From Casetext: Smarter Legal Research

Cassidy v. Highrise Hoisting & Scaffolding Inc.

Supreme Court, Appellate Division, First Department, New York.
Nov 10, 2011
89 A.D.3d 510 (N.Y. App. Div. 2011)

Summary

In Cassidy, the plaintiff, a laborer employed by a concrete subcontractor, was injured while working on a temporary loading dock (89 AD3d at 510).

Summary of this case from Simms v. Tishman Constr. Corp.

Opinion

2011-11-10

Robert Sands CASSIDY, Plaintiff–Respondent–Appellant,v.HIGHRISE HOISTING & SCAFFOLDING, INC., Defendant,Rockrose GC MWA L.L.C., et al., Defendants–Appellants–Respondents.

Fabiani Cohen & Hall, LLP, New York (Kevin B. Pollack of counsel), for appellants-respondents.O'Dwyer & Bernstien, LLP, New York (Steven Aripotch of counsel), for respondent-appellant.


Fabiani Cohen & Hall, LLP, New York (Kevin B. Pollack of counsel), for appellants-respondents.O'Dwyer & Bernstien, LLP, New York (Steven Aripotch of counsel), for respondent-appellant.

Order, Supreme Court, New York County (Marylin G. Diamond, J.), entered August 5, 2010, which granted plaintiff's motion for summary judgment on his claim pursuant to Labor Law § 240(1), and granted defendants-appellants' cross motion for summary judgment as to plaintiff's Labor Law §§ 241(6) and 200, and common law causes of action, unanimously affirmed, without costs.

At the time of plaintiff's accident, Midtown West A.L.L.C. owned a building under construction, for which Rockrose GC MWA L.L.C. was the general contractor. Defendant Highrise Hoisting and Scaffolding, Inc. had installed a sidewalk bridge, hoistway and temporary loading dock. The temporary loading dock constructed by Highrise was a wooden platform measuring 20 feet by 40 feet and was, depending upon the witness, approximately 48 to 60 inches above the ground, about the height of a trailer truck. At the section of the loading dock where trucks load and unload, there was a removable horizontal pipe railing that was approximately 8 feet long and 2 inches in diameter. The horizontal pipe railing was secured to vertical posts with clamps at each end, and tightened into place with a nut and bolt. In order to allow for a delivery, the horizontal pipe railing would be unbolted from the clamps and removed.

Plaintiff, a laborer employed by the non-party concrete sub-contractor, was waiting for the hoist to come to the loading dock level, when he leaned against the dock railing, which fell, causing him to fall as well. He suffered personal injuries to his neck and back.

The motion court properly granted plaintiff summary judgment on his Labor Law § 240(1) claims. Plaintiff was performing work protected by Labor Law § 240(1), his injuries were gravity-related, and the elevated platform served as a device designed to protect a worker from gravity-related hazards ( see Brennan v. RCP Assoc., 257 A.D.2d 389, 391, 683 N.Y.S.2d 69 [1999], lv. dismissed 93 N.Y.2d 889, 689 N.Y.S.2d 431, 711 N.E.2d 645 [1999]; see also Cordeiro v. TS Midtown Holdings, LLC, 87 A.D.3d 904, 931 N.Y.S.2d 41 [2011] ). Since the safety rail which was intended to protect the plaintiff from falling off the elevated platform failed, the owner and the general contractor were in violation of § 240(1).

However, defendants established that plaintiff could not recover under Labor Law § 241(6). Since the temporary loading dock was a platform under Industrial Code § 23–1.22(c)(2), and not a scaffold, plaintiff failed to plead any applicable Industrial Code violations to support his claim ( see Ross v. Curtis–Palmer Hydro–Elec. Co., 81 N.Y.2d 494, 501–504, 601 N.Y.S.2d 49, 618 N.E.2d 82 [1993] ).

Plaintiff's common law and Labor Law § 200 claims were also properly dismissed. There is no evidence that defendants were on notice that the rail, which had been detached for a delivery made within 1/2 hour prior to plaintiff's fall, was improperly re-attached. The affidavit of plaintiffs' site safety expert failed to create questions of fact warranting denial of summary judgment. An expert's opinion should be disregarded where no authority, treatise, standard, building code, article or other corroborating evidence is cited to support the assertion concerning an alleged deviation from good and accepted industry custom and practice ( Buchholz v. Trump 767 Fifth Ave., LLC, 5 N.Y.3d 1, 2, 798 N.Y.S.2d 715, 831 N.E.2d 960 [2005] ). “Before a claimed industry standard is accepted by a court as applicable to the facts of a case, the expert must do

more than merely assert a personal belief that the claimed industry-wide standard existed at the time the design was put in place” ( Hotaling v. City of New York, 55 A.D.3d 396, 398, 866 N.Y.S.2d 117 [2008], affd. 12 N.Y.3d 862, 881 N.Y.S.2d 655, 909 N.E.2d 577 [2009] ).

We decline to reach defendants' argument concerning Labor Law § 240(3), raised for the first time in their appellate reply brief.


Summaries of

Cassidy v. Highrise Hoisting & Scaffolding Inc.

Supreme Court, Appellate Division, First Department, New York.
Nov 10, 2011
89 A.D.3d 510 (N.Y. App. Div. 2011)

In Cassidy, the plaintiff, a laborer employed by a concrete subcontractor, was injured while working on a temporary loading dock (89 AD3d at 510).

Summary of this case from Simms v. Tishman Constr. Corp.
Case details for

Cassidy v. Highrise Hoisting & Scaffolding Inc.

Case Details

Full title:Robert Sands CASSIDY, Plaintiff–Respondent–Appellant,v.HIGHRISE HOISTING …

Court:Supreme Court, Appellate Division, First Department, New York.

Date published: Nov 10, 2011

Citations

89 A.D.3d 510 (N.Y. App. Div. 2011)
932 N.Y.S.2d 456
2011 N.Y. Slip Op. 7936

Citing Cases

Winter v. Church

Etheridge v Marion A. Daniel & Sons, Inc., 96 AD3d 436 (1st Dept 2012); McGuire v 3901 Independence Owners,…

Stefatos v. Frezza

Plaintiffs offer no substantive arguments in their opening brief regarding their declaratory judgment,…