From Casetext: Smarter Legal Research

City of Pgh. et al. v. Pa. P.U.C. et al

Commonwealth Court of Pennsylvania
Aug 14, 1979
404 A.2d 786 (Pa. Cmmw. Ct. 1979)

Opinion

Argued March 6, 1979

August 14, 1979.

Pennsylvania Public Utility Commission — Allocation of costs of relocating facilities — Public Utility Law, Act 1937, May 28, P.L. 1053 — Retroactive application of statutory amendments — Reconstruction of rail crossing — Contractual agreement to allocate costs — Jurisdiction — Abandonment of tracks — Conditions of contract.

1. Prior to amendments in 1963 to the Public Utility Law, Act 1937, May 28, P.L. 1053, non-transportation utilities were required to bear the cost of relocating their facilities when required to do so by governmental exercise of the police power in constructing a throughway, and amendments permitting the allocation of such expense between the utility and the governmental unit have no retroactive application to a project completed, except for the allocation of expenses, prior to the effective date of the statutory amendments. [84-5]

2. Under the Public Utility Law, Act 1937, May 28, P.L. 1053, the Pennsylvania Public Utility Commission has authority to allocate costs of relocation of track in the reconstruction of a crossing between the public utility involved, and the concerned municipality or the Commonwealth, unless it is established that such parties have already agreed to a certain allocation between themselves and have made payment for the reconstruction under the terms of that contract. [86-7]

3. The Public Utility Commission does not lose jurisdiction over tracks or a crossing so as to prevent it from allocating costs involved in their relocation or reconstruction merely because the tracks or crossing may be unused, as the Commission retains jurisdiction until permission to abandon operation of the tracks is sought and granted by the Commission. [87-8]

4. The Pennsylvania Public Utility Commission will allocate costs of reconstructing a crossing although an agreement may exist between parties as to liability for costs, when the contract is conditional and the conditions have not been shown by the parties to have been fulfilled. [88]

Argued March 6, 1979, before President Judge BOWMAN and Judges CRUMLISH, JR., WILKINSON, JR., MENCER, ROGERS and MacPHAIL. Judges BLATT, DiSALLE and CRAIG did not participate.

Appeal, No. 30 C.D. 1978, from the Order of the Pennsylvania Public Utility Commission in cases of Application of the City of Pittsburgh for approval of the construction of the crossings where (1) the Liberty-Crosstown Thoroughfare and ramps thereof will cross below the grade of the tracks of Pittsburgh Railways Company located in the bed of Wylie Avenue as relocated, (2) the same Thoroughfare will cross above grade of Fifth Avenue and (3) the same Thoroughfare and ramps thereof will cross above the grade of the tracks of said company located in the beds of Forbes Street and Sixth Avenue, respectively, all in the City of Pittsburgh, Allegheny County, and the allocation of the costs and expenses incident thereto, Application Docket No. 83297; Application of Pittsburgh Railways Company for approval of the amendment of the charter and acceptance of franchises from the City of Pittsburgh authorizing the construction of street railway track and related facilities in the Lower Hill District of the City of Pittsburgh, Allegheny County, Application Docket No. 85375; Application of Pittsburgh Railways Company for approval of the abandonment or discontinuance of service, rights, powers, franchises or privileges in the Lower Hill District of the City of Pittsburgh, Allegheny County, Application Docket No. 85376; and City of Pittsburgh v. Pittsburgh Railways Company, Complaint Docket No. 16928.

Applications with the Pennsylvania Public Utility Commission for construction and alteration of crossing. Approval granted. Relocations of facilities ordered. Hearings held on allocation of costs. Order entered. City of Pittsburgh and Urban Redevelopment Authority of Pittsburgh appealed to the Commonwealth Court of Pennsylvania. Held: Affirmed as modified.

Marvin A. Fein and John O. Wicks, with them, Mead J. Mulvihill, Jr., City Solicitor; and John E. Fullerton, for petitioners.

Edward J. Morris, Harry H. Frank and Louis G. Cocheres, Assistant Attorney General, with them, Herbert G. Zahn, Assistant Attorney General; Robert W. Cunliffe, Deputy Attorney General; Gerald Gornish, Acting Attorney General; Candace N. Kreiger, Assistant Counsel; John B. Wilson, Assistant Counsel; Kathleen Herzog Larkin, Chief Counsel; Gerard F. Hickel; and Walter T. Wardzinski, for respondents.


The City of Pittsburgh and Urban Revelopment Authority of Pittsburgh appeal from an order of the Pennsylvania Public Utility Commission which required the City to reimburse Duquesne Light Company and Pittsburgh Railways Company (PRC) for expenses incurred in relocation resulting from the construction of the Liberty-Crosstown Thoroughfare.

In 1956 the City requested Commission approval to construct crossings where the proposed thoroughfare would cross street railway tracks of the PRC. Commission approval was granted on May 12, 1958, and PRC was ordered to relocate, as were all public utilities which would interfere with construction. Hearings on the allocation of costs surrounding this redevelopment project were not completed until September 23, 1975. The Commission entered its final order on December 12, 1977, resulting in this appeal.

City of Pittsburgh — Duquesne Light Company

Pursuant to the Commission order of May 12, 1958 and amendments thereto, Duquesne Light Company (Duquesne) was compelled to relocate its facilities in the construction area. Hearings on the allocation of costs for the relocation were completed September 23, 1975, and by final order the City was compelled to pay Duquesne 50% of the relocation costs. The City requests reversal of this allocation and we reverse.

The Commission approved the City's planned crossings and ordered:

That any relocation of, changes in, or removal of any adjacent structures, equipment, or other facilities of any public utility, other than Pittsburgh Railways Company, which may be required as incidental to the alteration, relocation or construction of the crossings herein ordered in A.83297 and C.16928, be made by said public utility in such a manner as will not interfere with the construction of the improvement.

The City correctly argues that, prior to 1963, it was a well-settled policy of the law that non-transportation public utilities bear the expenses of relocating their facilities when the relocation is brought about by governmental exercise of the police power such as in construction, relocation, alteration, protection or abolition of a highway-rail crossing. Delaware River Port Authority v. Pennsylvania Public Utility Commission, 393 Pa. 639, 145 A.2d 172 (1958).

It is equally clear that on July 3, 1963, the legislature amended Section 411(a) of the Public Utility Law, thereby conferring specific authority to allocate such expenses.

Act of May 28, 1937, P.L. 1053, as amended, 66 P. S. § 1181. The former Public Utility Law has since been repealed by the Act of July 1, 1978, P.L. 598; a similar provision is now found in the Public Utility Code, 66 Pa. C.S. § 2704.

In its order dated December 12, 1977, the Commission stated:

With respect to the 1963 amendment to Section 411 of the Public Utility Law, 66 P. S. § 1181, whereby the legislature empowered the Commission to allocate relocation expenses incurred for non-carrier public utility facilities at or adjacent to a crossing site, this Commission need not be concerned with whether the actual relocation work commenced prior to the 1963 amendment. The legislature clearly intended by the 1963 amendment to expand the scope of this Commission's allocation power and imposed no restriction on this power by requiring the involved work to be initiated and completed after 1963. Accordingly, we hereby determine and conclude that this Commission has the power in this proceeding to allocate costs incurred for the alteration or relocation of fixed utility facilities located at or adjacent to the involved crossing.

We would be applying the act retroactively were we to accept the Commission's interpretation of the legislative grant of authority. That a retroactive application of the act was not intended is evidenced by the absence of language to that effect.

The Pennsylvania Supreme Court has stated it to be a fundamental rule of statutory construction that "statutes, other than those affecting procedural matters, must be construed prospectively except where the legislative intent that they shall act retroactively is so clear as to preclude all questions as to the intention of the legislature. . . . This principle has been promulgated as law by our legislature in 1 Pa. C.S. § 1926. . . ." (Citations omitted.) Costa v. Lair, 241 Pa. Super. 517, 519, 363 A.2d 1313, 1314 (1976).

Appellants counter that the Commission is merely applying the Act prospectively, in that the allocation of costs occurred after the amendment's effective date. In the instant case, all events affecting substantive rights occurred prior to the amendment. The Commission had approved the project, the City commenced construction in reliance on the order at a time when they had no legal duty to incur non-transportation utility relocation expenses, the utility actually relocated and put its new facilities into service prior to the effective date of the amendment. The only event occurring post-amendment was the actual allocation of expenses by the Commission. Applying the statute to this factual situation would clearly be an unauthorized retroactive application.

The Commission's order of December 12, 1977 included this finding which is supported by substantial evidence:

32. The relocated facilities of Duquesne Light Company, in the vicinity of the entire improvement, were placed in service by June 22, 1961, according to the company witness.

City of Pittsburgh — PRC I

The Commission's final order required the City to reimburse PRC $307,957.12, without prejudice to either party's contractual rights, for relocation expenses incurred in removing and relocating track facilities pursuant to prior order. The City argues in effect that the Commission lacked jurisdiction to make this allocation and that, by so doing, it abrogated the pre-existing contractual rights of the parties. We disagree.

Section 411(a) of the Public Utility Law provides in pertinent part:

Such compensation, as well as the expense of such construction, relocation, alteration, protection, or abolition of any crossing, shall be borne and paid, as hereinafter provided, by the public utilities or municipal corporations concerned, or by the Commonwealth, in such proper proportions as the Commission may, after due notice and hearing, determine, unless such proportions are mutually agreed upon and paid by the interested parties. (Emphasis added.)

"It has been held, therefore, that where the parties have (1) allocated the cost of such reconstruction between themselves by contract, and (2) have paid for the reconstruction in accordance with the terms of the contract, the PUC does not have the power to abrogate that contract by ordering one party to reimburse the other party in proportionate amounts contrary to those as provided in the contract. City of Philadelphia v. Pennsylvania Public Utility Commission, 449 Pa. 402, 296 A.2d 804 (1972)." Pennsylvania Public Utility Commission v. Southeastern Pennsylvania Transportation Authority, 21 Pa. Commw. 106, 109, 343 A.2d 371, 373 (1975). The record is devoid of evidence that either of the prerequisites which would bar Commission authority to allocate costs without prejudice is present.

All expenditures made by PRC were from funds advanced by a third party and all parties, including PRC and the City, by agreement dated December 31, 1957, specifically agreed:

(4) That the money being paid by Auditorium to Railways pursuant to paragraph A(1) hereof will be applied by Railways only to the payment of costs of relocation referred to in Paragraph D(5) hereof and that Auditorium will be reimbursed therefor by the party or parties ultimately determined to bear legal responsibility for such costs.

The Commission order is clearly warranted and in line with Southeastern Pennsylvania Transportation Authority, supra.

II

The City next argues that even if the Commission could allocate costs without abrogating contracts, it could not assume jurisdiction over abandoned or unused crossings. This argument is premised on the contention that PRC's president testified that some of the tracks or crossings which the City by ordinance ordered PRC to relocate were not in use at the time of the relocation. The City would unduly restrict the jurisdiction of the Commission.

The Superior Court case of Jennings v. Pennsylvania Public Utility Commission, 140 Pa. Super. 569, 14 A.2d 882 (1940), relied upon by appellants, is not here applicable. In Jennings, supra, a railway company abandoned railway tracks after receiving permission to abandon by the state public utility authorities. The authority, some time later, ordered the railroad to remove its tracks but the Court reversed, reasoning that once the Commission gives permission to abandon and, when actually carried into effect, that it cannot rescind the permission to abandon. The instant facts do not concern abandoned rights of way since the Commission retains jurisdiction over a crossing until permission to abandon operation of the tracks is sought and granted by the Commission. The tracks involved were owned by an operating street railway company and their removal was a reasonable part of a single integrated project involving several crossings.

City of Pittsburgh — PennDOT

The City argues that the Commission erred by not ordering PennDOT to reimburse the City as per a prior agreement between the parties which reads:

(B) The Commonwealth agrees

. . . .

2. That it will reimburse the City for any track relocation costs, solely attributable to the construction of the Wylie Avenue Bridge, which the City may be required to pay to the Pittsburgh Railways Company.

Having previously discussed Commission authority to allocate costs without prejudice in the absence of mutual agreement as to the proportions of liability, we need merely point out that a pre-condition to the above quoted agreement is a determination of the costs solely attributable to the Wylie Avenue Bridge which the City has failed to show. The City may proceed with its contract claim in a proper forum as we find no error with the Commission's order.

Accordingly, we

ORDER

AND NOW, this 14th day of August, 1979, the order of the Pennsylvania Public Utility Commission entered December 12, 1977, requiring the City of Pittsburgh to pay Duquesne Light Company a sum or sums of money equal to fifty (50%) percent of the cost the company incurred in relocating pursuant to Commission order is reversed. The order in all other respects is affirmed.


Summaries of

City of Pgh. et al. v. Pa. P.U.C. et al

Commonwealth Court of Pennsylvania
Aug 14, 1979
404 A.2d 786 (Pa. Cmmw. Ct. 1979)
Case details for

City of Pgh. et al. v. Pa. P.U.C. et al

Case Details

Full title:City of Pittsburgh and Urban Redevelopment Authority of Pittsburgh…

Court:Commonwealth Court of Pennsylvania

Date published: Aug 14, 1979

Citations

404 A.2d 786 (Pa. Cmmw. Ct. 1979)
404 A.2d 786

Citing Cases

Equitable Gas Co. v. Pa. P.U.C

The omitted footnote refers the reader interested in the allocation of costs in non-highway project cases…

PECO Energy Co. v. Pennsylvania Public Utility Commission

We determined that the 1963 amendment was enacted in response to our decision in Delaware River Port…