From Casetext: Smarter Legal Research

Craft v. Arkansas Louisiana Gas Co.

Court of Appeals of Arkansas
May 4, 1983
649 S.W.2d 409 (Ark. Ct. App. 1983)

Summary

holding that construction of a building over a gas line interfered with the use of an easement

Summary of this case from Campbell v. Carter

Opinion

No. CA 82-363

Opinion delivered May 4, 1983

1. JUDGMENTS — SUMMARY JUDGMENT — EXTREME REMEDY — WHEN PROPER TO GRANT. — Summary judgment is an extreme remedy and should be granted only when no genuine issue of fact exists. 2. APPEAL ERROR — APPEAL OF MOTION FOR SUMMARY JUDGMENT — STANDARD OF REVIEW. — On appeal of an order granting a motion for summary judgment, the appellate court reviews the evidence in the light most favorable to the party resisting the motion, and the burden is on the appellee to demonstrate that, even though the facts may be in dispute, reasonable minds could not differ as to the conclusion to be drawn from them. 3. VENDOR VENDEE — DUTY OF PURCHASER OF REAL PROPERTY TO TAKE NOTICE OF PRIOR RECORDED INSTRUMENTS IN CHAIN OF TITLE. — A purchaser of real property must take notice of all prior recorded instruments in the chain of title. 4. EASEMENTS — EASEMENT IS DOMINANT TENEMENT — LAND CONSTITUTES SERVIENT TENEMENT. — When an easement exists, it is the dominant tenement and the land constitutes the servient tenement. 5. EASEMENTS — ACCESSIBILITY PRIMARY INCIDENT OF EASEMENT FOR UNDERGROUND PIPELINE — BUILDING OVER PIPELINE CLEAR RESTRICTION OF RIGHT OF FULL ENJOYMENT. — One of the primary incidents of an easement for an underground pipeline is that the line be accessible for maintenance and repair; hence, the construction of a building over a gas line is a hindrance to access for maintenance and repair and a clear restriction on the right of full enjoyment. 6. EASEMENTS — CONSTRUCTIVE NOTICE THAT EASEMENT EXISTED — ACTUAL NOTICE NOT REQUIRED. — Where an easement was recorded and was in the purchasers' chain of title, they had constructive notice that the easement existed, and actual notice is not required; thus, any alleged violations of the Arkansas Pipeline Code were irrelevant to the issue of notice under the facts presented. 7. JUDGMENTS — RENEWAL OF MOTION FOR SUMMARY JUDGMENT ON DAY OF TRIAL NOT PREJUDICIAL ERROR UNDER CIRCUMSTANCES. — It was not prejudicial error for the appellee to renew a motion for summary judgment on the day of trial where the motion and the arguments of counsel were the same as previously submitted. 8. JUDGMENTS — SUMMARY JUDGMENT — RECONSIDERATION NOT ERROR. — It is not error for the trial court to reconsider and grant a motion for summary judgment after overruling it at an earlier date.

Appeal from Craighead Circuit Court, Western District; Gerald Pearson, Judge; affirmed.

R. James Lyons, for appellants.

Wallace, Hilburn, Clayton, Calhoon Forster, Ltd., by: Janet L. James, for appellee.


This is an appeal from the granting of the appellee's motion for summary judgment. The appellee filed suit for damages against the appellants for the cost of relocating the appellee's gas line. The gas line allegedly had to be relocated because the appellants had constructed a large building directly over the line, creating a risk of explosion and difficulty in maintenance. The trial court granted the appellee's motion for summary judgment on the issue of liability, reserving the question of damages for the jury. From the order granting the summary judgment, comes this appeal.

The appellants contend that the trial court erred in granting the motion for summary judgment because reasonable minds might differ as to the conclusions to be drawn from the facts in this case. Summary judgment is an extreme remedy and should be granted only when no genuine issue of fact exists. Purser v. Corpus Christi State Nat'l Bank, 258 Ark. 54, 522 S.W.2d 187 (1975). In Davis v. Lingl Corp., 277 Ark. 303, 641 S.W.2d 27 (1982), the Arkansas Supreme Court stated:

[a] summary judgment is appropriate only where the pleadings, depositions and answers to interrogatories, together with the affidavits, show there is no genuine issue as to any material fact, and the moving party is entitled to a judgment as a matter of law. Rule 56, ARCP; Turner v. Baptist Medical Center, 275 Ark. 424, 631 S.W.2d 275 (1982).

In considering an order granting a motion for summary judgment, the trial court may search and review the entire record to determine whether the grant the motion. Purser, supra.

On appeal of an order granting a motion for summary judgment, we review the evidence in the light most favorable to the party resisting the motion. Bourland v. Title Ins. Co. of Minnesota, 4 Ark. App. 68, 627 S.W.2d 567 (1982). See also Dodrill v. Arkansas Democrat Co., 265 Ark. 628, 590 S.W.2d 840 (1979). The burden is on the appellee to demonstrate that, even though the facts may be in dispute, reasonable minds could not differ as to the conclusion to be drawn from them. Henricks v. Burton, 1 Ark. App. 159, 613 S.W.2d 609 (1981).

On October 31, 1967, the appellee was assigned an easement on the property later purchased by the appellants. This easement was properly recorded in the office of the Craighead County Circuit Clerk and Ex Officio Recorder's Office. The appellee thereafter maintained an active gas line within the recorded easement. On September 20, 1976, the appellant, Jerry B. Craft, purchased the property subject to the easement. Subsequently, the appellants constructed a building over the active gas line operated by the appellee. Upon discovering the building, the appellee capped the existing line located under the building and rerouted the line due to the potentially dangerous situation of having a building constructed over an active gas line. The appellee then filed suit for damages as a result of the relocation of the gas line.

The appellants argue that fact questions existed concerning the extent of the easement, the provisions of the easement document, and whether there was an unreasonable interference with the gas line. We do not agree.

The document containing the easement was properly filed in the Craighead County Circuit Clerk and Ex Officio Recorder's Office. It has long been recognized that a purchaser of real property must take notice of all prior recorded instruments in his chain of title. White v. Moffett, 108 Ark. 490, 158 S.W. 505 (1913). See also Union Sawmill Co. v. Rowland, 178 Ark. 372, 10 S.W.2d 858 (1928). When an easement exists, it is the dominant tenement and the land constitutes the servient tenement. Natural Gas Pipeline Co. of America v. Cox, 490 F. Supp. 452 (E. D. Ark. 1980). In Hatfield v. Arkansas Western Gas Co., 5 Ark. App. 26, 632 S.W.2d 238 (1982), we stated that:

[t]he rule in this state is that the owner of an easement may make use of the easement compatible with the authorized use so long as the use is reasonable in light of all facts and circumstances of the case. Massee v. Schiller, 243 Ark. 572, 420 S.W.2d 839 (1967). In the case of underground pipelines it would appear that one of the primary incidents of the easement is that the line be accessible for maintenance and repair. Without such rights the easements could become useless. The chancellor found that building over a gas line is a hindrance to access for maintenance and repair and a clear restriction on the right of full enjoyment.

After reviewing the record we find that the trial court did not err in granting the appellee's motion for summary judgment on the issue of liability. The appellants had constructive notice that the easement existed because the documents were in their chain of title. Actual notice is not required and thus any alleged violations of the Arkansas Pipeline Code were irrelevant to the issue of notice under the facts presented. Further, we cannot say that reasonable minds would differ on the issue of whether the construction of a building over an active gas line interfered with the use of the easement. Hatfield, supra.

The appellants argue that the trial court also erred in granting the motion for summary judgment because it was untimely filed and resulted in prejudice to the appellants. The record indicates that the motion was originally filed on October 22, 1981, and argued before Judge Olan Parker on December 18, 1981. The motion was subsequently denied. On the day of trial, April 9, 1982, the appellee renewed its motion before Judge Gerald Pearson. The motion was granted on the issue of liability, reserving the question of damages for the jury. The appellants argue that the renewal of the motion on the date of trial violated Rule 56 of the Arkansas Rules of Civil Procedure, which states that the motion must be served at least ten days before a hearing is held. The purpose of the ten day requirement is to allow the nonmoving party time to prepare a response. Purser v. Corpus Christi State Nat'l Bank, supra. In the case at bar, the appellee submitted the same motion on the day of trial that it had previously submitted and the arguments of counsel appear from the record to have been the same. The appellants argue that the law of the case should govern and that once the motion was denied it could not be reconsidered. We disagree. In Farmers Mutual Ins. Co. v. Lane, 278 Ark. 53, 643 S.W.2d 544 (1982), the Arkansas Supreme Court stated:

[l]astly, appellant argues that the trial court erred in reconsidering appellees' motion for summary judgment after overruling it at an earlier date. The record reflects the trial court reversed himself on the motion for summary judgment after hearing argument of counsel. We find no error.

In Purser v. Corpus Christi State Nat'l Bank, supra, the Court stated that the notice requirements of Rule 56 of the Federal Rules of Civil Procedure are intended to provide an opportunity for the opposing party to adequately prepare a response. However, the Court noted that Arkansas has never held that a trial court is without jurisdiction to grant a motion for summary judgment within the ten day period if "the party against whom the judgment is rendered is not prejudiced."

Rule 56 of the Federal Rules of Civil Procedure is identical to Rule 56 of the Arkansas Rules of Civil Procedure.

The term "prejudiced" as used in this context should be interpreted to mean that the nonmoving party is not allowed time to adequately prepare a response. In the case at bar, it can hardly be said that the appellants were surprised by the issues raised by the reconsideration of the motion. The parties had previously argued the issues before the court and no new grounds were relied upon by the appellee. Thus, assuming, although not deciding, that the ten day notice period had not previously been complied with by the appellee, the reconsideration of the motion did not prejudice the appellants. Therefore, we find no error by the trial court in reconsidering the motion for summary judgment on the day of trial.

Affirmed.


Summaries of

Craft v. Arkansas Louisiana Gas Co.

Court of Appeals of Arkansas
May 4, 1983
649 S.W.2d 409 (Ark. Ct. App. 1983)

holding that construction of a building over a gas line interfered with the use of an easement

Summary of this case from Campbell v. Carter
Case details for

Craft v. Arkansas Louisiana Gas Co.

Case Details

Full title:Jerry B. CRAFT, d/b/a CRAFT REALTY COMPANY, and Jerry B. CRAFT, An…

Court:Court of Appeals of Arkansas

Date published: May 4, 1983

Citations

649 S.W.2d 409 (Ark. Ct. App. 1983)
649 S.W.2d 409

Citing Cases

Scroggin v. Scroggin

The point of the rule's timetable is to give the parties adequate time to brief and argue a potentially…

Campbell v. Carter

We noted that, in the case of underground pipelines, "it would appear that one of the primary incidents of…