From Casetext: Smarter Legal Research

Fernandez v. Morales Bros. Realty, Inc.

Supreme Court, Appellate Division, Second Department, New York.
Oct 2, 2013
110 A.D.3d 676 (N.Y. App. Div. 2013)

Opinion

2013-10-2

Gladys FERNANDEZ, appellant, v. MORALES BROS. REALTY, INC., et al., respondents.

Richard L. Giampa, P.C., Bronx, N.Y., for appellant. Gannon, Rosenfarb, Balletti & Drossman, New York, N.Y. (Lisa L. Gokhulsingh of counsel), for respondent.



Richard L. Giampa, P.C., Bronx, N.Y., for appellant. Gannon, Rosenfarb, Balletti & Drossman, New York, N.Y. (Lisa L. Gokhulsingh of counsel), for respondent.
DANIEL D. ANGIOLILLO, J.P., L. PRISCILLA HALL, SHERI S. ROMAN, and JEFFREY A. COHEN, JJ.

In an action to recover damages for personal injuries, the plaintiff appeals from so much of an order of the Supreme Court, Queens County (Butler, J.), entered March 19, 2012, as denied that branch of her motion which was pursuant to CPLR 306–b for an extension of time to effect service of process upon the defendant Morales Bros. Realty, Inc., nunc pro tunc to September 11, 2011, and granted that branch of the defendants' cross motion which was pursuant to CPLR 3211(a)(8) to dismiss the complaint insofar as asserted against the defendant Morales Bros. Realty, Inc., for lack of personal jurisdiction.

ORDERED that the order is reversed insofar as appealed from, on the facts and in the exercise of discretion, with costs, that branch of the plaintiff's motion which was pursuant to CPLR 306–b for an extension of time to effect service of process upon the defendant Morales Bros. Realty, Inc., is granted, and that branch of the defendants' cross motion which was pursuant to CPLR 3211(a)(8) to dismiss the complaint insofar as asserted against the defendant Morales Bros. Realty, Inc., for lack of personal jurisdiction is denied.

On May 12, 2011, the plaintiff filed a summons and complaint with the Queens County clerk naming, as defendants, Morales Bros. Realty, Inc. (hereinafter MBRI) and Jorge A. Morales. According to the affidavit of service, the plaintiff's process server served both MBRI and Morales on September 11, 2011, or 3 days after the expiration of the 120–day period of service set forth in CPLR 306–b, by personally delivering a copy of the summons and complaint to Morales, who is also the president of MBRI.

The defendants contend that MBRI was never served with a copy of the summons and complaint. We disagree. Service of one copy of a summons and complaint upon an officer of a corporation constitutes service upon the corporation itself as well as upon the individual officer, where, as here, there was simultaneous compliance with CPLR 311(a)(1) and CPLR 308(1) ( see Matter of T.E.A. Mar. Automotive Corp. v. Scaduto, 181 A.D.2d 776, 780, 581 N.Y.S.2d 370;Lac Leasing Corp. v. Dutchess Aero Inc., 32 A.D.2d 949, 303 N.Y.S.2d 723;Port Chester Elec. Co. v. Ronbed Corp., 28 A.D.2d 1008, 284 N.Y.S.2d 9;cf. Lakeside Concrete Corp. v. Pine Hollow Bldg. Corp., 104 A.D.2d 551, 479 N.Y.S.2d 256,affd.65 N.Y.2d 865, 493 N.Y.S.2d 309, 482 N.E.2d 1225). Here, MBRI was served pursuant to CPLR 311(a)(1) when the plaintiff's process server delivered the summons and complaint to the individual defendant, an officer of MBRI. Accordingly, the method employed to serve MBRI was proper and, thus, that branch of the defendants' cross motion which was pursuant to CPLR 3211(a)(8) to dismiss the complaint insofar as asserted against MBRI for lack of personal jurisdiction should have been denied.

In this case, where the statute of limitations expired between the time that the action was commenced and the time that the copy of the summons and complaint was served, that branch of the plaintiff's motion which was pursuant to CPLR 306–b to extend the time to serve the summons and complaint upon MBRI nunc pro tunc to September 11, 2011, should have been granted in the interest of justice ( see Leader v. Maroney, Ponzini & Spencer, 97 N.Y.2d 95, 105–106, 736 N.Y.S.2d 291, 761 N.E.2d 1018;Rosenzweig v. 600 N. St., LLC, 35 A.D.3d 705, 706, 826 N.Y.S.2d 680). The copy of the summons and complaint was served only 3 days after the 120–day time period of CPLR 306–b had expired, the plaintiff promptly sought relief after receiving the answer, and there was no demonstrable prejudice to MBRI attributable to the delay in service ( see Thompson v. City of New York, 89 A.D.3d 1011, 1012, 933 N.Y.S.2d 701;DiBuono v. Abbey, LLC, 71 A.D.3d 720, 895 N.Y.S.2d 726;Abu–Aqlein v. El–Jamal, 44 A.D.3d 884, 885, 844 N.Y.S.2d 385;Beauge v. New York City Tr. Auth., 282 A.D.2d 416, 722 N.Y.S.2d 402;Busler v. Corbett, 259 A.D.2d 13, 17, 696 N.Y.S.2d 615).


Summaries of

Fernandez v. Morales Bros. Realty, Inc.

Supreme Court, Appellate Division, Second Department, New York.
Oct 2, 2013
110 A.D.3d 676 (N.Y. App. Div. 2013)
Case details for

Fernandez v. Morales Bros. Realty, Inc.

Case Details

Full title:Gladys FERNANDEZ, appellant, v. MORALES BROS. REALTY, INC., et al.…

Court:Supreme Court, Appellate Division, Second Department, New York.

Date published: Oct 2, 2013

Citations

110 A.D.3d 676 (N.Y. App. Div. 2013)
972 N.Y.S.2d 332
2013 N.Y. Slip Op. 6345

Citing Cases

Wynn v. Burleigh

In addition, plaintiff has not demonstrated any prejudice attributable to the delay in service, which only…

Wells Fargo Bank v. Barrella

Moreover, the plaintiff failed to explain its more than six-month delay in moving for relief pursuant to CPLR…