Opinion
June 2, 1916.
Henry H. Man, for the appellants.
Abraham Lipton, for the respondent.
On the 17th of June, 1911, Nathan Herrmann, the defendants' testator, offered to build for and donate to the Jewish Protectory and Aid Society, a charitable organization, a building for use as a trade school. His offer was formally accepted on July 21, 1911.
Plaintiff is an architect, who, prior to the making of the offer by Herrmann, had, at his request, prepared preliminary sketches for the building. After the acceptance of the offer Herrmann, on the 25th of July, 1911, entered into two written agreements with the plaintiff. The first provided for the erection by the plaintiff as contractor of a frame and stucco building in conformity with the preliminary sketches at a cost of not to exceed $18,800. The second provided that Herrmann would pay the plaintiff six per cent of $18,800, viz., $1,128 for "all architectural services required or desirable for the planning, erection and supervision of Nathan Herrmann Agricultural and Trades School Building, * * * the services to consist of the necessary conferences, the preparation of preliminary studies, working drawings, specifications, large scale and full size detail drawings, and of the general direction and supervision of the work * * *."
The complaint alleges, in substance, that subsequent to the making of these contracts the plans and specifications referred to therein were modified with the knowledge and consent of Dr. Charles Schram, Herrmann's agent, which necessitated the drafting of new plans and specifications, with the result that the cost of the building was increased from $18,800 to $48,800, and that thereby the agreed and reasonable value of plaintiff's services as architect was increased to six per cent of the latter sum, viz., $2,928, of which only $828 has been paid. Judgment was demanded for the amount remaining due. The answer denied that there was anything due the plaintiff; that the agreements between him and defendants' testator were ever modified or superseded, and set up a counterclaim for $30,000 damages alleged to have been caused by the plaintiff's act in increasing the cost of the building from $18,800 to $48,800. The jury rendered a verdict in favor of the plaintiff for the amount claimed by him and against the defendants on their counterclaim. The defendants appeal from a judgment entered upon the verdict (the counterclaim not being mentioned or referred to therein) and an order denying a motion for a new trial, as well as an order granting plaintiff a certificate for costs.
The fact is undisputed that plaintiff did prepare plans and specifications for a much more elaborate building than that contemplated by the preliminary sketches, by reason of which the construction of the building cost $48,800 instead of $18,800, as originally planned. The main points of difference were that the plans and specifications provided for a basement under the entire building instead of under only a part, for the rearrangement of rooms, the addition of a balcony, and for the use of brick and stucco instead of frame and stucco.
The question presented upon the appeal is whether or not, by reason of the changes made by the plaintiff, Herrmann became obligated to pay him a sum greater than that fixed by the written contract of employment. There was no proof that any other or greater compensation was agreed upon. The recovery is predicated upon plaintiff's testimony to the effect that the reasonable value of his services was six per cent of the total cost of the building. This recovery cannot be sustained unless evidence was adduced at the trial sufficient to sustain a finding that the written agreement, by which plaintiff was to be paid $1,128, was modified so as to enable him to recover six per cent upon the total cost of the building. No evidence was offered that Herrmann personally knew of or assented to any change in the plans for the construction of the building, or to the modification of either of the contracts of July 25, 1911. It may well be doubted whether plaintiff proved that Dr. Schram's authority as agent was sufficient to permit him to consent to a modification or abandonment of those contracts. But even if that fact be assumed, I am unable to discover any evidence in the record, either that the contracts of July 25, 1911, were modified, or that they were in fact abandoned and new contracts made. Substantially the only evidence bearing upon this question is the disputed testimony of the plaintiff himself to the effect that at a meeting of the board of directors of the protectory, at which he and Dr. Schram were present, the changes above referred to were suggested by the directors, and that Dr. Schram then said to the plaintiff: "You have heard what the committee desires; draw plans in accordance with those instructions. Draw the building to be of brick. Draw the building with the entire basement and provide a balcony and place the assembly room on the ground floor." Any effect, however, which might be claimed from this testimony is completely destroyed when it was conclusively established that the meeting of the directors at which these changes were alleged to have been ordered by Dr. Schram, and the alleged statements made by him, was held on July 20, 1911 — five days before the contracts between Herrmann and the plaintiff were executed. It needs no argument to demonstrate the absurdity of the claim that these written instruments, fixing the rights and obligations of the parties to them, were modified by a conversation which took place prior to their execution. The written contracts were made for the sole purpose of fixing the rights of the parties, and any oral agreement theretofore had necessarily was merged in them. A contract cannot be changed or modified before it is made. When made, if it does not set forth the agreement, by reason of a mutual mistake, or a mistake of one of the parties and the fraud of the other, then a reformation may be had. But so long as it remains in the form in which it was executed, the rights and obligations of the parties must be determined by it. The plaintiff, doubtless recognizing the force of this rule, asserts that Dr. Schram knew of and assented to the changes which were made in the plans and specifications and the construction of the building in accordance with them, and by reason of that fact Herrmann became bound, at least by implication, to pay the reasonable value of the services rendered, which was six per cent of the cost of the building. It may be conceded that Dr. Schram knew that the preliminary sketches had been changed and the building was being constructed upon other plans, but it does not follow that he knew, at least until after Herrmann's death, that either the cost of the building or plaintiff's compensation would thereby be increased. The written contract as to the construction of the building provided that "the preliminary drawings may be changed or altered by the architect if deemed advisable in order to have them properly work out, but for that purpose only." Indeed, the acts of the plaintiff himself could hardly have done otherwise than have convinced Dr. Schram that the changes would not increase either the cost of the building or plaintiff's compensation. Thus, on September 27, 1911, he sent a letter to Dr. Schram, advising him that an application had been made to the State Board of Charities to approve the plans and specifications. In this letter he said: "I enclose a copy of original application, wherein you will notice at the bottom that I mentioned the estimated cost $30,000.00; this I did only because this amount had been published before, and has no bearing on the actual cost. * * * The problem was difficult, to get a brick building for the price of a frame building, but I desired to do something extra to aid in the good cause Mr. Herrmann had in mind." Not only this, but during the progress of the work, between November 12, 1911, and June 13, 1913, he issued to himself as contractor fifteen certificates calling for payments under the building contract. These certificates are on printed forms, filled out by plaintiff himself. Each of the first four reads in part as follows: "Contract price $18,800.00. Extra work None. Deduction none. Total, $18,800.00." The remaining eleven are in the same form, except that instead of the word "None," after "Extra work" and "Deduction," appear either dashes or blank spaces. In each of these certificates the balance is computed as the difference between $18,800 and the amount of the prior payments.
But even of more significance than these certificates are the two which plaintiff issued to himself as architect and in which he certified that he was entitled to payments under his written agreement of employment. This agreement, as before stated, specified that plaintiff's compensation was to be $1,128, of which $225 was payable upon the completion of the preliminary studies and $450 upon completion of the specifications and general working drawings, exclusive of details. These sums were paid to plaintiff on September 9, 1911. The agreement also provided that an additional $153 should be paid upon completion of large scale and full size detail drawings. On May 24, 1912, plaintiff certified that this payment was due. The certificate states the contract price as $1,128; the balance to be paid as $300, and mentions no claim for extra compensation. According to plaintiff's testimony he knew long before the second certificate was issued to him that the building would cost largely in excess of $18,800. The conclusion, therefore, is irresistible that at that time he did not consider that his written contract of employment had been modified in any way by the changes in the plans and the increased cost of the building. His every act down to the time of Herrmann's death is inconsistent with his present claim. It clearly shows that up to that time he did not expect compensation other than that specified in the written agreement.
Herrmann died on August 23, 1912. At that time plaintiff as contractor had called for and received payments aggregating only $2,969.19 under the building contract. Of course whatever authority Dr. Schram had as Herrmann's agent ceased upon the latter's death and nothing subsequently done by him could bind Herrmann's estate, nor could the acts of Herrmann's executors affect plaintiff's rights against Herrmann's estate. ( Chisolm v. Toplitz, 82 App. Div. 346; affd., on opinion below, 178 N.Y. 599. ) The powers of the executors were limited. They could only discharge obligations legally incurred by their testator. This they did, making payments to the plaintiff on his certificates up to June 13, 1913, at which time he had received on the building contract substantially the entire contract price, $18,784.96. Thereafter they refused to make further payments or to complete the building, and on December 12, 1913, the protectory took over the work and in April, 1914, completed the building at a cost of $30,000 under the direction of its own superintendent.
Plaintiff did not supervise the work done under the contract made by the protectory or have anything to do with it; in fact, he was ordered by the protectory to keep away from the building. As already indicated, plaintiff had been paid prior to Herrmann's death $828 out of $1,128, the price fixed for his services by the contract of employment. The balance of $300 was payable "upon completion of the building" and was apparently intended to cover the general direction and supervision of the work, which was required of plaintiff by his contract. As he concededly did not perform a substantial portion of the work of supervision, and as he stands squarely upon a plea of complete performance, he is not entitled to recover such balance in this action. ( Hecla Iron Works v. Hall, 115 App. Div. 126; Stern v. McKee, 70 id. 142; La Chicotte v. Richmond R. El. Co., 15 id. 380.)
Proper motions were made to dismiss the complaint at the end of plaintiff's case and renewed at the close of the evidence. The motions were denied and exceptions taken.
If the foregoing views be correct, then it follows that the judgment and orders appealed from must be reversed, with costs to the appellants, and the complaint dismissed, with costs.
CLARKE, P.J., LAUGHLIN, SCOTT and DOWLING, JJ., concurred.
Judgment and orders reversed, with costs, and complaint dismissed, with costs.