Opinion

No. 8225.

Argued January 18, 1961.

Decided January 20, 1961.

J. Means McFadden, Columbia, S.C. (Robinson, McFadden Moore, Columbia, S.C., on the brief), for appellant.

Philip C. Herr, Philadelphia, Pa. (Tison Tison, Hartsville, S.C., on the brief), for appellee.

Before SOBELOFF, Chief Judge, and SOPER and HAYNSWORTH, Circuit Judges.


In this case, an owner of a building and the contractor who built it assert multiple cross-claims. Previously, the owner appealed to this Court from an order denying a motion to require arbitration of the claims. The appeal was dismissed as being premature, but reference was made in the opinion of this Court to documents and evidence tendered in this Court which had not been submitted to the District Judge. The case was remanded with leave to supplement the record in the District Court, which could then enter such further order, or orders, as appeared appropriate.

Hering Realty Company v. General Construction Co., 272 F.2d 371.

After the remand, the record was expanded and, thereafter, the District Court entered an order requiring submission of certain claims to arbitration under the provisions of the construction contract but refusing to refer other claims to arbitration. In this order, a number of claims were described as being "valid" or "invalid," the language used in the construction contract in connection with the arbitration of claims and the finality of rulings of the engineer-architect. On this appeal, the contractor complains that the order amounts to a summary judgment as to those claims described as being "valid" or "invalid."

We do not so construe the order. The only motion before the District Court was one requiring the arbitration of all of the cross-claims. Referring to the contract, the Court decided that certain of the claims should be arbitrated, while others should not be arbitrated, but there is nothing in the order, itself, which suggests that the Court intended its order to be a final adjudication of any of the claims, or that it should in any way foreclose any defense to any claim which has been set up by the pleadings, or which may hereafter be properly raised.

As we construe it, the order does no more than refer certain claims to arbitration while staying proceedings in the District Court until the arbitration proceeding shall have been completed. As such, the order is purely interlocutory and is not appealable.

Appeal dismissed.


Summaries of

General Construction Co. v. Hering Realty Co.

United States Court of Appeals, Fourth Circuit
Jan 20, 1961
286 F.2d 641 (4th Cir. 1961)
Case details for

General Construction Co. v. Hering Realty Co.

Case Details

Full title:GENERAL CONSTRUCTION COMPANY, Columbia, South Carolina, a corporation…

Court:United States Court of Appeals, Fourth Circuit

Date published: Jan 20, 1961

Citations

286 F.2d 641 (4th Cir. 1961)

Citing Cases

General Construction Co. v. Hering Realty Co.

Apparently, the contractor thought that certain language in Judge Williams' Order might be construed as…

Woodward v. Reliance Inc.

All federal courts of appeal but one have followed this rationale.Zosky v. Boyer, 856 F.2d 554, 557-60 (3d…