadline for expert depositions.

Motion for Summary Judgment

Shelly's first argues that it is entitled to summary judgment because Brescia's claim against it is premised on an expert's theory that has no factual basis in the record. Brescia supplied Shelly's with an expert report of a professional engineer; Mr. Klaus Haglid. The report cites knots and moisture level of the trusses Shelly's supplied as contributing factors in the collapse. Shelly's argues the expert report is not based on any reliable methodology, or compared to industry standards and amounts to a conclusory and speculative report that may not be admitted into evidence to preclude summary judgment.

Brescia counters by stating there is a material issue of fact for jury determination because the expert report of Klaus Haglid is based on observations made when he went to the site the day after the incident, at which time he observed the trusses and took several pictures to support his findings. Brescia argues these observations make the Haglid report neither speculative nor conclusory.

The issues here are analogous to the recent Superior Court decision in Kennedy v. Invacare Corp. In Kennedy, the defendant made a motion for summary judgment based on the speculative nature of the plaintiff expert's preliminary report. The liability issue in the case dealt with an injury that was sustained due to an alleged defect in a motor operated bed. The plaintiff expert reviewed a medical report, rental documentation and photographs of the bed after the malfunction. The expert report established that absent negligence of the defendants, the injury would not have taken place and the conclusions were "within a reasonable degree of engineering probability." Based on this factual review, the Court found the report was not based on "subjective belief or speculation."

2005 WL 2249564 (Del.Super.Ct.)

Id.

Id. at *3.

Id. citing Price v. Blood Bank of Del., 790 A.2d 1203, 1210 (Del. 2002).

The expert report issued by Mr. Haglid for Brescia states that he reviewed manufacturer's specifications for the trusses, manufacturer's drawings, photographs, wood guide for characteristics with moisture, ASTM Standard, D9-87, "Standard Terminology Relating to wood," effect of temperature on Mode 1 fracture toughness of graphite/epoxy composites, diagrams and field notes. In addition, Mr. Haglid went to the site the day after the incident to observe the trusses in person. Based on these facts, Mr. Haglid came to the conclusion that, "to a reasonable degree of engineering probability," the material condition of the truss member in question caused the incident, the material condition or defect of the wood truss member was visually apparent, and the defect could have been found and the incident avoided.

Defendant Shelly's Building Supply Motion for Summary Judgment/Motion In Limine Against Brescia Construction, exhibit B ( Klaus Haglid Expert Report) at 3.

The full findings of the expert report of Klaus Haglid read:

1. To a reasonable degree of engineering probability, the wood trusses were very wet and the moisture made the trusses weaker and more flexible.
2. To a reasonable degree of engineering probability, the material defect of the three knots concentrated at one point made the scissor truss very weak.
3. To a reasonable degree of engineering probability, the material condition of the truss member in question caused this accident.
4. To a reasonable degree of engineering probability, the material condition or defect of the wood truss member was visually apparent.
5. To a reasonable degree of engineering certainty, with a reasonably careful visual inspection of the wooden truss member, this defect could have been found and the accident avoided.

Brescia further claims that a conclusion by Plaintiff Paylor's expert that Shelly's failure to put warning labels was a contributing causal factor in the incident also creates an issue of fact for jury determination. The expert report of Plaintiff Paylor makes reference to a possible issue of negligence on Shelly's behalf. The report of Steven A. Estrin states in section 7.10 that a contributing factor in the incident was "Shelly's failure to staple the TPI Instruction for Continuous Lateral Bracing being required to the top cord of each truss contributed to the truss collapse and Mr. Paylor's fall to fatal injury."

Third-Party Defendant Brescia Construction Opposition to Motion for Summary Judgment/Motion In Limine, exhibit C ( Expert Report of Steven A. Estrin) at 4.

At oral argument, counsel for Shelly's focused on the reference in the Haglid expert report to an unidentified witness as an impermissible basis for the conclusions in the report. This argument would have force if Mr. Haglid did not observe the site himself and based his report solely on the representations of the unnamed witness, but that is not the case. Even without the reference to the unnamed witness representations, the expert report withstands scrutiny because it is based on the personal observations of Mr. Haglid.

The expert reports issued by Mr. Haglid and Mr. Estrin, timely presented to opposing parties, create issues of fact for the jury regarding Shelly's liability. The Haglid report is based on personal observations and opined within a reasonable degree of engineering probability. Mr. Eskin's conclusions similarly create issues of material fact that remain to be decided. Taking the facts in the light most favorable to the nonmoving party, these issues of material fact are appropriate for jury determination, thereby precluding summary judgment.

Conclusion

For the reasons set forth herein the Motion In Limine is DENIED and the Motion for Summary Judgment of Defendant Shelly's Building Supply, Inc. is hereby DENIED. Both Motions are DENIED without prejudice.

IT IS SO ORDERED.


Summaries of

Hallmon v. C. Raymond Davis Sons, Inc.

Superior Court of Delaware for New Castle County
Mar 30, 2006
C.A. No. 02C-05-317 MJB (Del. Super. Ct. Mar. 30, 2006)
Case details for

Hallmon v. C. Raymond Davis Sons, Inc.

Case Details

Full title:STEVE HALLMON, Plaintiff, v. C. RAYMOND DAVIS SONS, INC. Defendant. MARY…

Court:Superior Court of Delaware for New Castle County

Date published: Mar 30, 2006

Citations

C.A. No. 02C-05-317 MJB (Del. Super. Ct. Mar. 30, 2006)