From Casetext: Smarter Legal Research

Fodera Enterprises v. State

Appellate Division of the Supreme Court of New York, Second Department
Oct 11, 2000
275 A.D.2d 85 (N.Y. App. Div. 2000)

Opinion

Argued May 16, 2000

October 11, 2000.

APPEAL from so much of a judgment of the Court of Claims (Susan Phillips Read, J.), dated June 22, 1999, as, in favor of in favor of the claimant in an action to recover damages for the acquisition of real property pursuant to EDPL 501 and 701.

Eliot Spitzer, Attorney-General, New York, N.Y. (Peter H. Schiff and Michael S. Buskus of counsel), for appellant.

Goldstein, Goldstein Rikon, P.C., New York, N.Y. (Michael J. Goldstein of counsel), for respondent.

Before: DAVID S. RITTER, J.P., THOMAS R. SULLIVAN, ANITA R. FLORIO, SANDRA J. FEUERSTEIN, JJ.


OPINION ORDER


In a claim to recover damages for the acquisition of real property, we are asked to determine whether the Court of Claims erred in declining to limit the claimant's consequential damages to the "cost-to-cure" the same. On the record presented, we hold that it did not.

The claimant is the owner of real property in Queens. On February 1, 1993, the appellant, State of New York (hereinafter the State), appropriated a permanent easement on a wedge-shaped portion of the claimant's property. By judgment dated June 22, 1999, the claimant, after a nonjury trial, was awarded direct damages in the principal sum of $27,000, and consequential damages in the principal sum of $30,000, arising from the loss of parking. On appeal, the State challenges only the proper measure of the claimant's consequential damages.

The State, noting that the claimant has a duty to mitigate its damages, asserts that it presented evidence that the loss of parking could be cured by relocating an existing curb cut approximately 10 feet from its current location and reconfiguring the remaining parking area. The proposed curb cut would require a permit from the Department of Transportation of the City of New York (hereinafter the DOT). Concerning the burden of proof on the issue of the permit, the State argues that it had a "threshold obligation" of showing the "economic and engineering feasibility " of the permit, and that it met that obligation. The State also argues that the circumstances were sufficient "to raise an inference that the administrative agency might grant the permit". The State asserts that the claimant, in opposition thereto, failed to meet its burden of proffering proof "on the issue of the likelihood that such a permit would be granted". Accordingly, the State concludes, because the claimant should be limited to a cost-to-cure remedy if there is a "reasonable likelihood" that the permit would issue, this gap in the evidence must inure to the detriment of the claimant, and the claimant's damages should be limited to the State's proffered cost-to-cure.

The claimant, while acknowledging a duty to mitigate its consequential damages, argues, inter alia, that the goal of "full and perfect compensation" will be violated if a claimant is obligated to seek a permit when "there is the remotest possibility that it might not be gotten"; that is, when the entity that is to issue the permit retains even the "least amount of discretion" to deny the same. Here, the claimant argues, it presented proof that the grant or denial of a permit for a curb cut was discretionary and turned on factors both subjective and objective in nature. Thus, the claimant concludes, on the facts presented, it should not be required to seek a curb cut permit in mitigation of its consequential damages.

The Court of Claims, while finding that "sound public policy at least arguably favors the test urged by the State," believed that the decision of the Court of Appeals in Donaloio v. State of New York ( 64 N.Y.2d 811) precluded the application of that test. Accordingly, the Court of Claims awarded the claimant consequential damages in the amount of the diminution of the value of the property arising from the loss of parking. We now affirm, although for reasons different from those stated by the Court of Claims.

As correctly conceded by the claimant, consequential damages arising from a partial taking must be mitigated where possible (see, Wilmot v. State of New York, 32 N.Y.2d 164; Mayes Co. v. State of New York, 18 N.Y.2d 549). In such cases, the award of consequential damages may be limited to the cost-to-cure, provided, of course, that such amount does not exceed the diminution in the value of the property after the taking (see, Hylan Flying Serv. v. State of New York, 49 N.Y.2d 840; City of Yonkers v. State of New York, 40 N.Y.2d 408; Goldsmith v. State of New York, 26 N.Y.2d 899; Nichols and Sackman, Nichols on Eminent Domain, Bk 4A, § 14A.04[2][a] [Rev. 3rd ed.]). For example, an award of consequential damages may be limited to the cost-to-cure when it is shown that the claimant can replace parking lost to a taking by dedicating a portion of the remaining parcel to the same use (see, e.g., Martabano v. State of New York, 120 A.D.2d 712; Boyertown Burial Casket Co. v. State of New York, 38 A.D.2d 624; see also, City of Yonkers v. State of New York, supra). Thus, the issue presented on the appeal is whether an award of consequential damages may be limited to the cost-to-cure when the proposed cure requires a permit from a governmental agency. There is no controlling authority addressing this issue, or addressing what must be demonstrated concerning the permit and who bears the burden of proof with respect thereto. Although certain language in Donaloio v. State of New York (supra), the case relied upon by the Court of Claims, appears to address this issue, upon closer scrutiny, it is clear that the decision of the Court of Appeals in Donaloio rested upon an exception to the rule concerning the mitigation of damages not raised herein (see, Wolfe v. State of New York, 22 N.Y.2d 292; cf., County of Schenectady, 194 A.D.2d 1004, affd 83 N.Y.2d 756; B B Food Corp. v. State of New York, 96 A.D.2d 893; Windham v. State of New York, 34 A.D.2d 590, affd 27 N.Y.2d 481; Campbell v. State of New York, 39 A.D.2d 615, affd 32 N.Y.2d 952). However, we discern no compelling public policy or other relevant consideration that would warrant a conclusion that a claimant's recovery of damages may never be limited to the amount of the cost-to-cure when the proposed cure requires a permit. Thus, we must only determine whether the State met its threshold burden of presenting evidence as to the likelihood that the permit would be issued (see, Mayes Co. v. State of New York, 18 N.Y.2d 549; Nichols and Sackman, Nichols on Eminent Domain, Bk 4A, § 14A.04[2][a] [Rev. 3rd ed.]). We find that it did not.

The State did not present any evidence as to the criteria used to decide an application for a curb cut, or any evidence that the curb cut proposed would meet such criteria. Rather, the State merely endeavored to prove, through cross-examination of the claimant's expert, that if all of the relevant (but undisclosed) criteria were met, a permit would issue as a matter of right, a conclusion which the claimant's expert challenged. Further, the State presented no evidence that the curb cut proposed would involve work wholly within the claimant's property (see, Donaloio v. State of New York, supra; BB Food Corp. v. State of New York, supra). Indeed, the claimant's expert noted that permission for a curb cut entailed scrutiny by the DOT of the area surrounding the proposed curb cut and that the grant of a permit could be conditioned, for example, on the applicant agreeing to repair an adjacent public right of way. Moreover, the State's proposed cost-to-cure measure of damages does not appear to account for the expenses of applying for and securing the permit. In sum, there was a failure of proof, and accordingly, the Court of Claims did not err in declining to adopt the State's proposed cost-to-cure measure of the claimant's consequential damages. Therefore, the judgment is affirmed insofar as appealed from.

ORDERED that the judgment is affirmed insofar as appealed from, with costs.


Summaries of

Fodera Enterprises v. State

Appellate Division of the Supreme Court of New York, Second Department
Oct 11, 2000
275 A.D.2d 85 (N.Y. App. Div. 2000)
Case details for

Fodera Enterprises v. State

Case Details

Full title:FODERA ENTERPRISES, ETC., RESPONDENT, v. STATE OF NEW YORK, APPELLANT

Court:Appellate Division of the Supreme Court of New York, Second Department

Date published: Oct 11, 2000

Citations

275 A.D.2d 85 (N.Y. App. Div. 2000)
714 N.Y.S.2d 113

Citing Cases

J.W. Mays, Inc. v. State of New York

The engineer conceded that his design ignored numerous regulations of the New York State Department of…

J.W. Mays, Inc. v. State of New York

The engineer conceded that his design ignored numerous regulations of the New York State Department of…