From Casetext: Smarter Legal Research

Dame v. Wood

Supreme Court of New Hampshire Belknap
Oct 6, 1908
70 A. 1081 (N.H. 1908)

Summary

In Dame v. Wood, 75 N.H. 38, 70 A. 1081, 1082, there was a contract to install a heating plant, but the building was destroyed by fire before the work was completed.

Summary of this case from Dermer v. Faunce

Opinion

Decided October 6, 1908.

Where complete execution of a contract for the installation of a heating plant has been rendered impossible without fault of either party, the contractor is entitled to compensation for labor performed and materials furnished, if both parties understood that the portions of the apparatus put in place in accordance with the contract were affixed to the realty and became the property of the owner thereof. A prevailing plaintiff in an action of assumpsit is in any event entitled to interest from the date of the writ, although his claim was for unliquidated damages.

ASSUMPSIT, to recover for labor performed and materials furnished under a contract for the installation of a heating plant in the defendant's dwelling-house. Trial by jury and verdict for the plaintiff for $512.38. Transferred from the November term, 1907 of the superior court by Stone, J.

The plaintiff contracted with the defendant to put into the latter's house a heating apparatus, consisting of a boiler, radiators, piping, and other appliances and fixtures, and the defendant agreed to pay $587.90 upon the completion of the work. When the plaintiff had affixed to the realty materials of the value of $466.38, by an expenditure of labor amounting to $46.80, the building and its contents were destroyed by fire.

The defendant excepted to the denial of his motions for a nonsuit and the direction of at verdict in his favor, and to the refusal of the court to give certain requested instructions. The defendant objected to an allowance of interest, on the ground that the action was for unliquidated damages. A verdict having been returned for the amount of the plaintiff's damages, it was agreed that interest should be computed thereon from the date of the writ, or from the date of judgment, in accordance with the decision of the supreme court.

Walter S. Peaslee and Cox Fowler, for the plaintiff.

Stephen S. Jewett, for the defendant.


The first time this case was before the court it was said the plaintiff could not recover unless he showed that the parties must have understood the heating apparatus was to be accepted from day to day as the work progressed. Dame v. Woods, 73 N.H. 222, 224. What must be intended by this is that he can recover if he shows that the boiler, radiators, and piping became a part of the defendant's real estate at the time they were put in place; for the theory of that decision is that the plaintiff cannot recover unless he proves he has conferred a benefit on the defendant. The only possible way to do that is to show that so much of the heating apparatus as was put in place before the fire was the defendant's property, because he neither has used nor can use it for the purpose for which it was intended. Therefore, the test of the defendant's liability is to inquire whether the different units that went to make up the completed heating plant became a part of the defendant's real estate when they were put in place. This depends on the intention of the parties (Dana v. Burke, 62 N.H. 627, 629) and is clearly a question of fact; but it does not follow that its determination raises an issue for the jury.

Both parties testified that they understood, "at the time the contract was made and thereafter, that from day to day as the work progressed, as fast as any portion of the boiler, piping, and radiators had been set up and connected in its proper place, it was not thereafter to be removed." They understood that when any part of the heating apparatus was put in place, it was affixed to the defendant's real estate and became his property if it was what the contract called for. That is, the parties testified that their intention as to when the different parts of the heating plant should become the property of the defendant was just what the court, in the first opinion, said it could be found to be, if it was found "that the removal of the boiler, radiators, and piping before they were destroyed by fire was not reasonably possible." The defendant does, not contend that the parts of the heating plant which had been installed were not what the contract called for; consequently the plaintiff is entitled to recover the value of the labor done and materials provided at the time of the fire, measured in the terms of the contract. Britton v. Turner, 6 N.H. 481.

The next question to be considered is the exception to the court's refusal to instruct the jury that the measure of damages was the amount the defendant was benefited by what the plaintiff had done. Although this may be sound as an abstract legal proposition, it was not error for the court to refuse to give it. As has been seen, the plaintiff was entitled to recover such a part of the contract price as the work and materials he had done and furnished was of the work and materials he agreed to perform and provide. This seems to have been the theory on which the question of damages was submitted to the jury.

The only other question to be considered is that of interest. It is the general rule that when no time is fixed for the payment of money due and owing it is payable on demand, and bears interest from and after a demand made. Morrill v. Weeks, 70 N.H. 178, 181. Consequently, the test to determine whether a claim carries interest before it is reduced to a judgment is not to inquire whether it is liquidated, but whether it is due; for interest is given as damages for the failure to pay money at the time it is due. Wright v. Company, ante, 3.

Exceptions overruled.

PARSONS, C. J., was in doubt: the others concurred.


Summaries of

Dame v. Wood

Supreme Court of New Hampshire Belknap
Oct 6, 1908
70 A. 1081 (N.H. 1908)

In Dame v. Wood, 75 N.H. 38, 70 A. 1081, 1082, there was a contract to install a heating plant, but the building was destroyed by fire before the work was completed.

Summary of this case from Dermer v. Faunce
Case details for

Dame v. Wood

Case Details

Full title:DAME v. WOOD

Court:Supreme Court of New Hampshire Belknap

Date published: Oct 6, 1908

Citations

70 A. 1081 (N.H. 1908)
70 A. 1081

Citing Cases

Anderson v. Shattuck

They had already performed a substantial part of the work they contracted to do, when the fire destroyed the…

White v. Schrafft

70 due the defendant, and disallowance of additional credits and payments claimed by the defendant (findings…