Opinion
Case No. 4:17CV02812 AGF
09-06-2018
MEMORANDUM AND ORDER
This matter is before the Court on Plaintiffs' motion for default judgment (ECF No. 11) against Defendant AbatePro, Inc. Plaintiffs are the union and trustees of various employee benefit plans. Plaintiffs filed this action to recover delinquent contributions and liquidated damages owed to them under the Employee Retirement Income Security Act, 29 U.S.C. §§ 185 & 1132.
Clerk's Entry of Default was entered against Defendant July 20, 2018. ECF No. 9. Plaintiffs seek judgment against Defendant in the amounts of $99,848.07 for delinquent contributions, $8,964.31 for supplemental dues, $47.418.53 for liquidated damages, $8,719.16 for interest, $1,590 for payroll examination fees, $1,353.50 for attorney fees, and $776.88 for costs, for a total of $168,670.45. Plaintiffs have provided affidavits and exhibits supporting these amounts. ECF Nos. 11-1-10, 18-1-3.
Plaintiffs originally sought $10,455.67 in interest, of which $10,033.63 was for residential work. Plaintiffs subsequently revised the residential portion to $8,267.12. ECF No. 18 --------
"Where default has been entered, the allegations of the complaint, except as to the amount of damages are taken as true." Carpenters' Dist. Council of Greater St. Louis and Vicinity v. Hard Rock Foundations, LLC, No. 4:13CV01549 AGF, 2013 WL 6037097, at *2 (E.D. Mo. Nov. 14, 2013) (citation omitted). "In determining the amount of damages for a default judgment in an ERISA case brought by a plan against an employer, the court may rely on detailed affidavits or documentary evidence to determine the appropriate sum for the default judgment." Painters Dist. Council 2 v. Grau Contracting, Inc., No. 4:10CV02339 AGF, 2012 WL 2848708, at *1 (E.D. Mo. July 11, 2012) (internal quotation omitted). A plaintiff is entitled to recover all of the principal contributions owed pursuant to the payroll examination, plus liquidated damages totaling twenty percent of the delinquency, interest, attorneys' fees, and costs. See 29 U.S.C. § 1132(g)(2)(E). Damages must be proven by a preponderance of the evidence. See Iron Workers St. Louis Dist. v. Arrow Fence, Inc., No. 4:11CV02019 AGF, 2013 WL 991658, at *2 (E.D. Mo. Mar. 13, 2013).
Upon review of the record, the Court finds that Plaintiffs have provided sufficient evidence to support their motion.
Accordingly,
IT IS HEREBY ORDERED that Plaintiffs' motion for default judgment is GRANTED. ECF No. 11. A Judgment against Defendant in the amount of $168,670.45 shall accompany this Memorandum and Order.
/s/_________
AUDREY G. FLEISSIG
UNITED STATES DISTRICT JUDGE Dated this 6th day of September, 2018.