From Casetext: Smarter Legal Research

Colberg v. Sebastian

Court of Appeals of Indiana
Feb 25, 1943
113 Ind. App. 94 (Ind. Ct. App. 1943)

Opinion

No. 16,970.

Filed February 25, 1943.

1. CONTRACTS — Action for Breach — Evidence — Performance Prevented by Defendant — Recovery of Contract Price Less Cost of Completing Work. — In a contractor's action to enforce a mechanic's lien for labor and materials furnished in repairing defendant's home, evidence that after the work was under progress defendant delayed the work by not making up her mind on color of paints, refused to select wallpaper and bathroom tile, ordered the contractor's employees from the premises, together with other facts shown, was sufficient to sustain the finding that the contractor had been prevented from completing the contract and that he was entitled to recover the contract price less cost of completion of the work. p. 97.

2. CONTRACTS — Actions for Breach — Pleading — Denomination of Action Immaterial. — Where a contractor was prevented by defendant from completing a contract to repair defendant's home, whether contractor's action, to enforce a mechanic's lien and for foreclosure, was called an action on the contract or a common count for work, labor, and materials is of no importance under Indiana code which requires only a statement of the facts which will entitle plaintiff to recover. p. 98.

3. CONTRACTS — Actions for Breach — Pleading — Action on Special Contract — Recovery on Quantum Meruit. — A contractor who brought suit on a special contract for furnishing materials to defendant was not precluded from recovering on a quantum meruit, where the evidence showed that the contractor had been prevented from completing his contract by the defendant, for, under such circumstances, the contractor could recover on the quantum meruit for such materials furnished, but not to exceed the contract price. p. 98.

4. APPEAL — Presentation in Lower Court of Grounds of Review — Issue Not Raised by Special Pleading — Effect. — Where an issue is not raised by special pleading before the trial court, the Appellate Court will not pass upon it. p. 99.

5. DAMAGES — Measure of Damages — Breach of Contract to Repair Property — Performance Prevented by Defendant. — Where a contractor entered into a contract with defendant to furnish labor and materials in making repairs to defendant's property, but was prevented from completing the contract by the defendant, the contractor may recover the contract price, less the estimated cost of completing the same. p. 99.

From the Marion Superior Court; Joseph T. Markey, Judge.

Action by Lewis B. Sebastian, doing business as Sebastian Sales Company, against Nellie E. Colberg to recover an amount due under a contract for the repair of certain property and to foreclose a mechanic's lien. From a judgment for plaintiff, defendant appealed.

Affirmed. By the court in banc.

Linder, Seet Rigot and James E. McDonald, all of Indianapolis, for appellant.

Owen S. Boling, Harry C. Hendrickson, and Leland Rees, all of Indianapolis, for appellee.


Appellee, contractor and materialman, brought suit against appellant, owner, for enforcement of mechanic's lien against real estate and for foreclosure. Appellee's complaint was in two paragraphs, to which appellant filed no answer or cross-action. The parties having gone to trial without the issues having been closed the complaint will be deemed to have been controverted by a denial under the rules of pleading prevailing at the time (1938). The trial resulted in a judgment in favor of appellee in the amount of $750.00 together with attorney's fee in the amount of $100.00 and a foreclosure of the lien.

Error assigned is the overruling of appellant's motion for a new trial.

In the early part of 1936, appellant made application to the Home Owners Loan Corporation, hereinafter referred to as the Corporation, for a loan, which application was granted. One of the requirements of the Corporation was that certain repairs should be made to the property involved before the loan could be closed. A list of such repairs was submitted by the Corporation to prospective bidders and appellee submitted, on a bid form supplied by the Corporation, the successful bid. Appellee therein agreed to furnish labor and materials for the repairs to and alterations of the dwelling house and garages situated on the real estate for the sum of $1,265.00. Appellee, in his bid, agreed to be bound by a contract appended thereto which contained several provisions, those pertinent to the issues here being:

1. Work was to begin within three days after notice of acceptance by the Corporation and to be completed within 40 days thereafter. (Note: The record does not disclose the date of acceptance, but appellee's bid is dated February 17th, 1936.)

2. Work was to be done in a substantial and workmanlike manner and contractor was to obtain and deposit with the Corporation satisfactory releases of liens and claims for liens of contractors, subcontractors, laborers, materialman, etc.

3. Work was to be done to the satisfaction and approval of the Corporation.

4. The Corporation was to hold, in escrow deposit, the amount of the bid, i.e., $1,265.00 and to pay same to appellee upon completion of the work in a manner satisfactory to the Corporation.

A disagreement having arisen between appellee and appellant as to the quality of some of the work and as to the alleged failure of appellee to perform certain portions thereof, the Corporation refused to pay over the amount of the escrow deposit and still holds same.

On September 24, 1937, and within sixty days after furnishing certain labor and materials appellee filed notice of his intention to hold a lien on the premises for the amount due. The amount was not paid, whereupon appellee brought his action in the court below.

Specifications 3, 4, 5, 6 and 7 of appellant's motion for new trial relate to alleged erroneous reception of evidence by the trial court over appellant's objection. We find no error here.

In considering appellant's remaining specifications, i.e., the decision of the court is not sustained by sufficient evidence; and, the decision of the court is contrary to law, the 1. evidence most favorable to appellee discloses that appellee was approved as contractor by the Corporation; that the work was to be performed to the satisfaction of the Corporation and not the owner; that appellee did certain work and furnished certain materials which were applied to the real estate here involved and that during the progress of the work it was inspected many times by engineers and inspectors of the Corporation who made only minor objections and criticisms and that appellee took prompt steps to remedy such objections when they were called to his attention; that appellant, owner, had difficulty in making up her mind as to selections of paint, wallpaper, etc., and on one occasion an inspector spent a half day with appellee's painters and appellant attempting to obtain a color combination to suit appellant; that the work was delayed many times by appellant's objections and criticisms, her refusals to permit the work to proceed and her demands for alterations and departures from the contract provisions; that appellant insisted on complete retiling of bathrooms when the contract provision was for replacement of missing and broken tile; that appellant refused to make a selection of wall paper, thereby delaying the work of papering; that by reason of her refusal to select wall paper and bathroom tile the appellee was unable to complete the work of papering and retiling and that this portion of the work was still uncompleted at the time of the trial in the court below; that appellant refused to proceed to arbitration in conformity with arbitration provisions of the contract; that appellant ordered appellee's employees off the premises on several occasions; that appellee was ready and willing to complete the work and willing to proceed to arbitration but that appellant refused; that appellee expended $1,525.18 on the work whereas the contract price thereof was $1,265.40; that the estimated cost of completing the work was from $496.00 to $625.00; that the Corporation still holds in escrow the deposit of $1,265.40, no part of which has been paid to appellee.

We are of the opinion that the evidence was sufficient to sustain the finding of the trial court.

Appellant urges that appellee, having declared upon a special contract in the trial court, could not recover on an implied contract. This contention, we believe is not supported by 2. the authorities. Whether the action is called an action on the contract or a common count for work and labor and material is of no importance under our Code, which requires only a statement of the facts which will entitle the plaintiff to recover. Western Wheeled Scraper Co. v. Scott Const. Co. (1940), 217 Ind. 408, 417, 27 N.E.2d 879.

Appellant also contends that appellee, having sued on a special contract, could not recover on a quantum meruit. This point is not well taken. It has been held that where one enters into 3. a special contract to furnish materials to another and is prevented from completing his contract by the other party he may recover for the materials furnished on the quantum meruit not to exceed the contract price. French v. Cunningham (1898), 149 Ind. 632, 49 N.E. 797; Cullen-Friestedt Co. v. Turley (1912), 50 Ind. App. 468, 97 N.E. 946.

Appellant also points out the lien release clauses in the contract and claims that these operate as waivers of lien on the part of appellee. This we do not pass upon for the reason 4. that such issue was not raised by special pleadings before the trial court. Baldwin, etc., Works v. Edward Hines Lumber Co. (1920), 189 Ind. 189, 125 N.E. 400, 40 C.J. 439, § 607.

Although the evidence in the instant case is somewhat conflicting, it seems clear to this court that appellee was prevented from carrying out and completing his contract by 5. the appellant. The amount of recovery could be measured by the contract price less the estimated cost of completing same. The amount awarded by the trial court was well within this limitation.

The decision of the court below was not contrary to law.

Affirmed.

NOTE. — Reported in 46 N.E.2d 716.


Summaries of

Colberg v. Sebastian

Court of Appeals of Indiana
Feb 25, 1943
113 Ind. App. 94 (Ind. Ct. App. 1943)
Case details for

Colberg v. Sebastian

Case Details

Full title:COLBERG v. SEBASTIAN

Court:Court of Appeals of Indiana

Date published: Feb 25, 1943

Citations

113 Ind. App. 94 (Ind. Ct. App. 1943)
46 N.E.2d 716

Citing Cases

Ind. Tri-City Plaza B. v. Estate of Glueck

These cases are distinguishable on their facts. Colberg v. Sebastian (1943), 113 Ind. App. 94, 46 N.E.2d 716;…

Ind. Mich. Elec. v. Terre Haute Indus

Estate of Glueck, supra. Profit is the contract price less cost. Id.; Foster v. United Home Improvement Co.…