Opinion
4:21-cv-03220-HSG
12-22-2021
GOOGLE LLC, Plaintiff, v. ECOFACTOR, INC., Defendant.
ORDER TO JOINT STIPULATION TO MODIFY SCHEDULING ORDER
HAYWOOD S. GILLIAM, JR. UNITED STATES DISTRICT JUDGE
PURSUANT TO STIPULATION, IT IS SO ORDERED.
There being a showing of good cause based on the parties' stipulation, the Court hereby moves the dates for the Joint Claim Construction and Prehearing Statement to January 14, 2022, the Responsive Damages Contentions to January 17, 2022, and that the Completion of Claim Construction Discovery to January 21, 2022 and hereby moves the date for EcoFactor's Response to Google's Motion for Judgment on the Pleadings to January 12, 2022, and Google's Reply to January 19, 2022.