Freda Green Associates, Inc. v. Heydt

Appellate Division of the Supreme Court of New York, First Department
Nov 29, 1990
167 A.D.2d 328 (N.Y. App. Div. 1990)

Summary

rejecting plaintiff's claim that New York General Construction Law § 25 extended the expiration date of the parties' contract because it "fell on a Sunday" and stating that the agreement "required no `payment of money' or `performance of a condition' warranting such an extension of time"

Summary of this case from J.P.T. Automotive, Inc. v. Toyota Motor Sales, U.S.A.

Opinion

November 29, 1990

Appeal from the Supreme Court, New York County (Myriam Altman, J.).


Plaintiff, a licensed real estate broker, was granted "exclusive and irrevocable right and authority" to sell the defendant's cooperative apartment until expiration of the parties' written agreement on April 30, 1989. Defendant entered into a contract for the sale of the property on May 1, 1989, one day after the expiration of the brokerage agreement, with purchasers he had himself procured. Despite the fact that the plaintiff admittedly had nothing whatsoever to do with the sale of the subject premises, plaintiff claims an entitlement to a commission based upon plaintiff's interpretation of General Construction Law § 25 and the defendant's alleged bad faith under the contract.

The IAS court did not err in dismissing plaintiff's first cause of action alleging that the term of the exclusive agreement was extended to Monday, May 1, 1989 pursuant to General Construction Law § 25 merely because the expiration of the parties' agreement, April 30, 1989, fell on a Sunday. As plaintiff concedes, the agreement, which was drafted by the plaintiff, required no "payment of money" or "performance of a condition" warranting such an extension of time under General Construction Law § 25 (1) on the expiration date of the parties' agreement (see generally, Kulanski v. Celia Homes, 7 A.D.2d 1006).

Defendant was entitled to summary judgment on plaintiff's second cause of action alleging that the defendant had, in bad faith, breached the parties' agreement by secretly showing the subject premises to the ultimate purchasers thereof. Again, plaintiff concedes that the defendant negotiated in good faith with every prospective purchaser procured by the plaintiff and in no way interfered with the plaintiff's attempts to perform under the agreement prior to the expiration thereof. Thus, in the absence of an agreement to the contrary and fraud or bad faith on the part of the seller, the broker was not entitled to a commission on a sale negotiated after the term of its employment. (Bashant v. Spinella, 67 A.D.2d 1100.)

Concur — Kupferman, J.P., Carro, Kassal, Ellerin and Smith, JJ.


Summaries of

Freda Green Associates, Inc. v. Heydt

Appellate Division of the Supreme Court of New York, First Department
Nov 29, 1990
167 A.D.2d 328 (N.Y. App. Div. 1990)

rejecting plaintiff's claim that New York General Construction Law § 25 extended the expiration date of the parties' contract because it "fell on a Sunday" and stating that the agreement "required no `payment of money' or `performance of a condition' warranting such an extension of time"

Summary of this case from J.P.T. Automotive, Inc. v. Toyota Motor Sales, U.S.A.
Case details for

Freda Green Associates, Inc. v. Heydt

Case Details

Full title:FREDA GREEN ASSOCIATES, INC., Appellant, v. MARK HEYDT, Individually and…

Court:Appellate Division of the Supreme Court of New York, First Department

Date published: Nov 29, 1990

Citations

167 A.D.2d 328 (N.Y. App. Div. 1990)
562 N.Y.S.2d 79

Citing Cases

J.P.T. Automotive, Inc. v. Toyota Motor Sales, U.S.A.

The fact that the date chosen happened to fall on a holiday does not extend the effective date of the…

J.P.T. Automotive, Inc. v. Toyota Motor Sales, U.S.A.

The fact that the date chosen happened to fall on a holiday does not extend the effective date of the…