From Casetext: Smarter Legal Research

Fanelli v. J.C. Millbank Constr. Co.

Supreme Court, Appellate Division, Second Department, New York.
Jan 17, 2012
91 A.D.3d 703 (N.Y. App. Div. 2012)

Opinion

2012-01-17

Frank J. FANELLI, appellant, v. J.C. MILLBANK CONSTRUCTION COMPANY, INC., et al., respondents, et al., defendants.

Conway & Kirby, LLP, Latham, N.Y. (Kimberly Boucher Furnish of counsel), for appellant. Kelly & Meenagh, LLP, Poughkeepsie, N.Y. (John P. Meenagh of counsel), for respondent J.C. Millbank Construction Company, Inc.


Conway & Kirby, LLP, Latham, N.Y. (Kimberly Boucher Furnish of counsel), for appellant. Kelly & Meenagh, LLP, Poughkeepsie, N.Y. (John P. Meenagh of counsel), for respondent J.C. Millbank Construction Company, Inc. Ahmuty, Demers & McManus, Albertson, N.Y. (Brendan T. Fitzpatrick of counsel), for respondent Pantel Contracting Corp.Burke Lipton & Gordon, White Plains, N.Y. (Ashley E. Sproat of counsel), for respondent JMOA Engineering, P.C.Susan B. Owens, White Plains, N.Y. (Paul L. Neugebauer of counsel), for respondent Dutchess Mechanical, Inc.DANIEL D. ANGIOLILLO, J.P., RUTH C. BALKIN, THOMAS A. DICKERSON, and L. PRISCILLA HALL, JJ.

In an action to recover damages for personal injuries, the plaintiff appeals, as limited by his brief, from so much of an order of the Supreme Court, Dutchess County (Pagones, J.), dated December 23, 2010, as (1) denied those branches of his motion which were for summary judgment on the issue of liability on the causes of action alleging violations of Labor Law § 240(1) and § 241(6) insofar as asserted against the defendants J.C. Millbank Construction Company, Inc., and JMOA Engineering, P.C., and alleging a violation of Labor Law § 200 insofar as asserted against the defendants J.C. Millbank Construction Company, Inc., JMOA Engineering, P.C., Dutchess Mechanical, Inc., and Pantel Contracting Corp., (2) granted those branches of the separate cross motions of the defendants Dutchess Mechanical, Inc., and Pantel Contracting Corp. which were for summary judgment dismissing the cause of action alleging a violation of Labor Law § 200 insofar as asserted against them, (3) granted that branch of the cross motion of the defendant JMOA Engineering, P.C., which was for summary judgment dismissing the cause of action alleging a violation of Labor Law § 241(6) insofar as asserted against it, and (4) upon searching the record, awarded summary judgment to the defendant J.C. Millbank Construction Company, Inc., dismissing the cause of action alleging a violation of Labor Law § 241(6) insofar as asserted against that defendant.

ORDERED that the order is modified, on the law, (1) by deleting the provision thereof granting that branch of the cross motion of the defendant JMOA Engineering, P.C., which was for summary judgment dismissing the cause of action alleging a violation of Labor Law § 241(6) insofar as asserted against it, and substituting therefor a provision denying that branch of the cross motion, and (2) by deleting the provision thereof, upon searching the record, awarding summary judgment to the defendant J.C. Millbank Construction Company, Inc., dismissing the cause of action alleging a violation of Labor Law § 241(6) insofar as asserted against it; as so modified, the order is affirmed insofar as appealed from, without costs or disbursements.

On August 1, 2005, the plaintiff was working as a carpenter on a construction project at the Violet Avenue Elementary School in the Hyde Park School District in Poughkeepsie. The project involved, among other things, the renovation of a bathroom. The defendant J.C. Millbank Construction Company, Inc. (hereinafter Millbank), was the general contractor. The defendant JMOA Engineering, P.C. (hereinafter JMOA), was the construction manager. The defendant Pantel Contracting Corp. (hereinafter Pantel) was the prime contractor for electrical work, and the defendant Dutchess Mechanical, Inc. (hereinafter Dutchess), was the prime contractor for plumbing work. The plaintiff's employer, Paterson Construction Company, was retained as a subcontractor to install sheetrock. The plaintiff allegedly was injured while attempting to install a two-foot-by-eight-foot piece of sheetrock by himself near the ceiling of the bathroom. After ascending an A-frame ladder with the sheetrock, the plaintiff realized that the piece was too large, and he started to descend. The ladder allegedly wobbled, and the plaintiff fell, catching his foot in a hole that had been drilled in the floor. He alleged that construction debris on the floor had caused the ladder to be unsteady.

The plaintiff commenced this action to recover damages for his injuries, alleging common-law negligence and violations of Labor Law §§ 200, 240(1), and 241(6) against, among others, Millbank, JMOA, Pantel, and Dutchess. After issue was joined, the plaintiff moved for summary judgment on the issue of liability against various defendants. JMOA, Dutchess, and Pantel separately cross-moved for summary judgment dismissing the complaint insofar as asserted against them. The Supreme Court denied the plaintiff's motion as to the causes of action alleging violations of the Labor Law, but did not address the cause of action alleging common-law negligence. In addition, the Supreme Court granted those branches of the cross motions which were for summary judgment dismissing the causes of action alleging violations of Labor Law § 241(6) and, upon searching the record, awarded summary judgment to Millbank dismissing that cause of action insofar as asserted against it, even though it had not moved for relief. The Supreme Court also granted those branches of the cross motions of Pantel and Dutchess which were for summary judgment dismissing the causes of action alleging violations of Labor Law §§ 200 and 240(1) insofar as asserted against them.

The Supreme Court correctly denied that branch of the plaintiff's motion which was for summary judgment on the issue of liability on the causes of action alleging violations of Labor Law § 240(1) and § 241(6) insofar as asserted against Millbank and JMOA. There were triable issues of fact as to whether those defendants' alleged violations of Labor Law § 240(1) and § 241(6) proximately caused the plaintiff's injuries ( see Reborchick v. Broadway Mall Props., Inc., 10 A.D.3d 713, 714, 781 N.Y.S.2d 899; cf. Ernest v. Pleasantville Union Free School Dist., 28 A.D.3d 419, 811 N.Y.S.2d 573). For the same reason, however, Millbank and JMOA were not entitled to summary judgment dismissing the cause of action alleging violations of Labor Law § 241(6) insofar as asserted against them ( see Gurung v. Arnav Retirement Trust, 79 A.D.3d 969, 970, 915 N.Y.S.2d 97).

The Supreme Court properly denied that branch of the plaintiff's motion which was for summary judgment on the cause of action alleging a violation of Labor Law § 200 insofar as asserted against Millbank, JMOA, Pantel, and Dutchess. The plaintiff failed to establish, prima facie, that Pantel and Dutchess violated that statute ( see Linkowski v. City of New York, 33 A.D.3d 971, 974, 824 N.Y.S.2d 109). In opposition to the plaintiff's prima facie showing of entitlement to judgment as a matter of law as to Millbank and JMOA, those defendants raised a triable issue of fact as to whether they violated the statute and whether any such violation proximately caused the plaintiff's injuries ( cf. Martinez v. City of New York, 73 A.D.3d 993, 997–998, 901 N.Y.S.2d 339).

The Supreme Court properly granted those branches of the cross motions of Pantel and Dutchess which were for summary judgment dismissing the Labor Law § 200 cause of action insofar as asserted against each of them. On their cross motions, Pantel and Dutchess established, prima facie, that they had not violated Labor Law § 200 and, in opposition, the plaintiff failed to raise a triable issue of fact ( see Ortiz v. I.B.K. Enters., Inc., 85 A.D.3d 1139, 1140, 927 N.Y.S.2d 114; Georgakopoulos v. Shifrin, 83 A.D.3d 659, 660, 920 N.Y.S.2d 383; Rojas v. Schwartz, 74 A.D.3d 1046, 1047, 903 N.Y.S.2d 484).

The parties' contentions regarding the causes of action alleging common-law negligence as to Millbank, JMOA, Pantel, and Dutchess, are not properly before this Court. Since the Supreme Court did not address the branches of the motions relating to those causes of action, they remain pending and undecided ( see Young Chool Yoo v. Rui Dong Wang, 88 A.D.3d 991, 931 N.Y.S.2d 373; Katz v. Katz, 68 A.D.2d 536, 542–543, 418 N.Y.S.2d 99).


Summaries of

Fanelli v. J.C. Millbank Constr. Co.

Supreme Court, Appellate Division, Second Department, New York.
Jan 17, 2012
91 A.D.3d 703 (N.Y. App. Div. 2012)
Case details for

Fanelli v. J.C. Millbank Constr. Co.

Case Details

Full title:Frank J. FANELLI, appellant, v. J.C. MILLBANK CONSTRUCTION COMPANY, INC.…

Court:Supreme Court, Appellate Division, Second Department, New York.

Date published: Jan 17, 2012

Citations

91 A.D.3d 703 (N.Y. App. Div. 2012)
937 N.Y.S.2d 114
2012 N.Y. Slip Op. 325

Citing Cases

Quality Health Supply Corp. v. Amica Mut. Ins. Co.

However, no appeal lies from an order or portion thereof which fails to determine a motion or branch thereof…

PDG Psychological, P.C. v. State Farm Mutual Insurance Co.

"However, no appeal lies from an order or portion thereof which fails to determine a motion or branch thereof…