From Casetext: Smarter Legal Research

Finlin v. Pennsylvania Railroad Company

United States Court of Appeals, Third Circuit
Apr 10, 1961
288 F.2d 826 (3d Cir. 1961)

Opinion

No. 13393.

Argued February 10, 1961.

Decided April 10, 1961.

James M. Davis, Jr., Mount Holly, N.J. (Powell Davis, Mount Holly, N.J., on the brief), for appellants.

F. Morse Archer, Jr., Camden, N.J. (John P. Hauch, Jr., Archer, Greiner, Hunter Read, Camden, N.J., John B. Prizer, Richard N. Clattenburg, Philadelphia, Pa., on the brief), for appellee.

Before BIGGS, Chief Judge, and STALEY and HASTIE, Circuit Judges.


The appellants' wage claims were denied by the National Railroad Adjustment Board. By their complaint they seek a trial de novo in the court below on the ground that the Board has not afforded them procedural due process. The court dismissed the action for lack of jurisdiction holding that the Board's action was not reviewable and that the appellants were not entitled to a trial de novo and that the Board was a necessary party to the action. 1960, 187 F. Supp. 381.

The bases of the appellants' claims are substantially similar to those asserted in Pennsylvania R. Co. v. Day, 1959, 360 U.S. 548, 79 S.Ct. 1322, 3 L.Ed. 2d 1422. In the Day case and in Union Pacific R. Co. v. Price, 1959, 360 U.S. 601, 79 S.Ct. 1351, 3 L.Ed.2d 1460, the Supreme Court held that claims such as that at bar were subject to the exclusive primary jurisdiction of the Board and when denied could not be relitigated in a common-law damage suit. The court below was, therefore, correct in its conclusion that it could not afford the appellants a trial de novo.

The appellants contend that a United States district court can grant some form of relief where the Board's action constitutes a taking of property without due process of law as is alleged here. See Union Pacific R. Co. v. Price, supra, 360 U.S. at page 616, 79 S.Ct. at page 1359, Barnett v. Pennsylvania-Reading Seashore Lines, 3 Cir., 1957, 245 F.2d 579, 582. Even if it be assumed, however, that the appellants' position in this respect is correct, binding relief could not be granted in a case such as that at bar unless the Board be made a party to the action. See Stranford v. Pennsylvania R. Co., D.C.D.N.J. 1957, 155 F. Supp. 680, 690, citing Blackmar v. Guerre, 1952, 342 U.S. 512, 72 S.Ct. 410, 96 L.Ed. 534. Since the Board is not a party to this action the court below was correct in dismissing the amended complaint.

The judgment will be affirmed.


Summaries of

Finlin v. Pennsylvania Railroad Company

United States Court of Appeals, Third Circuit
Apr 10, 1961
288 F.2d 826 (3d Cir. 1961)
Case details for

Finlin v. Pennsylvania Railroad Company

Case Details

Full title:Thomas J. FINLIN, Charles H. Hogentogler and Darrell L. Middleton…

Court:United States Court of Appeals, Third Circuit

Date published: Apr 10, 1961

Citations

288 F.2d 826 (3d Cir. 1961)

Citing Cases

Radin v. United States

Radin's claim can only be viewed as a challenge to the validity of the award rendered against him. There are…

Fong v. American Airlines, Inc.

No formal intervention by the board is contemplated in the section or necessary to effectuate its review…