Dinallo v. DAL Electric

Appellate Division of the Supreme Court of New York, Second Department
Mar 3, 2009
60 A.D.3d 620 (N.Y. App. Div. 2009)

Opinion

No. 2008-00129.

March 3, 2009.

In an action to recover damages for personal injuries, etc., the plaintiff's appeal from an order of the Supreme Court, Kings County (Kramer, J.), dated November 21, 2007, which granted the motion of the defendant Lehr Construction Corp. for leave to renew its prior motion for summary judgment dismissing the complaint insofar as asserted against it, which had been determined in an order dated September 18, 2007, and, upon renewal, granted the prior motion.

Longo D'Apice, Brooklyn, N.Y. (Mark A. Longo of counsel), for appellant.

Camacho Mauro Mulholland, LLP, New York, N.Y. (Eric L. Cooper of counsel), for respondent.

Before: Spolzino, J.P., Santucci, Balkin and Chambers, JJ.


Ordered that the order is affirmed, with costs.

Pursuant to an order dated September 18, 2007, this court dismissed the plaintiffs' claims based upon Labor Law § 200 and common-law negligence against the defendant DAL Electric and the defendant Thyssenkrupp Elevator ( see Dinallo v DAL Elec, 43 AD3d 981). On October 11, 2007, the defendant Lehr Construction Corp. (hereinafter Lehr) moved for leave to renew its motion for summary judgment dismissing the complaint insofar as asserted against it based upon a change in decisional law. In opposition, the plaintiff's contended, among other things, that Lehr's motion was untimely.

A motion for leave to renew is the appropriate vehicle for seeking relief from a prior order based on a change in the law (see CPLR 2221 [e] [2]). CPLR 2221 (e) (2) provides that a motion for leave to renew shall be based on new facts not offered on the original motion or "shall demonstrate that there has been a change in the law that would change the prior determination." A clarification of the decisional law is a sufficient change in the law to support renewal (see CPLR 2221 [e] [2]; Roundabout Theatre Co. v Tishman Realty Constr. Co., 302 AD2d 272).

Absent circumstances set forth in CPLR 5015, which are inapplicable here, a motion for leave to renew based upon a change in the law must be made prior to the entry of a final judgment or before the time to appeal has expired ( see Glicksman v Board of Educ./Cent. School Bd. of Comsewogue Union Free School Dist., 278 AD2d 364). Here, since Lehr made its motion prior to trial and prior to the entry of a final judgment, the Supreme Court correctly determined that the motion for leave to renew was timely.

The plaintiffs' remaining contentions are without merit.


Summaries of

Dinallo v. DAL Electric

Appellate Division of the Supreme Court of New York, Second Department
Mar 3, 2009
60 A.D.3d 620 (N.Y. App. Div. 2009)
Case details for

Dinallo v. DAL Electric

Case Details

Full title:STEPHEN DINALLO et al., Appellants, v. DAL ELECTRIC et al., Defendants…

Court:Appellate Division of the Supreme Court of New York, Second Department

Date published: Mar 3, 2009

Citations

60 A.D.3d 620 (N.Y. App. Div. 2009)
2009 N.Y. Slip Op. 1607
874 N.Y.S.2d 246

Citing Cases

Storper v. WL Ross & Co.

A motion for leave to renew a prior motion must be based upon "new facts not offered on the prior motion that…

Specialized Loan Servicing, LLC v. Chan

As is relevant to this motion, a motion for leave to renew ... "shall demonstrate that there has been a…