From Casetext: Smarter Legal Research

Carter v. Sherwood Plaza, Inc.

Court of Appeals of Georgia
Oct 8, 1968
164 S.E.2d 867 (Ga. Ct. App. 1968)

Opinion

43846.

ARGUED SEPTEMBER 9, 1968.

DECIDED OCTOBER 8, 1968. REHEARING DENIED NOVEMBER 7, 1968.

Garnishment. Hall City Court. Before Judge Smith.

Stow, Garvin Glenn, Frank B. Stow, for appellant.

Telford, Wayne Stewart, for appellee.


On the trial of the traverse to an answer of not indebted in a garnishment action the garnishee was entitled to prove that it owed the defendant in fi. fa. nothing because the defendant, a contractor, had abandoned its contract to improve the real estate of the owner-garnishee at a time when he had paid the defendant an amount on the contract price in excess of the value of the work completed, and that payments subsequently made by the garnishee to materialmen, or to a materialman and the defendant jointly, were in fact payments for materials used in the construction for which the garnishee had pledged its personal credit as an inducement for further credit deliveries to the contractor, prior to the service of the summons of garnishment.

ARGUED SEPTEMBER 9, 1968 — DECIDED OCTOBER 8, 1968 — REHEARING DENIED NOVEMBER 7, 1968 — CERT. APPLIED FOR.


Carter filed an affidavit and bond for garnishment on Sherwood Plaza, Inc., which was served December 7, 1965, based on a judgment against Lanier Roofing Metal Co., Inc. The garnishee answered not indebted on January 10, 1966. Following a traverse, the issue was tried before a jury which returned a verdict in favor of the garnishee. The evidence construed in favor of the verdict was that Sherwood Plaza, Inc., was engaged in constructing a shopping center and entered into a written contract with Lanier Roofing Metal Co., Inc., for certain roofing, gutter and flashing installations at a price of $20,000; that the contract was never completed and was in fact less than 50% completed by Lanier for which was paid "approximately $7,000 more than 50%" of the contract price; that Lanier, at some unspecified date, went into receivership, and that the garnishee agreed with Lanier's president, Reed, that Reed individually, trading as Reed Roofing Metal Company, should complete the contract, that Reed did some further work between November, 1965, when Lanier quit and May, 1966; that counting the work both Reed and Lanier did, the contract was about 60% completed and the garnishee then completed it at a total cost of $26,000. The witness further testified that during the course of the work by Lanier various materialmen who were not being paid refused to deliver further materials which Lanier had to have to go on with the work, and that an arrangement was entered into by which certain accounts were guaranteed by Sherwood Plaza in order to obtain the materials, at the suggestion of Reed acting for Lanier Roofing Co. Much of this testimony was contradicted by the plaintiff, who further proved that following the service of the summons of garnishment and prior to its answer the garnishee had drawn a check in the sum of $2,401 payable to "Parks Lumber Co. and Lanier Roofing Co."; that between April and July, 1966, it had paid out several checks to Parks Lumber Co. and to Philyaw Co., another materialman, and that early in 1966 it had twice written Reed and/or Lanier Roofing Metal Co. calling on them to complete the contract.

The plaintiff appeals from the denial of his motions for new trial and for judgment notwithstanding the verdict.


We agree with the appellant that the lien created by service of the summons of garnishment may not be defeated by arrangements between the defendant and the garnishee for that purpose ( Legg v. Spratlin, 37 Ga. App. 392 ( 140 S.E. 518)), and also that the test of whether funds in the hands of a third person are subject to garnishment is whether or not the original defendant could himself recover such funds by suit directly against the garnishee ( Butler v. Billups, 101 Ga. 102 ( 28 S.E. 615)). Under the testimony of the garnishee's officer in charge of building construction, the defendant abandoned the contract at a time when it had been paid more than 50% of the contract price for less than 50% of the contract work, and accordingly the defendant could not have collected any further amount from the garnishee whose real estate was being improved. Spirides v. Victory Lumber Co., 76 Ga. App. 78, 81 ( 45 S.E.2d 65); Prince v. Neal-Millard Co., 124 Ga. 884 ( 53 S.E. 761, 4 AC 615). The plaintiff attempted to counter this defense by showing that the garnishee had in fact made payments on the contract price after the summons of garnishment was served upon it. The garnishee admitted this, but contended that the payments were made direct to materialmen under a prior agreement between the parties necessitated by the fact that the materialmen had refused to make further deliveries to the contractor unless payment was made or guaranteed by Sherwood. We dealt with a somewhat analogous situation in Melton v. Lowe, 117 Ga. App. 783 ( 161 S.E.2d 912). There it was held that, on a question of priority of materialmen's liens, the owner might pledge his personal credit in order to induce materialmen to continue to make deliveries to the contractor and thereby render himself personally liable; that actual payment by him nevertheless constituted a preference, which would amount to payment of the contract price so as to defeat the inchoate lien of other materialmen only until such time as their liens were actually filed, but that after a lien was filed by other materialmen working on the same project the preference would be illegal, the fund being available to all who had perfected their liens pro tanto. Carter's claim in the present case does not fall under this rule because he was not a materialman, his judgment against the defendant arose from an unrelated transaction, and the only question he is entitled to pose is whether or not the owner was indebted to the contractor at the time of the garnishment. There was evidence to support a jury conclusion that Sherwood was not indebted to Lanier because Lanier had abandoned its contract, and that Sherwood's indebtedness to Philyaw and Parks Lumber Company arose from a personal pledge of credit to induce these materialmen to continue deliveries to Lanier for use on the job, independently of its contract obligations to Lanier and Lanier's indebtedness to these suppliers. It is greatly to be doubted under the facts in evidence that Lanier, had it filed suit against Sherwood on December 7, 1965, would under this evidence have recovered the balance of the contract price or any part thereof. Furthermore, "the statute [creating materialman's liens] operates as a sort of automatic garnishment, which without summons or service impounds the fund due by the owner, and requires it to be held up until the expiration of the time named in the statute. But if nothing becomes due to the contractor, there is nothing caught. There is no fund out of which those employed by him are to be paid. For in all these cases it must be understood that the contractor's employees are to be paid out of the contractor's money." Rowell v. Harris, 121 Ga. 239, 240 ( 48 S.E. 948). In the present case, the evidence authorizes the conclusions that the fund, if any was due the contractor, was already subject to the inchoate lien of the materialmen paid by the garnishee, that nothing was in fact due because the defendant had abandoned the contract, and that the garnishee's liability was not only secondary as to the owner but primary because of its personal guarantee of payment. The letters written by the garnishee subsequent to December 7, 1965, calling on Lanier and/or Reed to complete the contract constitute evidence contrary to the appellee's contentions, but do not demand a contrary conclusion in view of the explanatory testimony.

Judgment affirmed. Jordan, P. J., and Pannell, J., concur.


Summaries of

Carter v. Sherwood Plaza, Inc.

Court of Appeals of Georgia
Oct 8, 1968
164 S.E.2d 867 (Ga. Ct. App. 1968)
Case details for

Carter v. Sherwood Plaza, Inc.

Case Details

Full title:CARTER v. SHERWOOD PLAZA, INC

Court:Court of Appeals of Georgia

Date published: Oct 8, 1968

Citations

164 S.E.2d 867 (Ga. Ct. App. 1968)
164 S.E.2d 867

Citing Cases

Vulcan Materials v. Hall

Held: The trial judge properly based his judgment on the case of Carter v. Sherwood Plaza, 118 Ga. App. 612 (…

Morgan v. Morgan

4. The test as to whether funds in the hands of another are subject to garnishment is whether or not the…