From Casetext: Smarter Legal Research

Flooring Systems v. Radisson Group

Court of Appeals of Arizona, Division Two, Department A
Oct 12, 1988
158 Ariz. 111 (Ariz. Ct. App. 1988)

Opinion

No. 2 CA-CV 88-0022.

March 24, 1988. Petition for Review Granted in Part October 12, 1988.

Gordon, C.J., of the Supreme Court, did not participate in the determination of this matter.

Appeal from the Superior Court, Maricopa County, Marilyn A. Riddel, J.

Tower, Byrne Beaugureau, P.C. by David L. Beaugureau and Amy Schwartz, Phoenix, for plaintiff/appellant.

Snell Wilmer by James J. Sienicki and David W. Counce, Phoenix, for defendants/appellees.



OPINION


This is an appeal from the granting of a summary judgment involving a contract dispute between the defendants/appellees (Radisson and CSA), and the plaintiff/appellant (Flooring). We find no genuine issues of material fact and affirm the decision of the trial court.

FACTS

The parties are involved in a dispute regarding payment for carpeting installed by Flooring in a remodeling project at the Radisson Resort Hotel in Scottsdale, Arizona. CSA, the project designer, sent invitations to bid to subcontractors, including Flooring, and to general contractors, including Five Star.

After submitting a bid, Flooring was selected to do the carpet installation. After Flooring began work, Five Star was employed as the general contractor and executed a contract with CSA. Under the contract, CSA, as Radisson's agent, was to pay Five Star for subcontracted work, including that of Flooring. Appellees have conceded arguendo that a contract was formed between themselves and Flooring. After Radisson/CSA contracted with Five Star, a contract was formed between Five Star and Flooring, with Five Star as the general contractor and Flooring as the subcontractor. The subcontract specifically provided the exact contract sum and terms of payment to be made to Flooring by Five Star, and a requirement that Flooring apply for periodic payments directly to Five Star. The contract expressly incorporated the CSA/Five Star contract, specifically providing for the work to be done by Flooring. Indeed, Five Star paid Flooring the initial "deposit on contract" required in its contract with CSA. Throughout the work, Flooring submitted all payment requests to Five Star, and not to CSA.

Five Star did not pay Flooring in full, and subsequently filed for bankruptcy. Flooring is still owed approximately $25,000 of the subcontract price of approximately $59,000. CSA has paid all but $25,000 of the total contract of approximately $160,000 with Five Star. Flooring filed a breach of contract and unjust enrichment action against Radisson/CSA. Radisson/CSA obtained a summary judgment, arguing that a novation occurred, substituting the Five Star/Flooring contract for the CSA/Flooring contract.

On appeal, Flooring questions: (1) whether the trial court erred in concluding that defendants established a novation as a matter of law; (2) whether there is a triable issue of fact regarding Flooring's right to recover from Radisson/CSA under an unjust enrichment theory, and (3) whether the trial court abused its discretion in awarding attorney's fees to Radisson/CSA.

NOVATION

Flooring argues that there is conflicting evidence precluding summary judgment. It contends that the second contract between itself and Five Star merely indicates that an additional debtor, namely Five Star, has been added to the original CSA/Flooring agreement, rather than acting as a substitute for that agreement. Flooring also contends that a novation may not occur unless the same parties are involved in both contracts. We believe that argument is without legal basis.

We find that the original CSA/Flooring agreement was replaced by the subsequent Five Star/Flooring contract. Both the conduct of the parties and common practice in the construction industry would indicate that Flooring entered into a typical subcontract with a general contractor. Common practice dictates that Flooring should look to its general contractor, and not the owner (Radisson) for payment. The general contractor acts as a conduit for payment from the owner to the subcontractor. Indeed, Flooring did look to Five Star for payment from the time it received the initial deposit from Five Star and for all subsequent payment applications. This was required by the Five Star/Flooring contract.

Contrary to Flooring's belief, a novation need not occur between the same parties as those to the original agreement. "It [novation] is generally used only when the substituted contract involves at least one new party; and according to the more general practice, this new party must be a substituted obligor in place of the former obligor or debtor who is discharged." 6 A. Corbin, Corbin on Contracts, § 1297 at 213 (1962). The creditor's (Flooring) assent is usually required, and may be inferred from his conduct and the circumstances, Corbin, supra, at 214-15, as the circumstances in the present case so indicate. The Five Star/Flooring contract involved the same subject matter, contract price and work specifications as the original CSA/Flooring contract. Additionally, it provided that all payments would be made by Five Star, not CSA. An ordinary interpretation of the contract language leads to the conclusion that the Five Star/Flooring contract was meant to supercede, and not merely supplement the CSA/Flooring contract. This conclusion is irrefutable in light of the circumstances before us, and the custom and usage of subcontracts in the construction industry. In Brady v. Black Mountain Investment Co., 105 Ariz. 87, 459 P.2d 712 (1969), the Arizona Supreme Court held that the issue of novation is not always a question of the parties' intention, nor must it be express, but that it may be found by operation of law as a result of steps taken by the parties. See also Catalina Groves, Inc. v. Oliver, 73 Ariz. 38, 236 P.2d 1022 (1951). The Brady court relied upon language from an earlier supreme court case:

A contract will be considered as having been rescinded by the substitution of another and subsequent contract relating to the same subject-matter, where it appears to have been the intention of the parties, that the later contract should supersede the first one. . . . [citations omitted] Where the entire subject-matter is covered, and there is nothing on the face of the second agreement to show that it is intended to be supplemental to the original agreement, it supersedes and rescinds the original, not as a question of intention, but by operation of law, as a result of steps taken by the parties. . . .

Arizona-Parral Mining Co. v. Forbes, 16 Ariz. 395, 406, 146 P. 504, 508 (1915), quoting Redding v. Vogt, 140 N.C. 562, 567, 6 Ann. Cas. 312, 313, 53 S.E. 337, 338 (1906).

UNJUST ENRICHMENT ISSUE

Flooring further argues that Radisson has been unjustly enriched by the retention of approximately $25,000 of the funds owed to Five Star. We disagree. First, Flooring's reliance upon Costanzo v. Stewart, 9 Ariz. App. 430, 453 P.2d 526 (1969), is misplaced. There, the court found in favor of a subcontractor where the owner paid no one for the work performed by the subcontractor. In the present case, Radisson/CSA has paid Five Star a substantial portion of the contract price, and has retained the sum in question pursuant to Article 6.2 in the contract, which provides that the owner may withhold final payment until the general contractor has "satisfied all known indebtedness." Five Star defaulted on payments to subcontractors, thereby justifying the retention of final payment. In its response to plaintiff's motion for reconsideration, Radisson/CSA assured the court that it had no intention to permanently retain the sum, but was merely exercising its contractual right to withhold the final payment until Five Star's creditor's claims had been liquidated and satisfied. It is not the role of an owner in an owner-general contractor relationship to determine which subcontractors should be paid and the amount they are due. That function is an important reason for employing a general contractor.

Second, Flooring relies upon a recent case to argue that Arizona courts allow a subcontractor to sue an owner for unjust enrichment even where there is an express contract between the subcontractor and the general contractor. Commercial Cornice Millwork, Inc. v. Camel Construction Services Corp., 154 Ariz. 34, 739 P.2d 1351 (App. 1987). Again, Flooring's reliance is misplaced. In Commercial Cornice, during construction, the owner individually and personally agreed to pay the subcontractor upon completion of all the required work. No similar personal guaranty during construction was made in the present case. Thus, no contractual relationship establishing a basis for liability was ever formed between Raddison/CSA and Flooring. Id; Costanzo v. Stewart, supra. The court in Commercial Cornice distinguished cases relied upon by both the owner in that case and the present case, on the basis that in those cases the owners had fully paid the general contractors under the terms of the contract. However, the general contractors failed to pay the subcontractors. Thus, no unjust enrichment existed in favor of the owners. Similarly, Radisson/CSA has paid its general contractor pursuant to the contract, and is only withholding those funds it is permitted to retain according to the terms of the contract. It is Five Star, as the general contractor, who has failed to pay the subcontractors in full. The rule of Commercial Cornice is inapplicable in the present case. Flooring has no basis upon which to hold Radisson/CSA liable for unjust enrichment.

ATTORNEY'S FEES

The trial court awarded Radisson/CSA $10,000 in attorney's fees. Flooring argues that this award constituted a gross injustice. We will not substitute our discretion for that of the trial court regarding attorney's fees where the record contains a reasonable basis to sustain the decision of the court. Wheel Estate Corp. v. Webb, 139 Ariz. 506, 679 P.2d 529 (App. 1983). The record supports the award in this case.

Appellees' request for attorney's fees on appeal will be granted upon compliance with Ariz.R.Civ.App.P., 21(c), 17A A.R.S.

Affirmed.

FERNANDEZ, J., concur.


The appellant is in a "Catch 22" situation. The majority has decided it is not entitled to proceed against the appellees on the theory of unjust enrichment because appellee has a right to withhold the final payment until the general contractor has "satisfied all indebtedness." The general contractor has not "satisfied all indebtedness" nor any indebtedness, as far as the record shows, since the suit was instituted. There is no evidence that the general contractor will ever satisfy all indebtedness. A question of fact exists as to whether the general contractor will ever satisfy the requirements of its contract with the owner. Thus, summary judgment is precluded. If the evidence in the trial court is that the general contractor will never be able to pay, then Costanzo v. Stewart, 9 Ariz. App. 430, 453 P.2d 526 (1969), applies because the general contractor has not been paid. I would reverse and remand for further proceedings.


Summaries of

Flooring Systems v. Radisson Group

Court of Appeals of Arizona, Division Two, Department A
Oct 12, 1988
158 Ariz. 111 (Ariz. Ct. App. 1988)
Case details for

Flooring Systems v. Radisson Group

Case Details

Full title:FLOORING SYSTEMS, INC., an Arizona corporation, Plaintiff/Appellant, v…

Court:Court of Appeals of Arizona, Division Two, Department A

Date published: Oct 12, 1988

Citations

158 Ariz. 111 (Ariz. Ct. App. 1988)
761 P.2d 733

Citing Cases

Flooring Systems, Inc. v. Radisson Group

The court of appeals affirmed, relying on "common practice in the construction industry" to support its…

Adelman v. Christy

"A contract will be considered as having been rescinded by the substitution of another and subsequent…