Opinion
DA 21-0250
05-10-2022
For Appellants: Michael J. Uda, Anna M. Kecskes, Colson R. Williams, Lowell J. Chandler, Uda Law Firm, P.C., Helena, Montana For Appellees: Benjamin J. Alke, Crist, Krogh, Alke & Nord, PLLC, Billings, Montana (for NorthWestern Energy) Sarah N. Norcott, NorthWestern Energy, Helena, Montana, Clark Robert Hensley, NorthWestern Energy, Missoula, Montana, Jason Brown, Montana Consumer Counsel, Helena, Montana, Ben W. Reed, Lucas R. Hamilton, Aimee Hawkaluk, Public Service Commission, Helena, Montana
For Appellants: Michael J. Uda, Anna M. Kecskes, Colson R. Williams, Lowell J. Chandler, Uda Law Firm, P.C., Helena, Montana
For Appellees: Benjamin J. Alke, Crist, Krogh, Alke & Nord, PLLC, Billings, Montana (for NorthWestern Energy) Sarah N. Norcott, NorthWestern Energy, Helena, Montana, Clark Robert Hensley, NorthWestern Energy, Missoula, Montana, Jason Brown, Montana Consumer Counsel, Helena, Montana, Ben W. Reed, Lucas R. Hamilton, Aimee Hawkaluk, Public Service Commission, Helena, Montana
Justice Laurie McKinnon delivered the Opinion of the Court. ¶1 CED Wheatland Wind, CED Teton County Wind, and CED Pondera Wind—three wholly owned subsidiaries of Consolidated Edison Development ("CED")—appeal the April 19, 2021, Order on Petitions for Judicial Review issued by the First Judicial District Court, Lewis and Clark County, which partially affirmed and partially reversed two earlier Orders on Reconsideration issued by the Montana Public Service Commission ("The Commission"). The Commission's orders set the terms and conditions for three CED wind farm projects that were to be undertaken with NorthWestern Energy Corporation ("NorthWestern"). On appeal, CED raises four issues, which we restate as follows:
1. Whether the District Court erred in upholding the Commission's determination that CED's three qualifying facilities were responsible for bearing the network upgrade costs required to upgrade NorthWestern's transmission system for each of the three QFs.
2. Whether the District Court properly upheld the Commission's decision to calculate avoided energy costs using a proxy model.
3. Whether the District Court properly upheld the Commission's decision to calculate ancillary service deductions based on NorthWestern's proposed rates.
4. Whether the District Court properly upheld the Commission's determination that 15-year contract lengths were appropriate for all three of CED's projects.
¶2 We affirm in part, reverse in part, and remand for further proceedings. FACTUAL AND PROCEDURAL BACKGROUND
¶3 Under the Public Utility Regulatory Policies Act of 1978 ("PURPA"), public utility companies are required by federal law to purchase electricity generated by "qualifying ... facilit[ies]." 16 U.S.C. § 824a-3(a). NorthWestern, is a public utility company subject to 16 U.S.C. § 824a-3(a). CED Wheatland Wind, LLC, CED Teton County Wind, LLC, and CED Pondera Wind, LLC are self-certified qualifying facilities ("QFs") under PURPA, which grants them the right to sell energy and capacity to a public utility such as NorthWestern. In the absence of a formal contract between a public utility and a QF, the Federal Energy Regulatory Commission ("FERC") has stated—under its PURPA authority—that a QF can still sell power to a public utility in the event that a "Legally Enforceable Obligation" ("LEO") is found to exist between the parties. 18 C.F.R. § 292.304(d)(2).
¶4 Authority to enforce PURPA is also delegated, in part, to state regulatory agencies like the Commission, due to their localized knowledge and expertise. As a result, shortly after PURPA's passage, Montana enacted its own "Mini-PURPA" law, which provides that if a utility provider and a QF cannot agree on contractual terms, "[t]he [Montana Public Service] Commission shall determine the rates and conditions of the contract upon petition" from either party. Section 69-3-603(2)(a), MCA. CED filed petitions asking the Commission to determine its contract terms with NorthWestern for three projects: a proposed 75-megawatt ("MW") wind farm to be located in Wheatland County, Montana ("Wheatland facility"), a 19-MW wind farm to be located in Teton County, Montana ("Teton facility"), and a 20-MW wind farm to be located in Pondera County, Montana ("Pondera facility").
PURPA and Montana's "Mini-PURPA" requires that for QFs between 3 and 80 MW avoided-costs be established between the QF and the purchasing public utility through a negotiated contract, on an "as available" basis, or pursuant to an LEO, whereas small QFs under 3 MW receive a standard avoided-cost rate set by the Commission every two years. MTSUN, LLC v. Mont. Dep't of Pub. Serv. Regulation , 2020 MT 238, ¶ 5, 401 Mont. 324, 472 P.3d 1154 (citations omitted).
¶5 Negotiations between CED and NorthWestern regarding power purchase agreements (PPAs) for each of the three facilities began in July 2018, September 2018, and May 2019 for the Teton, Wheatland, and Pondera facilities, respectively. As part of the negotiation process, CED requested that NorthWestern complete a Large Generation System Impact Study ("LGSIS") analyzing the potential impact of each facility on NorthWestern's system. Relating specifically to the Wheatland facility, NorthWestern studied the project as both Network Resource Interconnection Service ("NRIS") and Energy Resource Interconnection Service ("ERIS"). The LGSIS identified "no additional upgrades beyond the [point of interconnection]" necessary to interconnect through ERIS. However, under NRIS, the LGSIS indicated the Wheatland facility would cause overloads to NorthWestern's system and identified the corresponding need for a new 230 kilovolt (kV) transmission line to accommodate the increased generation. The LGSIS provided interconnection cost estimates of approximately $6 million for ERIS and $128 million for NRIS, subject to change. CED elected to interconnect through NRIS. The record indicates CED was aware of the estimated costs for ERIS and NRIS and apparently did not dispute the initial estimates or its responsibility for some of those costs.
¶6 In mid-2019, PPA negotiations for all three facilities stalled. On September 16, 2019, CED filed two separate "Petition[s] to Set Terms and Conditions for a Qualifying Small Power Production Facility Pursuant to [ ] § 69-3-603[, MCA,]" before the Commission for CED's Teton and Pondera facilities. Later, on October 4, 2019, CED filed a third petition with the Commission to set the terms for CED's Wheatland facility ("Wheatland matter"). On October 25, 2019, the Commission consolidated CED's Teton petition and Pondera petition into a single case before the agency ("Teton-Pondera matter"). The Intervenor in the present matter—the Montana Consumer Counsel (MCC) —first intervened in both the Teton-Pondera and Wheatland matters before the Commission.
The MCC is an office established by the Montana Constitution to advocate on behalf of the interests of Montana's utilities consumers. Mont. Const. art. XIII, § 2.
¶7 The Commission held evidentiary hearings in the Teton-Pondera matter from January 22-24, 2020, and entered a Final Order on March 23, 2020 ("Teton-Pondera Final Order"). Both CED and NorthWestern filed motions with the Commission for reconsideration of this decision. On July 9, 2020, the Commission issued its Order on Reconsideration in the Teton-Pondera matter ("Teton-Pondera Reconsideration Order"), which affirmed most aspects of the original Teton-Pondera Final Order.
¶8 The Commission held evidentiary hearings in the Wheatland matter from February 10-11, 2020. The Commission issued a Final Order in this matter on April 22, 2020 ("Wheatland Final Order"). Once again, both CED and NorthWestern filed motions with the Commission for reconsideration of this decision. On July 13, 2020, the Commission issued its Order on Reconsideration in the Wheatland matter ("Wheatland Reconsideration Order"), which also affirmed most aspects of the original Wheatland Final Order.
¶9 CED's petitions before the Commission in the Teton-Pondera matter and the Wheatland matter both presented eight identical issues for review. The following four issues are pertinent to CED's appeal: whether CED or NorthWestern should financially bear the network upgrade costs for each of the three wind facility projects (Issue I); whether the proper methodology was used for calculating the avoided energy costs for each facility (Issue II); whether the proper methodology was used for calculating ancillary services deductions —which are deducted from the avoided energy costs for each facility (Issue III); and whether the contract length awarded for each facility was appropriate (Issue IV). ¶10 Under § 2-4-702, MCA (the provision of the Montana Administrative Procedure Act ("MAPA") permitting judicial review of agency decisions), CED petitioned the District Court for review of the Commission's Teton-Pondera Reconsideration Order and the Commission's Wheatland Reconsideration Order. CED's petitions requested the District Court's review of the Commission's decisions on all eight issues presented to the Commission. The District Court consolidated CED's two petitions into a single appeal and heard oral argument on the matter. On April 19, 2021, the District Court issued its "Order on [the] Petitions for Judicial Review" (District Court's Order). The District Court affirmed the Commission's decisions on six of the eight issues raised, including the Commission's decisions on Issues I through IV. CED appeals the District Court's Order upholding the Commission's rulings on Issues I through IV.
Avoided [energy] costs are defined as "the incremental costs to an electric utility of electric energy or capacity or both which, but for the purchase from the qualifying facility or qualifying facilities, such utility would generate itself or purchase from another source." 18 C.F.R. § 292.101(b)(6). Stated more simply, avoided energy costs represent the amount NorthWestern would spend to generate the electricity itself or acquire it from another source.
Ancillary services are services that support the transmission of capacity and energy from generating resources to load while maintaining reliable operation of the system. Ancillary service tariffs function as deductions from the avoided energy costs that NorthWestern is required to pay CED's facilities for their power generation, in return for NorthWestern providing these ancillary services. NorthWestern proposed—and the Commission adopted—ancillary service deductions for the three CED facilities based on the Open Access Transmission Tariff or "OATT," which is a form of ancillary services tariff that is accepted and approved by FERC. See 18 C.F.R. § 35.28(c).
¶11 Additional facts are set forth within the relevant issues as necessary.
STANDARDS OF REVIEW
¶12 MAPA provides the standards of review governing appeals of administrative agency decisions in a contested case. Section 2-4-704, MCA. In administrative appeals, this Court applies the same standards of review as a district court. McGree Corp. v. Mont. Pub. Serv. Comm. , 2019 MT 75, ¶ 6, 395 Mont. 229, 438 P.3d 326 (citing NorthWestern Corp. v. Mont. Dep't of Pub. Serv. , 2016 MT 239, ¶ 25, 385 Mont. 33, 380 P.3d 787 ). This Court reviews an administrative decision in a contested case to determine whether the agency's findings of fact are clearly erroneous and whether its interpretation of law is correct. MTSUN , ¶ 51 (citing Whitehall Wind, LLC v. Mont. Pub. Serv. Comm. , 2010 MT 2, ¶ 15, 355 Mont. 15, 223 P.3d 907 ). Our review "must be confined to the record." Section 2-4-704(1), MCA. Accordingly, this Court may not substitute its judgment for that of the agency in weighing factual evidence. Vote Solar v. Mont. Dep't of Pub. Serv. Regulation , 2020 MT 213A, ¶ 36, 401 Mont. 85, 473 P.3d 963 ; Section 2-4-704(2), MCA. A finding of fact is clearly erroneous if it is not supported by substantial evidence in the record, if the fact-finder misapprehended the effect of the evidence, or if a review of the record leaves this Court with a definite and firm conviction that a mistake has been made. McGree , ¶ 8 (citations omitted). An agency's interpretation of a statute is a conclusion of law that we review de novo. McGree , ¶ 6 (citations omitted).
¶13 This Court may reverse or modify an agency decision if the substantial rights of a party have been prejudiced because the agency's decision: is in violation of constitutional or statutory provisions; exceeds the agency's statutory authority; is made upon unlawful procedure; is affected by other error of law; is clearly erroneous in light of the whole record; or is otherwise "arbitrary or capricious or characterized by [an] abuse of discretion." Section 2-4-704(2)(a)(i)-(vi), MCA. This Court may also reverse or modify an agency decision if "findings of fact, upon issues essential to the decision, were not made" despite being requested. Section 2-4-704(2)(b), MCA. While agencies possess specific, technical, and scientific knowledge exceeding that of this Court, an agency must articulate a satisfactory explanation for its actions and provide a rational connection between the facts found and the choice made. MTSUN , ¶ 52 (citations omitted). This Court will not defer to an agency's incorrect or unlawful decisions but will only defer to an agency action within permissible statutory bounds. MTSUN , ¶ 52 (citations omitted).
DISCUSSION
¶14 1. Whether the District Court erred in upholding the Commission's determination that CED's three qualifying facilities were responsible for bearing the network upgrade costs required to upgrade NorthWestern's transmission system for each of the three QFs.
¶15 NorthWestern calculated "interconnection network upgrade costs" of $3.27 million for the Teton facility; $2.49 million for the Pondera facility; and $267.8 million for the Wheatland facility–an increase from its initial estimate of $128 million. Approximately $237 million of the Wheatland estimate related to a new transmission line necessary to deliver the energy from the Wheatland facility to NorthWestern's load centers. Before the Commission, both parties agreed CED was responsible for the costs of interconnection and network upgrades for the Teton and Pondera facilities, but CED argued it was owed a refund for all costs and that NorthWestern could not deduct those costs from its avoided costs payments to CED. Regarding the Wheatland facility, the parties agreed CED remained responsible for interconnection costs, but CED contended it was not responsible for any network upgrade costs, which included the entirety of the $237 million transmission line and $30 million in additional related costs. CED argued the Wheatland facility was not a transmission service customer and should not be responsible for subsidizing NorthWestern's network by paying for the $237 million transmission line that would benefit all NorthWestern customers. CED's direct testimony made no adjustment for interconnection costs because CED intended to directly fund up front the cost to interconnect for each project. CED additionally made no adjustment to avoided cost for the cost of network transmission upgrades, because CED intended to fund those up front and expected to receive a reimbursement, consistent with NorthWestern's Open Access Transmission Tariff ("OATT").
The District Court erroneously attributed the $267 million price to the transmission line itself. The record indicates the transmission line cost approximately $237.5 million, with related costs adding an additional $30.3 million.
¶16 NorthWestern argued CED must be fully responsible for "interconnection network upgrade costs" for all three facilities because any other approach would violate PURPA and transfer those costs to NorthWestern's customers. NorthWestern contended its approach conformed with FERC orders and the Commission's rules because it required the qualifying facilities ("QFs") to bear responsibility for any network upgrade costs associated with the QFs that exceeded what NorthWestern would otherwise experience from adding similar capacity to its system. NorthWestern argued any costs associated with transmission network upgrades should be paid by CED, not NorthWestern's customers. Regarding the Wheatland facility, NorthWestern argued the $237 million transmission line was only necessary because of CED's siting decision for the Wheatland facility and thus, CED should be solely responsible for the transmission line and its associated costs.
¶17 The Commission found CED solely responsible for the full network upgrade costs for each project. The Commission's orders did not provide for a refund for CED's funds toward the upgrades for any of the three facilities. The Commission's Reconsideration Orders found that CED failed to show the Commission's decision was unlawful, unjust, or unreasonable and largely upheld the Commission's decision.
The Commission's Teton-Pondera Reconsideration Order reversed the Commission's decision to subtract $75,000 in network upgrade costs from the Teton and Pondera facilities, leading to the Commission finding CED responsible for the full amount of network upgrade costs for each project, with no deduction to avoided cost or refund.
¶18 On appeal, CED first contends the Commission exceeded its jurisdiction when it found network upgrade costs were necessary for interconnected operations with NorthWestern's system and assigned costs to CED. Because the transmission line will be used by other customers and affect interstate commerce, CED argues only FERC, and not the Commission, has jurisdiction to determine cost responsibility. NorthWestern and the Commission respond that the Commission has retained jurisdiction over this area since 1983 and the cost constitutes an interconnection cost CED is required to pay. ¶19 CED failed to raise its jurisdictional argument before either the Commission or the District Court. We have long declined to consider a change in legal theory or new arguments first raised on appeal, due to the fundamental unfairness of faulting the district court for failing to rule correctly on an issue it was never given the opportunity to consider. Schlemmer v. North Cent. Life Ins. Co. , 2001 MT 256, ¶ 22, 307 Mont. 203, 37 P.3d 63. However, notwithstanding CED's failure to raise its jurisdictional argument below, we conclude the Commission had authority to consider network upgrade costs associated with CED's interconnection to NorthWestern's system.
On appeal, CED does not clearly challenge the Commission's decision to forego refunds related to the Teton and Pondera projects, instead focusing much of its argument on the costs assigned to the Wheatland project. The record is further unclear as to the viability of refunds for these costs. We have recognized it is not our obligation to conduct research, guess at precise positions, or develop legal analysis to support parties’ positions. Stevens v. Novartis Pharms. Corp. , 2010 MT 282, ¶ 85, 358 Mont. 474, 247 P.3d 244 (citations omitted). However, as we are remanding under this issue, the parties may address the issue anew on remand.
¶20 Under the Federal Power Act (FPA), Congress provided FERC with jurisdiction over "transmission of electric energy in interstate commerce" and "the sale of electric energy at wholesale in interstate commerce." 16 U.S.C. § 824(b). FERC has divided the energy market into wholesale and retail sales, with retail sales including both bundled and unbundled services. Bundled services means "that consumers paid a single charge that included both the cost of the electric energy and the cost of its delivery." New York v. FERC , 535 U.S. 1, 5, 122 S. Ct. 1012, 1017, 152 L.Ed.2d 47 (2002). In 1935, when FPA became law, most electricity was sold by vertically integrated utilities that had constructed their own power plants, transmission lines, and local delivery systems. Most operated as separate local monopolies subject to state or local regulation. Since the enactment of the FPA, technological advancements have made it possible to generate energy across state lines in regional, multi-state power grids thereby implicating interstate commerce concerns and invoking FERC's jurisdiction. The states possessed broad authority to regulate these utilities, but their power was limited by the Commerce Clause. See generally New York v. FERC , 535 U.S. at 5, 122 S. Ct. at 1017. In keeping with this history of state regulatory involvement, FERC has exercised authority over unbundled retail services, but has declined to exercise authority over bundled retail services, leaving their regulation to the states. In re Promoting Wholesale Competition Through Open Access , Order No. 888, 61 Fed. Reg. 21,540, 24,577-21,578 (1996) ; reh'g denied Order No. 888-A, 62 Fed. Reg. 12,274, 12,303 (1997). NorthWestern provides bundled retail services to its customers. See In re NorthWestern 2018 Rate Case , Order 7604u, ¶¶ 135-37 (Dec. 20, 2019). FERC Order No. 2003 noted FERC "[does] not address interconnection issues related to [QFs] under [PURPA]." Order No. 2003 expressly delegated authority over interconnection costs related to QFs to the states, concluding "[w]hen an electric utility is obligated to interconnect under Section 292.303 of [FERC's] regulations, that is, when it purchases the QF's total output, the relevant state authority exercises authority over the interconnection and the allocation of interconnection costs." FERC Order No. 2003, ¶ 813. Finally, CED's initial petition to the Commission acknowledged both CED's request "that NorthWestern purchase the output from the QF under PURPA" and the Commission's jurisdiction under PURPA to set the terms of its PPA with NorthWestern. CED's Form 556, filed with FERC, additionally identified NorthWestern as the only electric utility "that are contemplated to transact with the facility" and represented that NorthWestern would not transmit CED's power to third parties. We conclude the Commission had jurisdiction to consider network upgrade costs and turn to the substance of the issue presented.
¶21 Costs of interconnection are to be assessed to the QF. 18 C.F.R. § 292.306 provides: "[e]ach qualifying facility shall be obligated to pay any interconnection costs which the State regulatory authority ... may assess against the qualifying facility on a nondiscriminatory basis with respect to other customers with similar load characteristics." CED does not contest its responsibility for interconnection costs. CED does contend that the Commission discriminated against CED because it ordered CED to pay for network upgrade costs—as compared to interconnection costs—without the benefit of a refund, whereas non-QF generators are entitled to refunds for payment of network upgrade costs.
¶22 In contrast to interconnection costs, costs of network upgrades are assessed to the electric utility. "Network upgrades provide a system-wide benefit, expenses associated with owning, maintaining, repairing, and replacing them shall be recovered from all [t]ransmission [c]ustomers [electric utility] rather than being directly assigned to the [i]nterconnection [c]ustomer [QF]." Standardization of Generator Interconnection Agreement and Procedures , Order No. 2003-A, 106 FERC ¶ 61,220 at ¶ 424. Furthermore, "longstanding Commission policy establishes that the costs of network upgrades may not be directly assigned to the interconnection customer because network upgrades are not ‘sole use’ facilities and they provide a benefit to all transmission system users." Public Serv. Co. of Colo. , 167 FERC ¶ 61,141, 61,747 (2019). Pursuant to its responsibility to allocate interconnection costs, the Commission's rules mirror FERC's treatment of interconnection costs and responsibility. See Admin. R. M. 38.5.1901(2)(d) (defining interconnection costs); Admin. R. M. 38.5.1904(3) (assigning interconnection costs to QFs).
¶23 Here, the Commission ordered CED to pay "interconnection network upgrade costs." Unfortunately, the Commission's reasoning and subsequent assessment of "interconnection network upgrade costs" to CED combined, rather than differentiated, interconnection costs and costs associated with upgrades to NorthWestern's transmission network. It is important to distinguish interconnection costs from network upgrade costs, rather than jumbling their meanings, because they express two distinct concepts. Importantly, distinguishing them is necessary for purposes of fairly and reasonably assessing costs in the complex arena of interconnecting a QF to a network. It is thus important to examine the statutory definition of "interconnection costs."
While "network upgrades" are not defined in PURPA, NorthWestern's policies define "network upgrades" as those "required at or beyond the point" at which the interconnection facilities connect to the transmission provider's transmission system. NorthWestern Corporation, Standard Large Generator Interconnection Procedures 12 (Jan. 15, 2021), https://perma.cc/52HS-J2T9. NorthWestern's policies do not apply directly to all QFs, which are often not transmission customers. Nonetheless, they are illustrative of NorthWestern's practice of distinguishing the two concepts.
¶24 Interconnection costs are defined in PURPA. Interconnection costs are:
the reasonable costs of connection, switching, metering, transmission, distribution, safety provisions, and administrative costs incurred by the electric utility directly related to the installation and maintenance of the physical facilities necessary to interconnect with a qualifying facility, to the extent such costs are in excess of the corresponding costs which the utility would have incurred if it had not engaged in interconnected operations, but instead generated or purchased an equivalent amount of electric energy or capacity from other sources.
18 C.F.R. § 292.101(b)(7). CED never contested that it must pay the basic costs needed to establish interconnected operations, even if some of that includes costs associated with transmission. CED does argue the Commission's order far exceeded what can reasonably be considered an "interconnection cost" because the Commission ordered it to pay the entire cost of upgrading NorthWestern's transmission system. We agree. The Commission's and NorthWestern's singular focus on "transmission," noting it is an explicit element of "interconnection costs," ignores important language in the statutory definition. While the definition of interconnection costs necessarily must be flexible to allow regulators to assess costs based on the diverse circumstances each interconnection presents, the costs for a QF to interconnect must nonetheless remain "reasonable " and "directly related " to the installation and maintenance of the physical facilities "necessary " to permit interconnected operations. These requirements dovetail with PURPA's mandate that utilities purchase electricity generated by QFs at rates that are "just and reasonable" to the consumer, "in the public interest," and nondiscriminatory to the QF. Vote Solar , ¶ 41 (citing 16 U.S.C. § 824a-3(b) ). When assessing costs, these competing obligations require the Commission to fairly balance the interests of its ratepayers with that of the QF such that it complies with PURPA and encourages QF development while making the ratepayer indifferent as to the energy source. Vote Solar , ¶ 41.
¶25 NorthWestern argues its customers should not be responsible for CED's costly siting decision of the Wheatland facility. However, if a QF seeking interconnection for transmission purposes locates its plant far from the utility's lines with the expectation that the interconnection costs would be spread among the utility's customers, the utility could simply refuse to transmit power. Although the utility would still have an obligation to purchase the QF's output, the QF, rather than the utility's customers, would pay for the interconnection. A QF could not afford to take this risk and would therefore do all it could to keep costs of interconnection to a minimum. See Western Mass. Electric Co ., 66 FERC ¶ 61,167, 61,336 (1994).
¶26 The Commission has previously found the term "interconnection costs" in both FERC and the Commission's rules "encompasses the costs associated with both interconnection facilities and network upgrades." In re the Petition of Kenfield Wind Park I, LLC and KWP-LC7, LLC to Set Terms and Conditions for Qualifying Small Power Production Facility , Order No. 7068b, ¶ 80, Dkt. D2010.2.18 (June 23, 2010). The Commission has also found interconnection costs apply equally to both parties. If a QF allows a utility to avoid or defer interconnection network upgrade costs, the QF receives an increased avoided cost payment. Conversely, if the QF causes NorthWestern to incur a cost it would not otherwise incur, the QF is responsible for such costs. Kenfield Wind , Order No. 7068b, ¶ 83. Here, however, the Commission's assessment of the entire cost of transmission upgrades to CED as "interconnection network upgrade costs" obscured the distinction between network costs and interconnection costs and resulted in a discriminatory assessment of costs to the QF. It failed to consider the proportionate amount of power Wheatland would generate in relation to costs, as well as other generation projects utilizing, or potentially utilizing, the transmission line.
¶27 The Wheatland facility would be located near an existing 230kV transmission line running from Great Falls to Broadview. The Large Generator System Impact Study identified this line would be overloaded by Wheatland's interconnection. However, numerous existing generation projects currently connect to that line. These projects together can supply over 200 MW of power. The Wheatland facility is one of six future interconnectors with plans to interconnect to the existing line. Three projects are in the queue ahead of Wheatland, sending their output to the current line. Wheatland and at least two subsequent projects may depend on transmitting their output via the capacity created on the new line.
¶28 This understanding requires an assessment of the proportional scale of Wheatland's generation. NorthWestern asserts the Wheatland facility's 75-MW output may be the additional output that overloads the entire existing line. However, up until Wheatland interconnects, the current line will have accommodated some 500 MW of power—the present 200 MW from existing projects along with approximately 300 MW from the three projects ahead of Wheatland in the interconnection queue. The assignment of $267 million in costs to CED, then, comes down almost solely to its place in the interconnection queue. In order to interconnect Wheatland, NorthWestern wants to construct a second transmission line of equal length and capacity, essentially doubling its transmission service and providing additional reliability to its network at CED's expense. In other words, the new line does far more than simply deliver Wheatland's power to a NorthWestern substation—it would be a significant addition to a long-distance transmission corridor with a capacity disproportionate to Wheatland's output. This results in discriminatory treatment toward the Wheatland facility and, accordingly, fails to comply with PURPA.
Calculating the MW capacity of a transmission line of a certain voltage is complicated and depends on various factors. However, according to NorthWestern's testimony, it remains clear that the current 230kV line in this corridor will accept about 500 MW of power from various generators prior to Wheatland overloading it.
¶29 NorthWestern's limited capacity requires it to purchase power generated beyond its own facilities. The Wheatland facility constitutes one 75-MW project among six scheduled interconnections totaling over 500 additional MW in the same corridor. Thus, Wheatland's excess costs, as considered in the definition of "interconnection costs," are entirely disproportionate to its added capacity to NorthWestern's system. However, given NorthWestern's need, and the concurrent need for increased transmission capacity and reliability, the Wheatland facility should bear some of the cost burden—but not all $267 million, as the Commission erroneously ordered.
¶30 We conclude the Commission erred in assigning $267 million in network upgrade costs to CED. The Commission's precedent obscures "interconnection costs" and "network upgrades" into "interconnection network upgrade costs," which do not exist. Interconnection costs are defined by both federal and Montana regulations. NorthWestern's policies define network upgrades as distinct from facilities required for interconnection and the associated costs. NorthWestern and the Commission's attempts to mire these distinct concepts in technicalities cannot result in discriminatory costs for QFs, as they did here. PURPA's mandate of just and reasonable rates that are nondiscriminatory requires assessing the costs incurred in the interconnection process in proportion to the QF's added load to NorthWestern's system. This ensures QFs bear the reasonable costs directly related to interconnecting to NorthWestern's system, while simultaneously preventing discriminatory costs disproportionate to the project's impact and ensuring ratepayer indifference.
¶31 The record indicates CED was aware of an early estimate of the costs associated with interconnecting through the Network Resource Interconnection Service. Thus, while CED may be held responsible for costs related to the proportional impact of its projects upon NorthWestern's system, the District Court erred in concluding the Commission's decision to allocate $267 million in network upgrade costs to CED was lawful. CED is responsible for all costs reasonably incurred by NorthWestern because of interconnection, which may include operation and maintenance costs, the costs of installing equipment elsewhere in the utility's system necessitated by interconnection, and other reasonable costs. However, in assessing CED's interconnection costs, the Commission must consider the amount of MW which will be generated by Wheatland in relation to those costs, the nondiscriminatory purpose of PURPA, the interconnection of other facilities, and who is the primary beneficiary of the network upgrades. CED does not dispute its responsibility for some costs, only that it is unreasonable for it to pay the entire $267 million. We agree, and remand for reconsideration incorporating the proportionality analysis set forth above.
¶32 2. Whether the District Court properly upheld the Commission's decision to calculate avoided energy costs using a proxy model.
¶33 CED calculated its avoided costs based on the Commission's most recently approved methodology. This methodology utilized the PowerSimm model, which incorporates a variety of factors, including market forecast and generation schedules. CED incorporated a monthly aggregation of the hourly modeling results typically produced by PowerSimm to develop its estimate. CED presented testimony indicating it chose this method not for its accuracy, but because CED thought it was the Commission-approved methodology. Using this approach and assuming a 25-year contract, CED calculated avoided costs for the Teton facility at $54.88/MWh during heavy load hours (HLH), $36.99/MWh during light load hours (LLH), and $46.65/MWh around-the-clock (ATC). For the Pondera facility, the approach yielded avoided costs of $54.35/MWh during HLH, $36.93/MWh during LLH, and $46.68/MWh ATC. CED's calculations for the Wheatland facility yielded $52.51/MWh during HLH, $36.51/MWh during LLH, and $45.11/MWh during ATC.
¶34 NorthWestern also relied upon the PowerSimm model to calculate its avoided costs. However, NorthWestern developed its calculations directly from the hourly model results, rather than from monthly aggregated data. NorthWestern's calculations, assuming a 15-year contract and a declining heat rate, produced avoided costs of $15.90/MWh ATC for the Teton facility, $15.47/MWh for the Pondera facility, and $15.86/MWh for the Wheatland facility. NorthWestern additionally modeled avoided costs without an assumed declining heat rate, resulting in avoided costs of $18.63/MWh for the Teton facility, $17.74/MWh for the Pondera facility, and $19.43/MWh for the Wheatland facility. The MCC supported the use of NorthWestern's hourly PowerSimm results over the use of CED's monthly aggregated data, arguing the hourly model better reflected the realities of generator scheduling, dispatch and energy trading. Notwithstanding its support, the MCC cited the Commission's previous rejection of the hourly model and noted that the MCC agreed with the Commission's concerns regarding the hourly model's lack of tractability and transparency.
NorthWestern later filed corrected avoided costs after discovering an error in the script it used to derive the estimates.
¶35 In rebuttal, CED criticized several aspects of NorthWestern's approach, including its marginal cost to serve load approach, its use of market price forecasts, and use of a declining heat rate without adequate justification. CED's rebuttal additionally presented an alternative method of calculating avoided costs based on the fixed and operating costs of the avoidable, or proxy, resource identified in NorthWestern's 2019 Resource Procurement Plan ("2019 Plan"). Notwithstanding its position on appeal, CED expressly argued, in its initial post-hearing brief to the Commission, "If the Commission rejects PowerSimm, it can set avoided energy cost using the Proxy Method." CED noted the Commission had recently used this proxy method as well, suggesting precedent supported the approach. CED assumed a 25-year contract length and calculated avoided costs based on the proxy methodology of approximately $35-36/MWh for the Teton and Pondera facilities and $70.78/MWh for the Wheatland facility. CED later noted these were not exact recommendations but served as benchmark estimates. At the hearing for the Teton-Pondera matter, CED presented testimony indicating its reliance on PowerSimm aimed to adhere to the Commission's past practices, but its proxy methodology was "cleaner and simpler," provided similar results, and should be utilized by the Commission going forward.
CED contended its proxy methodology estimate was merely intended as a benchmark to demonstrate the reasonableness of its PowerSimm calculations and that it did not advocate for the proxy methodology to be applied to its projects. Its argument in the post-hearing brief does not reflect this position.
¶36 The Commission took issue with CED's PowerSimm calculations, noting its selection of inputs deviated from Commission-approved methodology and consequently led to higher avoided costs for CED. The Commission additionally noted the legitimate concerns about NorthWestern's calculations raised by CED's rebuttal testimony and the lack of evidence presented to rebut those concerns. At the hearing for the Teton-Pondera matter, the Commission received testimony from NorthWestern indicating errors in the PowerSimm model would exist for either the hourly or monthly results. Citing the lack of reliability from both CED and NorthWestern's calculations, the Commission adopted the proxy methodology introduced by CED to calculate avoided costs for all three projects.
¶37 However, because CED introduced the methodology through rebuttal testimony without supporting calculations or explanation of how its prices were reached, the Commission elected not to rely on the avoided costs generated by CED's proxy methodology. Noting the lack of evidentiary support for the parties’ avoided cost estimates, alongside the Commission's statutory duty under Montana's "Mini-PURPA" to determine contractual rates within 180 days, the Commission adopted a proxy methodology based on an incremental resource identified in the 2019 Plan. The Commission noted it "would prefer not to pursue this course" but cited the parties’ support, to varying degrees, for the proxy methodology, and explained the inputs it relied upon in calculating avoided costs under this methodology. The Commission indicated it did not view this as a deviation from Commission precedent, but nonetheless felt its decision not to utilize the PowerSimm estimates was supported by its statutory timeline. Setting aside the reliability concerns raised and the lack of support for CED's proxy methodology, the Commission found what remained was "testimony from both CED and NorthWestern indicating that the proxy methodology is a reasonable alternative for estimating NorthWestern's avoided energy cost ... This justifies deviation from the Commission's past practice of reliance on PowerSimm in favor of the proxy method here."
¶38 Adopting the proxy methodology, both the Teton-Pondera and Wheatland Reconsideration Orders arrived at an avoided energy cost rate of $24.99/MWh for the Wheatland, Teton, and Pondera facilities, based on the awarded contract length of 15 years per facility.
This avoided energy cost figure was adjusted upward from the original Orders’ avoided cost of $24.18/MWh per facility after the Commission relied on a different proxy resource.
¶39 On appeal, CED argues it is entitled to have the avoided costs calculated using the existing methodology at the time of incurring its LEO. Alternatively, CED contends the Commission exceeded its authority by arbitrarily adopting its own methodology for calculating avoided costs. In response, the Commission and NorthWestern argue both NorthWestern and CED's proposed avoided costs were flawed and that CED presented evidence supporting the Commission's decision to adopt its own proxy methodology to calculate the avoided costs.
¶40 PURPA provides QFs the option of having avoided costs determined either at the time of delivery or at the time the QF incurs a LEO. 18 C.F.R. § 292.304(d)(1)(ii). The point of this statutory section is to calculate avoided costs accurately and reliably. Nothing in PURPA requires or mandates the calculation of avoided costs based on unreliable or inaccurate inputs, as was the case here. The record indicates unresolved reliability concerns with the PowerSimm model present in both CED and NorthWestern's estimates. Implicit in CED's argument is a request for this Court to find its monthly PowerSimm results reliable, while rejecting NorthWestern's hourly results. It would have been illogical and arbitrary for the Commission to reject NorthWestern's hourly PowerSimm rates, based on the unaddressed concerns CED pointed out, but adopt CED's PowerSimm rates, which relied on the same underlying hourly results but aggregated on a monthly basis. It would be just as illogical for us to do the same on appeal. We decline to substitute our judgment for the Commission's concerning the lack of reliability in the PowerSimm results. See Vote Solar , ¶ 36. For these reasons, PURPA cannot be read to require a QF have its avoided costs determined inaccurately, relying on the extant methodology, at the time it incurred a LEO.
CED's claim of a due process violation fails for the same reason. CED did not have a vested property interest in having its avoided costs inaccurately determined at the time it incurred a LEO.
¶41 Nor does CED's contention the Commission exceeded its statutory authority and acted sua sponte by adopting the proxy methodology prove persuasive. CED cites MTSUN for the proposition that the Commission "has not been specifically conferred sua sponte authority allowing to adjudicate undisputed issues." MTSUN , ¶ 73 (emphasis added). However, the avoided costs here were not undisputed, and CED's reliance on MTSUN for this proposition necessarily fails. Rather, as noted earlier in MTSUN , "the [Commission's] review is limited to making determinations in controversies ." MTSUN , ¶ 73 (internal quotations omitted, citing § 2-15-102(10), MCA ). The calculation of avoided costs here constituted precisely the type of controversy the Commission retained statutory power to determine. Acting in a quasi-judicial function while adjudicating § 69-3-603 petitions, the Commission's authority includes determining the fixing of prices. Section 2-15-102(10)(g), MCA. The Commission acted squarely within its statutory authority here to fix the avoided costs and, accordingly, did not exceed its statutory authority.
CED's emphasis on the mandatory nature of Admin. R. M. 38.5.1910(2) (2018), rather than the immediately preceding word, proves similarly unpersuasive. Rule 38.5.1910(2) (2018) requires "The utility must provide an initial avoided cost calculation" based on the methodologies most recently approved by the Commission for that utility, along with all assumptions and inputs used in that calculation. CED's reading of Rule 38.5.1910(2) (2018) imposes this duty on the Commission, contrary to the plain and unambiguous language of the text. The record does not indicate, and CED does not contend, NorthWestern, to whom this Rule actually applies, failed to comply with this requirement.
¶42 Faced with unreliable calculations from the parties and its statutory duty to resolve the case within 180 days, the Commission relied on its "specific, technical, and scientific knowledge" and adopted an alternative method deemed reasonable by CED and supported in the record, to varying degrees, by both CED and NorthWestern. See MTSUN , ¶ 52. The Commission's cost assumptions were drawn from the 2019 Plan, which guides the calculation of avoided costs and was relied upon by CED in calculating its proxy methodology estimate. The Commission incorporated inputs supported by the testimony and rejected inputs it found unsupported, such as NorthWestern's use of a declining heat rate. We decline to substitute our judgment for the Commission's regarding the reliability of the three avoided cost estimates provided.
¶43 The Commission's decision to adopt the proxy methodology was lawful and substantially supported by the record. The District Court correctly affirmed the Commission's decision to adopt this methodology. However, because we are remanding under Issue I, we likewise remand for clarification under Issue II to allow both NorthWestern and CED to provide avoided cost estimates using the proxy method.
¶44 3. Whether the District Court properly upheld the Commission's decision to calculate ancillary service deductions based on NorthWestern's proposed rates.
¶45 CED testified it derived estimated ancillary service deductions based on a 2017 decision by the Commission. CED noted its belief that NorthWestern could absorb all three QFs without any need for additional load-following products and accordingly excluded deductions for those integration services. NorthWestern provided testimony from Joe Stimatz providing extensive information about NorthWestern's OATT, how the rates are calculated, and an estimate under the OATT. Stimatz's testimony additionally rebutted CED's testimony and proposed ancillary deductions. The MCC testified that CED's proposed ancillary services deductions were based on a 2017 case excluding integration costs and thus outdated. MCC further testified CED's estimate failed to reflect the findings of a report identifying a need for integration services contained in the 2019 Plan. CED rebutted this testimony by noting the risk of "double-dipping" because ancillary services were already included in the PowerSimm model and stating its belief that FERC would reject NorthWestern's OATT because it was unreasonably high.
¶46 Based on the testimony provided, the Commission found CED's claims unsupported and inconsistent with the 2019 Plan. The Commission provided for the possibility that FERC would reject the OATT and allowed for a corresponding decrease in ancillary deductions. The Commission additionally found CED's concern of "double-dipping" was mooted by the Commission's decision to rely on the proxy method to determine avoided costs. The Commission's Reconsideration Orders largely upheld the ancillary service deductions, ultimately finding CED was responsible for the ancillary service charges under the OATT for each wind project.
¶47 CED does not dispute its responsibility for ancillary service deductions, but contends it is entitled to ancillary service deductions based on the date the LEOs were incurred. Alternatively, CED argues the Commission again acted arbitrarily and unlawfully by failing to sufficiently justify its decision to charge CED for ancillary services according to NorthWestern's OATT, rather than CED's proposed rate. NorthWestern and the Commission respond that the record substantially supports the ancillary services deduction and the OATT applies to every other generator connected to NorthWestern's system equally.
¶48 Under PURPA, QFs have the option to obtain a rate for energy and capacity (the cost of purchase ) as of the time of delivery or the date it incurs a LEO. 18 C.F.R. § 292.304(d). However, this does not pertain to rates for sales of services by a utility to a QF, which is addressed in 18 C.F.R. § 292.305. This section requires rates be just, reasonable, in the public interest, and similar to those paid by other generators, but it does not require rates for sales of services provided to the QF to be fixed for the term of the contract. 18 C.F.R. § 292.305. CED is not entitled to have its ancillary service deductions calculated as of the date it incurred LEOs.
¶49 Ancillary services can include services related to energy losses, energy imbalances, and system protection. Section 69-3-2003(1), MCA (repealed 2021). NorthWestern provides ancillary services based on an OATT. An OATT applies standard requirements to ensure system reliability and fairness. See 18 C.F.R. § 35.28. OATT schedules must be just and reasonable and remain subject to approval by FERC. 16 U.S.C. § 824d(a) ; 18 C.F.R. § 35.28(c).
Throughout the proceeding, NorthWestern's OATT rates were interim and subject to final approval by FERC. The Commission addressed this interim status by finding that, to the extent CED was correct in its assertions that FERC would reduce or reject the rates, the ancillary charges would be adjusted accordingly. FERC ultimately approved the interim rates without adjustment on January 29, 2021, with an effective date of July 1, 2019. See Northwestern Corp. , 173 F.E.R.C. ¶ 63,020 ; Northwestern Corp. , 174 F.E.R.C. ¶ 61,074.
¶50 The Commission's decision to determine ancillary service deductions based on NorthWestern's OATT was supported by substantial evidence. NorthWestern provided the OATT and related calculations to the Commission. MCC and NorthWestern rebutted CED's proposed rate, which excluded a service necessary under the 2019 Plan to integrate the QFs. The Commission noted the lack of support for CED's position and its inconsistency with the 2019 Plan. The Commission implicitly distinguished the 2017 case upon which CED relied by finding CED's proposal inconsistent with the 2019 Plan. Notwithstanding the lack of evidentiary support, the Commission addressed CED's concern that FERC would reject the OATT and eliminated the identified risk of "double-dipping" through its adoption of the proxy methodology.
¶51 The Commission adequately articulated its reasoning. Its decision was not arbitrary and it was supported by substantial evidence in the record. The District Court correctly affirmed the Commission's decision regarding ancillary service deductions.
¶52 4. Whether the District Court properly upheld the Commission's determination that 15-year contract lengths were appropriate for all three of CED's projects.
¶53 In its initial petition to set contract terms, CED argued it was entitled to a 25-year contract as a matter of law, arguing a Montana district court order served as binding precedent on the Commission. CED presented testimony noting its belief that a 25-year contract was generally necessary for economic feasibility and reiterating its view that a 25-year contract was required as a matter of law. CED further argued a 15-year contract was insufficient to secure financing and discriminatory because NorthWestern amortizes its generation assets over a period of 30 years. CED's witnesses presented additional statements alluding to previously experienced problems with 15-year contracts. ¶54 MCC and NorthWestern presented evidence of recent 15-year PPAs in Montana to demonstrate the economic feasibility of 15-year contracts. NorthWestern noted contract lengths may differ according to the factual circumstances and that the circumstances of this case merited a 15-year contract duration. The MCC, recognizing the Commission's competing obligations to satisfy PURPA as well as provide fair and reasonable rates for ratepayers, noted the risk longer contracts presented to ratepayers and argued that 15-year contracts appropriately balanced the risk to ratepayers and the opportunity to secure financing for QFs. Based on the evidence provided, the Commission found a 15-year contract sufficiently satisfied its competing obligations.
¶55 The Commission's Reconsideration Orders noted the lack of evidence supporting CED's position and remarked that CED framed its position as arguing a 25-year contract was necessary to obtain financing. The Commission found "In light of its position, it would be helpful for the Commission to have evidence as to the financing terms available to the project or direct evidence (not conclusory statements) that a 15-year term is not viable ... That evidence did not exist here." The Reconsideration Orders upheld the 15-year contract decision for all three projects.
¶56 CED argues the Commission failed to sufficiently justify its decision to set CED's contracts for 15 years, rather than the 25-year duration CED requested. Contract terms must enhance the economic feasibility and must allow for a return on investment, and the Commission's decision failed to weigh these considerations, CED contends. In reply, the Commission and NorthWestern point to language in Vote Solar that 15-year contracts are not per se unreasonable, notes that CED failed to provide specific testimony that would render the 15-year decision unreasonable and argues CED's net worth minimizes concerns of economic feasibility for the projects.
¶57 PURPA and Montana law encourage long-term contracts between utilities and QFs in order to enhance the economic feasibility of the QF. 16 U.S.C. § 824a-3(a) ; § 69-3-604(2), MCA. FERC provides that long-term contracts balance out any overestimations or underestimations of avoided costs so that neither the utility nor the QF is negatively impacted by market fluctuations. This in turn creates certainty regarding a return on investment for QF investors. FERC Order No. 69 at 12,224. While long-term contracts are encouraged, neither PURPA, FERC, nor Montana law provides a definition of "longterm." Balancing these concerns and adopting an appropriate contract duration thus falls to the Commission and, upon petition for judicial review, the courts.
¶58 The record contains sufficient evidence supporting the Commission's decision to adopt 15-year contract lengths. NorthWestern and MCC pointed to recent Commission decisions awarding 15-year contracts to wind generators in Montana to demonstrate the economic feasibility of 15-year contracts. NorthWestern noted contract lengths may differ according to the factual circumstances of the case. The MCC argued a 15-year contract struck the appropriate balance between enhancing economic feasibility for QFs and protecting Montana's ratepayers from unnecessary risk presented by longer contracts. These considerations informed the Commission's decision, which complied with our holding in Vote Solar , wherein we noted "the requirement that service commissions consider both the length of contracts alongside contract prices, recognizing the synergistic effect of these dual considerations." Vote Solar , ¶ 72. The Commission considered the evidence presented and the effect a 15-year contract could have on the corresponding avoided cost rate, ultimately finding the rate would not be discriminatory.
¶59 Conversely, the record lacks substantial evidence to support CED's requested 25-year contract duration. In its petition to set contract terms, CED argued it was entitled to a 25-year contract as a matter of law, citing the Eighth Judicial District Court's ruling reversing a 15-year contract in Vote Solar , which we affirmed on appeal. Vote Solar , ¶ 73. However, our holding in Vote Solar does not support CED's position. In Vote Solar , we reversed the Commission's decision to adopt a 15-year contract because it "was based almost entirely on a 2014 North Carolina Utilities Commission decision." Vote Solar , ¶ 69. We cited the Commission's lack of knowledge regarding QF development policies in North Carolina and noted the lack of evidence explaining why 15-year contracts balanced the need for certainty regarding a return on investment. Vote Solar , ¶ 70. That is not the case here. The Commission's decision relied on recent Montana contract decisions, not out of state considerations, and the record indicates NorthWestern and MCC provided testimony explaining how the 15-year contract balanced the competing interests of QFs and ratepayers and allowed for economic feasibility.
¶60 While we concluded in Vote Solar , given the lack of record support, the Commission acted arbitrarily, we noted "15-year contracts, standing alone, are not per se unreasonable." Vote Solar , ¶ 73. It is this language CED relies on in urging us to reverse the Commission's decision. Doing so would effectively require 20- to 25-year contracts for every QF, regardless of circumstances. While district court decisions do set precedent, CED's position would effectively strip the Commission of the ability to evaluate each request to set contractual terms on the basis of its individual facts, such as economic conditions, financing environment, and energy market forecasts, while insulating QFs and exposing ratepayers to greater risk. We decline to take such a position. If a QF believes the Commission erred, that decision can be reviewed by the courts following the filing of a petition by the QF. See Krakauer v. State , 2016 MT 230, ¶ 41, 384 Mont. 527, 381 P.3d 524 (disagreeing with the premise that a district court order in one scenario binds the Commissioner of Higher Education in subsequent cases).
¶61 Neither CED's testimony that 25-year contracts generally prove necessary for QF feasibility nor its vague assertions concerning "problems" with 15-year contracts convince us the Commission erred. This testimony, and the general assertions of discrimination, fails to identify specific issues with the 15-year contract length. The Commission found these general, conclusory statements unconvincing and insufficient to support a 25-year contract. The Commission noted its belief that the Eighth Judicial District Court decision in Vote Solar was not binding and that contract lengths may vary depending upon circumstances. The Commission pointed to several recent 15-year contracts, as well as a decision in which the Commission established a 20-year contract due to the unproven hybrid nature of the generator in that case, to demonstrate the factual basis upon which it establishes contracts.
¶62 Our review is confined to the record before us. The record provides no support for CED's conclusory statements that a 15-year contract duration was not viable for its projects. The record supports the Commission's decision to adopt a 15-year contract. The District Court correctly upheld the Commission's decision on contract length.
CONCLUSION
¶63 The District Court erred in affirming the Commission's orders as related to the interconnection costs associated with the transmission line under Issue I. On remand, the Commission's assignment of interconnection costs requires analysis concerning the proportional impact of QF projects on NorthWestern's system.
¶64 The District Court did not err in affirming the Commission's orders as related to Issues II through IV. Substantial evidence supported each of the Commission's decisions under Issues II through IV, and we are not convinced these decisions were clearly erroneous, arbitrary, capricious, or characterized an abuse of discretion. Section 2-4-704(2)(a), MCA. However, as we are remanding under Issue I, we likewise remand under Issue II to allow both parties to present avoided costs estimates using the proxy methodology adopted by the Commission. The District Court's Order is affirmed in part, reversed in part, and remanded for proceedings consistent with this Opinion.
We concur:
MIKE McGRATH, C.J.
JAMES JEREMIAH SHEA, J.
BETH BAKER, J.
INGRID GUSTAFSON, J.
DIRK M. SANDEFUR, J.
JIM RICE, J.