From Casetext: Smarter Legal Research

Etheridge v. McKenzie Tank Lines

District Court of Appeal of Florida, First District
Mar 14, 1990
557 So. 2d 962 (Fla. Dist. Ct. App. 1990)

Summary

In Etheridge, where the e/c's payment of the sums owed following issuance of the mandate was untimely, we held the claimant was entitled not only to 20 percent penalties under subsection (8), but also to statutory interest on the unpaid penalty from the date 30 days after the compensation was due, pursuant to subsection (9). For reasons already stated, we find the instant case to be factually distinguishable from Etheridge, so an award of interest on unpaid penalties would have been inappropriate.

Summary of this case from City of North Miami v. Marcy

Opinion

No. 88-2990.

March 14, 1990.

Appeal from the Judge of Compensation Claims.

John E. Houser, Jacksonville, for appellants.

J. Bruce Bickner, of Dawson, Galant, Sulik, Wiesenfeld Bickner, Jacksonville, for appellee.


Of the three issues raised by appellants, only their challenge to the judge of compensation claim's denial of a penalty, sought pursuant to the provisions of Section 440.20(8), Florida Statutes (1985), is meritorious. Despite the issuance of this court's mandate on July 29, 1988, following an earlier appeal from an order awarding death benefits, the employer/carrier failed to pay the sums owed until September 28, 1988, more than 30 days after our opinion had become final, contrary to section 440.20(8). Accordingly, appellants are entitled to be awarded a 20 percent penalty on the amount paid ($16,532.42) on September 28, 1988. See Binimelis v. M.E.F. Int'l Corp., 424 So.2d 941 (Fla. 1st DCA 1983); Jones v. Cling Elec., Inc., 397 So.2d 767 (Fla.1st DCA 1981). Appellants are similarly entitled to interest on the unpaid penalty from August 29, 1988, when the compensation was due, until the penalty is paid. § 440.20(9), Fla. Stat. (1985).

The remaining points raised by appellants are affirmed without discussion.

AFFIRMED in part, REVERSED in part, and REMANDED for further proceedings.

NIMMONS and ZEHMER, JJ., concur.


Summaries of

Etheridge v. McKenzie Tank Lines

District Court of Appeal of Florida, First District
Mar 14, 1990
557 So. 2d 962 (Fla. Dist. Ct. App. 1990)

In Etheridge, where the e/c's payment of the sums owed following issuance of the mandate was untimely, we held the claimant was entitled not only to 20 percent penalties under subsection (8), but also to statutory interest on the unpaid penalty from the date 30 days after the compensation was due, pursuant to subsection (9). For reasons already stated, we find the instant case to be factually distinguishable from Etheridge, so an award of interest on unpaid penalties would have been inappropriate.

Summary of this case from City of North Miami v. Marcy
Case details for

Etheridge v. McKenzie Tank Lines

Case Details

Full title:OSCAR W. ETHERIDGE, SR., ET AL., APPELLANTS, v. McKENZIE TANK LINES, INC.…

Court:District Court of Appeal of Florida, First District

Date published: Mar 14, 1990

Citations

557 So. 2d 962 (Fla. Dist. Ct. App. 1990)

Citing Cases

Steinbrecher v. Better Const. Co.

492 So.2d at 1179. See also Etheridge v. McKenzie Tank Lines, Inc., 557 So.2d 962 (Fla. 1st DCA 1990); Parker…

Sigg v. Sears, Roebuck & Co.

We are not unmindful of the apparent conflict in cases in this district concerning § 440.20(8), Fla. Stat.…