From Casetext: Smarter Legal Research

Central Gas & Electric Fixture Co. v. Kohn

New York Common Pleas — General Term
Apr 1, 1893
3 Misc. 235 (N.Y. Misc. 1893)

Opinion

April, 1893.

Benjamin H. Bayliss, for plaintiff (respondent).

Wm. J. Lippmann, for defendant (appellant).


In so far as this appeal purports to be from an order of affirmance of the General Term of the court below it must be dismissed, the order, as such, not being appealable. Whitfield v. Broadway Seventh Ave. R. Co., 16 Daly, 288.

On April 15, 1891, plaintiff agreed with one Carey, in writing, to supply certain buildings then in process of construction with gas fixtures of the value of $1,350 and to have them in place by the first day of May following. On April sixteenth, defendant, in consideration of the sum of $110 thereafter to be paid him, under his hand and seal, guaranteed Carey's payment for the fixtures when they were hung, as stated in plaintiff's agreement with Carey.

Thereafter this action was brought upon the guaranty, the complaint alleging performance by plaintiff of its agreement with Carey and that the latter had failed to pay the sum agreed. The answer denied these allegations.

On the trial it abundantly appeared from plaintiff's direct evidence that all the fixtures were supplied and hung except to the value of twenty-one dollars, and that both Carey and defendant had failed to pay the sum agreed after due demand. It also appeared that a substantial part of the work in hanging the fixtures was not done until a considerable time after May first, but in respect to this it further appeared that the delay was exclusively due to the fact that the buildings were not sooner in fit condition to enable plaintiff to annex the fixtures. Carey's testimony, which was adduced as part of plaintiff's case, also tended to show that he was only nominally the person interested in the erection and completion of the buildings; that he was acting under the direction of defendant, who supplied the money required for labor and materials, and that the latter was the real party in interest under plaintiff's agreement to supply the fixtures.

Defendant, maintaining that because plaintiff had not performed its agreement with Carey to hang the fixtures by May first and that his guaranty was conditioned upon plaintiff's performance at the time stated, claimed to be discharged from liability and moved the dismissal of the complaint. This motion was denied and defendant then rested without adducing further evidence on his behalf or requesting submission of the case to the jury. The trial court thereupon directed a verdict for plaintiff for $1,350, less $21, with interest, to which defendant excepted.

We can conceive of no ground upon which the disposition of the case by the court below may be justly assailed. Substantial performance of its agreement was all that was required of plaintiff to enable it to recover against Carey ( Flaherty v. Miner, 123 N.Y. 382, 388), and the motion for dismissal of the complaint without asking that the facts be submitted to the jury, conceded the evidence to be true and that only questions of law were involved. Such a motion authorizes the court to find all the facts of which there is any evidence, and for the purpose of this appeal we are compelled to assume that the trial court did find that plaintiff had substantially fulfilled its contract with Carey; that the delay was owing to Carey's neglect to have the buildings in fit condition; that in the matter of the completion of the buildings Carey acted as the representative of defendant, and that plaintiff's performance of its agreement to supply and hang the fixtures subsequent to May first was with defendant's knowledge and consent. Winchell v. Hicks, 18 N.Y. 558, 565; Collins v. Burns, 63 id. 1; Ormes v. Dauchy, 82 id. 443; Dillon v. Cockcroft, 90 id. 649; Provost v. McEncroe, 102 id. 650.

A guarantor or surety may limit his liability as such by whatever conditions he may see fit to impose, and however immaterial they may appear to be, noncompliance with them will preclude recourse to him. Benjamin v. Rogers, 126 N.Y. 60, 70. His undertaking is strictissimi juris and cannot be extended beyond the fair import of its language ( Henry McShane Co. v. Padian, 1 Misc. 332), and for the purposes of this appeal we may assume that the true interpretation of defendant's guaranty is as contended by him, and that, pursuant to its terms, he was not to be held for Carey's default in payment, unless the latter's agreement with plaintiff was fully performed by it on May first.

Such being the case, in the absence of the guarantor's consent to subsequent performance, it was unquestionably plaintiff's duty, when it was prevented from performance within the time agreed by Carey, to terminate its agreement with him and to confine its claim against the guarantor to the damages thus far sustained. Hunt v. Roberts, 45 N.Y. 691, 696. The case cited was an action brought to enforce the liability of the guarantor for performance of a contract to do carpenter work on certain houses. The work was to have been done by October 15, 1861, but was not so done owing to the failure of one Crossley, for whom it was to be done, to furnish the materials required therefor. The defendant had guaranteed Crossley's fulfillment of the contract, and after October fifteenth gave notice to plaintiffs that if the work was not completed by November first, he would not be responsible as guarantor therefor. Plaintiffs recovered judgment, and in reversing it the Court of Appeals says: "By the terms of the original contract the work was to have been completed on October fifteenth. If not performed at this time the defendant, had he not interfered in the transaction or consented to an extension of the time, would have been entitled to have the matter closed. If the delay had been owing to the default of the plaintiffs the defendant would have been discharged. If it was caused by Crossley, he had been guilty of a breach, and the defendant would have been entitled to insist upon the contract being terminated, and on such termination would have been liable as guarantor for the work done up to that time, and for the damages sustained by the plaintiffs in not being allowed to complete the job." McKecknie v. Ward, 58 N.Y. 541, 551; Emery v. Baltz, 94 id. 408, 414.

In Hunt v. Roberts, 45 N.Y. 691, the judgment against the guarantor was reversed upon the ground that his consent to plaintiffs' performance after Crossley's breach was expressly limited to performance by November first, and that the recovery included damages sustained after that time. Examining the question of the effect of the guarantor's notice, the court says: "We think that the extension left the parties in the same position on the first of November in which they would otherwise have been on the fifteenth of October, and that it did not operate as an extension of the guaranty indefinitely to such time as might be necessary to complete the work, but that the defendant had the right to insist that his liability as guarantor should be limited to the debt and damages which the plaintiffs were entitled to claim as of the day specified in his notice," thus sustaining the proposition required to support the judgment in the case at bar, that the waiver of plaintiffs' nonperformance at the time originally appointed and his consent to plaintiffs' future performance had the effect of extending defendant's liability upon his guaranty to the damage which plaintiff sustained from Carey's further default.

Equally untenable is defendant's claim that the judgment is excessive because he was not allowed out of the amount which plaintiff was held entitled to recover the sum promised to be paid him in consideration of his guaranty. No such claim was made by answer, nor was it suggested on the trial.

We have examined each of the remaining grounds of alleged error, and pronounce them of no gravity.

The judgment should be affirmed, with costs.

BISCHOFF and PRYOR, JJ., concur.

Judgment affirmed.


Summaries of

Central Gas & Electric Fixture Co. v. Kohn

New York Common Pleas — General Term
Apr 1, 1893
3 Misc. 235 (N.Y. Misc. 1893)
Case details for

Central Gas & Electric Fixture Co. v. Kohn

Case Details

Full title:CENTRAL GAS AND ELECTRIC FIXTURE Co. v . KOHN

Court:New York Common Pleas — General Term

Date published: Apr 1, 1893

Citations

3 Misc. 235 (N.Y. Misc. 1893)
22 N.Y.S. 758