From Casetext: Smarter Legal Research

Fernandez v. Evergreen Power, LLC

Supreme Court of New York, Appellate Division, First Department
Dec 2, 2021
No. 2021-75360 (N.Y. App. Div. Dec. 2, 2021)

Opinion

2021-75360 Motion 2021-03381

12-02-2021

Juvenal Fernandez, Plaintiff-Respondent, v. Evergreen Power, LLC, Asnat Realty, LLC, Grant Mackay Demolition Co., and Grant Mackay Company, Inc., Defendants, and Classic Environmental, Inc., Defendant-Appellant. [And Third-Party Actions] Index No. 23069/12E No. 2020-04018


Unpublished Opinion

MOTION DECISION

PRESENT: Hon. Rolando T. Acosta, Presiding Justice, Jeffrey K. Oing, Anil C. Singh, Julio Rodriguez III, Justices.

Defendant/second third-party plaintiff-appellant Classic Environmental, Inc., having moved for an extension of time in which to perfect the appeal taken from an order of the Supreme Court, Bronx County, entered on or about August 17, 2020,

Now, upon reading and filing the papers with respect to the motion, and due deliberation having been had thereon, It is ordered that the motion is granted and the time in which to perfect the appeal is extended to the April 2022 Term of this Court, with leave to seek additional extensions, if necessary.


Summaries of

Fernandez v. Evergreen Power, LLC

Supreme Court of New York, Appellate Division, First Department
Dec 2, 2021
No. 2021-75360 (N.Y. App. Div. Dec. 2, 2021)
Case details for

Fernandez v. Evergreen Power, LLC

Case Details

Full title:Juvenal Fernandez, Plaintiff-Respondent, v. Evergreen Power, LLC, Asnat…

Court:Supreme Court of New York, Appellate Division, First Department

Date published: Dec 2, 2021

Citations

No. 2021-75360 (N.Y. App. Div. Dec. 2, 2021)