From Casetext: Smarter Legal Research

E. F. Blankenship Co. v. N.C. Dept. of Transp

North Carolina Court of Appeals
Feb 1, 1986
79 N.C. App. 462 (N.C. Ct. App. 1986)

Opinion

No. 8510SC709

Filed 18 February 1986

Highways and Cartways 9 — action to recover for highway construction — claim improperly filed — complaint dismissed Where plaintiff alleged that it had not received compensation properly due under a highway construction contract and filed a claim pursuant to N.C.G.S. 136-29, but plaintiffs verification was not filed with its first claim and the second claim was not received within the statutorily prescribed period, plaintiff failed to fulfill a condition precedent to maintaining its action in superior court and its complaint was properly dismissed.

APPEAL by the plaintiff from Bailey, Judge. Judgment entered 26 February 1985 in Superior Court, WAKE County. Heard in the Court of Appeals 3 December 1985.

Blanchard, Tucker, Twiggs, Earls Abrams, by Charles F. Blanchard and Donald R. Strickland, for plaintiff appellant.

Attorney General Lacy H. Thornburg, by Senior Deputy Attorney General Eugene A. Smith and Assistant Attorney General Evelyn M. Coman, for defendant appellee.


Judge BECTON dissenting.


The plaintiff entered into a highway construction contract with the North Carolina Department of Transportation. On 12 March 1984, after completion of the project, the plaintiff received payment of its final estimate from the Department. The plaintiff, alleging that it had not received the compensation properly due under the contract, filed a claim pursuant to G.S. 136-29.

The plaintiff's office manager assembled and mailed the claim on 9 May 1984, but "inadvertently failed to attach" the plaintiff's president's affidavit verifying the claim. After the State Highway Administrator received the claim on 10 May 1984 he responded that the claim could not be considered because it was not verified as required by G.S. 136-29. The plaintiff then submitted an amended claim, which was another copy of the original claim with the affidavit attached. This amended claim was received on 21 May 1984. In a letter of 22 May 1984 the State Highway Administrator stated that the plaintiff's claim could not be considered because the first claim was not verified and the second claim was not received within the statutory time period.

The plaintiff filed this action which was dismissed by the superior court. The plaintiff appealed.


This action was brought pursuant to G.S. 136-29 which provides in part:

(a) Upon the completion of any contract for the construction of any State highway awarded by the Department of Transportation to any contractor, if the contractor fails to receive such settlement as he claims to be entitled to under his contract, he may, within 60 days from the time of receiving his final estimate, submit to the State Highway Administrator a written and verified claim for such amount as he deems himself entitled to under the said contract setting forth the facts upon which said claim is based . . . .

(b) As to such portion of the claim as is denied by the State Highway Administrator, the contractor may, within six (6) months from receipt of said decision, institute a civil action for such sum as he claims to be entitled to under said contract by the filing of a verified complaint and issuance of summons in the Superior Court of Wake County or in the superior court of any county wherein the work under said contract was performed. . . .

. . . . . .

(d) The submission of the claim to the State Highway Administrator within the time and as set out in subsection (a) of this section and the filing of an action in the superior court within the time as set out in subsection (b) of this section . . . shall be a condition precedent to bringing such an action under this section and shall not be a statute of limitations.

(e) The provisions of this section shall be deemed to enter into and form a part of every contract entered into between the Department of Transportation and any contractor, and no provision in said contracts shall be valid that is in conflict herewith.

The sole issue is whether the plaintiff's first claim, received on 10 May 1984, was "written and verified" within the meaning of G.S. 136-29 (a) so that the plaintiff fulfilled a condition precedent to bringing this action in superior court.

The express language of G.S. 136-29 (a) provides that a contractor may "within 60 days from the time of receiving his final estimate, submit to the State Highway Administrator a written and verified claim . . . ." (Emphasis added.) G.S. 136-29 (d) then clearly states that "submission of the claim to the State Highway Administrator within the time and as set out in subsection (a) . . . shall be a condition precedent to bringing such an action under this section. . . ." (Emphasis added.) Therefore, to satisfy G.S. 136-29 the contractor must submit a claim, accompanied by evidence of verification, within the statutory time limit.

Because the plaintiff's verification was not filed with the first claim and the second claim was not received within the prescribed period, the plaintiff failed to fulfill a condition precedent to maintaining its action in superior court and the plaintiff's complaint was properly dismissed.

The plaintiff argues that it complied with the statute because the claim was both written and verified within the statutory period. It contends the claim had been verified at the time it was filed on 10 May 1984 although the verification was not filed with the claim. We believe the plain words of the statute require that the verification be filed with the claim.

Affirmed.

Judge BECTON dissents.

Judge COZORT concurs.


Summaries of

E. F. Blankenship Co. v. N.C. Dept. of Transp

North Carolina Court of Appeals
Feb 1, 1986
79 N.C. App. 462 (N.C. Ct. App. 1986)
Case details for

E. F. Blankenship Co. v. N.C. Dept. of Transp

Case Details

Full title:E. F. BLANKENSHIP COMPANY v. NORTH CAROLINA DEPARTMENT OF TRANSPORTATION…

Court:North Carolina Court of Appeals

Date published: Feb 1, 1986

Citations

79 N.C. App. 462 (N.C. Ct. App. 1986)
339 S.E.2d 439

Citing Cases

Nello L. Teer Co. v. North Carolina Department of Transportation

(emphases added). In arguing that this statute involves a condition precedent, DOT relies upon C.W. Matthews…

E. F. Blankenship Co. v. N.C. Dept., Transportation

Appeal and Error 64 — evenly divided Court — decision affirmed without becoming precedent Where one member of…