From Casetext: Smarter Legal Research

Emmert Industrial v. City of Milwaukie

United States Court of Appeals, Ninth Circuit
Jan 7, 2009
307 F. App'x 65 (9th Cir. 2009)

Summary

holding that a litigation waiver in an agreement between a city and a private company did not amount to an unconstitutional condition

Summary of this case from Eklecco Newco LLC v. Town of Clarkstown

Opinion

No. 06-35866.

Argued and Submitted October 23, 2008.

Filed January 7, 2009.

Jonathan Clark, Esquire, Kelly W.G. Clark, Esquire, Kristian Roggendorf, O'Donnell Clark LLP, Portland, OR, for Plaintiff-Appellant.

Charles E. . Corrigan, Esquire, Ramis Crew Corrigan Bachrach, LLP, Portland, OR, for Defendant-Appellee.

Appeal from the United States District Court for the District of Oregon, Dennis James Hubel, Magistrate Judge, Presiding. D.C. No. CV-05-0514-HU.

Before: TASHIMA and M. SMITH, Circuit Judges, and WU, District Judge.

The Honorable George H. Wu, United States District Judge for the Central District of California, sitting by designation.


MEMORANDUM

This disposition is not appropriate for publication and is not precedent except as provided by 9th Cir. R. 36-3.

Plaintiff Emmert Industrial Corp. ("Emmert") appeals an order of the district court granting summary judgment to defendant, the City of Milwaukie (the "City"). Emmert filed an action against the City under 42 U.S.C. § 1983, alleging that the City's proposal to halt demolition of an Emmert property in exchange for a litigation waiver amounted to an "unconstitutional condition" that deprived Emmert of its First Amendment right to access the courts.

Emmert also alleged that the City's conduct amounted to Due Process, Equal Protection, and Takings violations. The district court ruled against Emmert on these claims as well, but these rulings are not challenged on appeal.

Emmert's claim stemmed from its acquisition of a run-down house in the City that was the subject of a nuisance abatement proceeding. Emmert intended to move the house to a new location to stave off demolition, but was unable to obtain the necessary permits.

Because the parties are familiar with the factual and procedural background, we recite it here only so far as is necessary to aid in understanding this disposition.

After the matter had dragged on for several months without resolution, the City decided to proceed with demolition. In a final effort to save the house, the City proposed a "Final Agreement" to Emmert. The agreement conditionally approved a permit to relocate the house and held demolition in abeyance — so long as Emmert met strict performance requirements. The agreement also required Emmert to waive all claims against the City related to the house. Emmert objected to several provisions, the parties never reached a definitive agreement, and the City demolished the house shortly thereafter.

In granting the City's motion for summary judgment, the district court concluded that the proposed agreement did not amount to an "unconstitutional condition." We have jurisdiction pursuant to 28 U.S.C. § 1291, and we affirm. We review the grant of summary judgment de novo. Qwest Commc'ns, Inc. v. City of Berkeley, 433 F.3d 1253, 1256 (9th Cir. 2006).

The record shows that the litigation waiver was not a but-for dealbreaker. Emmert objected to several provisions of the proposed agreement, and each was independently fatal to the settlement. Thus, the waiver was not the actual or proximate cause of Emmert's injury. Emmert cannot show the causation element required in a § 1983 action. See Harper v. City of Los Angeles, 533 F.3d 1010, 1026 (9th Cir. 2008).

Assuming arguendo that Emmert can show causation, the litigation waiver did not amount to an unconstitutional condition. The government may condition the grant of a discretionary benefit "if the condition is rationally related to the benefit conferred." United States v. Geophysical Corp., 732 F.2d 693, 700 (9th Cir. 1984). When the condition is imposed as part of a settlement agreement, we look for "a close nexus — a tight fit — between the specific interest the government seeks to advance in the dispute . . . and the specific right waived." Davies v. Grossmont Union High Sch. Dist., 930 F.2d 1390, 1399 (9th Cir. 1991); see also Dolan v. City of Tigard, 512 U.S. 374, 385-36, 114 S.Ct. 2309, 129 L.Ed.2d 304 (1994).

In this case, the City had a legitimate interest in settling a dispute over a rundown house that had dragged on for years. The condition the government imposed — a litigation waiver — directly advanced this interest by ensuring the dispute would come to a quick end. The benefit Emmert was to receive — a comprehensive settlement — was also closely connected to the litigation waiver and the City's need for resolution.

Moreover, it is not at all unusual or impermissible for the government to seek a litigation waiver as part of a settlement agreement of a pending dispute or a potential lawsuit. See Town of Newton v. Rumery, 480 U.S. 386, 107 S.Ct. 1187, 94 L.Ed.2d 405 (1987); see also La. Pac. Corp. v. Beazer Materials Servs., Inc., 842 F.Supp. 1243 (E.D.Cal. 1994).

The judgment of the district court is AFFIRMED.


Summaries of

Emmert Industrial v. City of Milwaukie

United States Court of Appeals, Ninth Circuit
Jan 7, 2009
307 F. App'x 65 (9th Cir. 2009)

holding that a litigation waiver in an agreement between a city and a private company did not amount to an unconstitutional condition

Summary of this case from Eklecco Newco LLC v. Town of Clarkstown
Case details for

Emmert Industrial v. City of Milwaukie

Case Details

Full title:EMMERT INDUSTRIAL CORPORATION, an Oregon corporation, Plaintiff-Appellant…

Court:United States Court of Appeals, Ninth Circuit

Date published: Jan 7, 2009

Citations

307 F. App'x 65 (9th Cir. 2009)

Citing Cases

Thomas v. Cnty. of Humboldt

For example, a litigation waiver included in a settlement agreement does not amount to an unconstitutional…

Lil' Man in the Boat, Inc. v. City of S.F.

Defendants rely exclusively for this argument on Emmert Indus. Corp. v. City of Milwaukie, a Ninth Circuit…