This matter arises on the Joint Motion to Amend Scheduling Order [Doc. # 50, filed 1/26/2011] (the "Motion for Extension"). The Motion for Extension demonstrates good cause justifying the relief sought, but the parties are cautioned that further extensions do not appear to be possible.
IT IS ORDERED that the Motion for Extension [Doc. # 50] is GRANTED, and the case schedule is modified to the following extent: April 25, 2011
Discovery Cut-Off:(All discovery must be completed by the discovery cut-off. All written discovery must be served so that responses are due on or before the discovery cut-off.)May 16, 2011 Dispositive Motions Deadline:
Expert Disclosures:
(a) The parties shall designate all experts and provide opposing counsel with all information specified in Fed.R.Civ.P. 26(a)(2) on or before March 14, 2011
(b) The parties shall designate all rebuttal experts and provide opposing counsel with all information specified in Fed.R.Civ.P. 26(a)(2) on or before April 11, 2011
Final Pretrial Conference: The final pretrial conference set for May 6, 2011, at 9:00 a.m., is VACATED and RESET to August 1, 2011, at 8:30 a.m., in Courtroom 401, 4th floor, Alfred A. Arraj United States Courthouse, 901 19th Street, Denver, Colorado. A Final Pretrial Order shall be prepared by the parties and submitted to the court no later than July 25, 2011.