From Casetext: Smarter Legal Research

Colonial Sur. Co. v. N.Y.C. Hous. Auth.

Appellate Division of the Supreme Court of the State of New York
Apr 30, 2020
182 A.D.3d 517 (N.Y. App. Div. 2020)

Opinion

11430 Index 656347/16

04-30-2020

COLONIAL SURETY COMPANY, Plaintiff–Appellant, v. NEW YORK CITY HOUSING AUTHORITY, Defendant–Respondent.

McElroy, Deutsch, Mulvaney & Carpenter, LLP, New York (Adam R. Schwartz of counsel), for appellant. Kelly D. MacNeal, New York (Gil Nahmias of counsel), for respondent.


McElroy, Deutsch, Mulvaney & Carpenter, LLP, New York (Adam R. Schwartz of counsel), for appellant.

Kelly D. MacNeal, New York (Gil Nahmias of counsel), for respondent.

Friedman, J.P., Kapnick, Webber, Oing, JJ.

Order, Supreme Court, New York County (Gerald Lebovits, J.), entered August 27, 2018, which granted defendant New York City Housing Authority's (N.Y.CHA's) CPLR 3211(a)(1) motion to dismiss the complaint, unanimously affirmed, without costs.

In support of its motion, NYCHA submitted documentary evidence showing that plaintiff Colonial Surety Company failed to timely notify NYCHA of its equitable adjustment claim. Section 23 of the construction contract between plaintiff's obligee (non-party Pioneer General Construction Company, LLC) and NYCHA required that plaintiff, as Pioneer's surety, file a notice of claim within 20 days after its accrual. Here, plaintiff's claim accrued on September 3, 2013, when NYCHA notified plaintiff that it intended to substantially reduce Pioneer's scope of work under the contract, and reduced the contract price by $2,053,800. Plaintiff's damages were ascertainable as of that point (see C.S.A. Contr. Corp. v. New York City School Constr. Auth. , 5 N.Y.3d 189, 192, 800 N.Y.S.2d 123, 833 N.E.2d 266 [1st Dept. 2005] ). We note that plaintiff's notice of claim would still have been untimely even if accrual was calculated from July 2015, when it substantially performed on the contract, or January 7, 2016, the date of submission of the final payment requisition to NYCHA, reflecting the reduction in the contract price ( id. ; see also D & L Assoc., Inc., v. New York City School Constr. Auth. , 69 A.D.3d 435, 436, 894 N.Y.S.2d 14 [1st Dept. 2010] ). Plaintiff did not file a notice of claim until March of 2016, years after NYCHA reduced the contract's scope of work and months after its final payment requisition.

NYCHA's submissions also establish that plaintiff's plenary action is barred by Section 20 of the construction contract, which precludes contractors from commencing such an action for damages upon a determination by the City that the contractor had defaulted under the contract (see Cal–Tran Assoc., Inc. v. City of New York , 43 A.D.3d 727, 841 N.Y.S.2d 445 [1st Dept. 2007] ; see also Sound Beyond Elec. Corp. v. City of New York , 100 A.D.3d 412, 413, 952 N.Y.S.2d 887 [1st Dept. 2012] ). Plaintiff's remedy under the contract was to commence an Article 78 proceeding challenging the default determination before bringing its claim for equitable adjustment.

We have considered plaintiff's remaining arguments and find them unavailing.


Summaries of

Colonial Sur. Co. v. N.Y.C. Hous. Auth.

Appellate Division of the Supreme Court of the State of New York
Apr 30, 2020
182 A.D.3d 517 (N.Y. App. Div. 2020)
Case details for

Colonial Sur. Co. v. N.Y.C. Hous. Auth.

Case Details

Full title:Colonial Surety Company, Plaintiff-Appellant, v. New York City Housing…

Court:Appellate Division of the Supreme Court of the State of New York

Date published: Apr 30, 2020

Citations

182 A.D.3d 517 (N.Y. App. Div. 2020)
2020 N.Y. Slip Op. 2543
120 N.Y.S.3d 772

Citing Cases

Universal Constr. Res., Inc. v. N.Y.C. Hous. Auth.

The Clerk is directed to enter judgment dismissing the complaints. NYCHA made out a prima facie entitlement…

R.S.N. Constr. Co. v. N.Y.C. Hous. Auth.

It is well settled that a contractor's claim accrues when its damages are ascertainable (Colonial Surety…