From Casetext: Smarter Legal Research

Capital Siding & Constr., LLC v. Alltek Energy Sys., Inc.

STATE OF NEW YORK SUPREME COURT COMMERCIAL DIVISION COUNTY OF ALBANY
Mar 13, 2015
2016 N.Y. Slip Op. 31043 (N.Y. Sup. Ct. 2015)

Opinion

Index No. 5644-14

03-13-2015

CAPITAL SIDING & CONSTRUCTION, LLC d/b/a ABAR CONSTRUCTION Petitioner, For Judgment Pursuant to Article 75 of the CPLR v. ALLTEK ENERGY SYSTEM, INC., Respondent.

APPEARANCES: FOX & KOWALEWSKI, LLP Attorneys for Petitioner (Brendan R. Wolf, of counsel) 4 Old Route 146 P.O. Box 958 Clifton Park, New York 12065 MCNAMEE, LOCHNER, TITUS & WILLIAMS, P.C. Attorneys for Respondent (Kevin Laurilliard, of counsel) 677 Broadway Albany, New York 12207


COPY

DECISION & ORDER RJI No.: 01-14-115464 (Judge Richard M. Platkin, Presiding) APPEARANCES: FOX & KOWALEWSKI, LLP
Attorneys for Petitioner
(Brendan R. Wolf, of counsel)
4 Old Route 146
P.O. Box 958
Clifton Park, New York 12065 MCNAMEE, LOCHNER, TITUS & WILLIAMS, P.C.
Attorneys for Respondent
(Kevin Laurilliard, of counsel)
677 Broadway
Albany, New York 12207 Hon. Richard M. Platkin, A.J.S.C.

In this proceeding brought pursuant to CPLR article 75, petitioner Capital Siding & Construction, LLC d/b/a Abar Construction ("Abar Construction") seeks an order and judgment permanently staying the arbitration demanded by respondent Alltek Energy System, Inc. ("Alltek") on the ground that there is a valid agreement to litigate all disputes between the parties and no agreement to arbitrate. BACKGROUND

On or about March 13, 2013, petitioner entered into a contract ("Contract") with the owner of 581 Livingston Avenue, LLC to demolish an existing structure and construct new senior housing apartments. On or about June 4, 2013, the parties entered into a subcontract ("Subcontract") whereby respondent would perform the mechanical and HVAC work. Petitioner alleges that after respondent failed to fully perform the subcontracted work, it permissibly withheld certain funds from respondent.

On or about October 17, 2014, petitioner received a Statement of Intention to Arbitrate ("Statement") pursuant to CPLR 7503 and General Business Law ("GBL") article 35-E. Petitioner now seeks to permanently stay this arbitration on the ground that Section 6.2 of the Subcontract provides for litigation of any disputes arising under the agreement. ANALYSIS

CPLR 7503 (b) provides that a party served with a demand for arbitration may apply for a permanent stay of the arbitration on the ground that a valid agreement to arbitrate has not been made. Here, the Subcontract provides that any claim not resolved by mediation shall be subject to binding resolution through litigation in a court of competent jurisdiction. Thus, there is no contractual agreement between the parties to arbitrate.

However, respondent's claims against petitioner arise under General Business Law article 35-E, also known as the "Prompt Payment Act" ("PPA"), a statutory scheme that governs payment procedures and remedies for private non-residential construction contracts in excess of a specified dollar threshold (see GBL § 756 [1]). If efforts to resolve a dispute arising under the PPA are unsuccessful, the aggrieved party may refer the matter to expedited arbitration before the American Arbitration Association (id.§ 756-b [3]). As the foregoing statute confers upon respondent the right to initiate binding arbitration, the absence of a contractual agreement to arbitrate is of no moment.

In seeking to deny respondent the arbitral rights granted by GBL § 756-b (3), petitioner relies upon GBL § 756-a, which, in pertinent part, reads as follows:

It is the policy and purpose of this article to expedite payment of all monies owed to those who perform contracting services pursuant to construction contracts. Except as otherwise provided in this article, the terms and conditions of a construction contract shall supersede the provisions of this article and govern the conduct of the parties thereto.
Thus, petitioner argues that the mutually agreed-upon dispute resolution procedures of the Subcontract - mediation followed by litigation in a court of competent jurisdiction - are controlling.

While GBL § 756-a establishes a general policy of giving primacy to the terms of the parties' negotiated agreement, the "[e]xcept as otherwise provided" language used by the Legislature necessarily contemplates certain exceptions to that rule. As observed by respondent, one such exception is GBL § 757 (3). Added by the Legislature to the PPA in 2009, GBL § 757 (3) renders void and unenforceable any contractual provision that denies an aggrieved party the right to expedited arbitration under GBL § 756-b (see L 2009, ch 417, § 5). Thus, insofar as petitioner maintains that Section 6.2 of the Subcontract operates to deny respondent the right to pursue arbitration of its PPA claims, the clear and unambiguous language of GBL § 757 (3) renders the Subcontract void and unenforceable to that limited extent.

To the extent that Supreme Court, New York County may have held otherwise in Turner Constr. Co. v J & A Concrete Corp. (44 Misc 3d 217 [2014]) - a decision relied upon by petitioner that does not even cite or re er to GBL § 757 (3) - this Court respectfully disagrees.

Based on the foregoing, the Court concludes that petitioner has failed to demonstrate its entitlement to the requested permanent stay of arbitration.

Accordingly, it is

ORDERED that petitioner's application for a permanent stay of arbitration is denied.

This constitutes the Decision & Order of the Court. The original of this Decision & Order is being returned to respondent's counsel; all other papers are being transmitted to the Albany County Clerk. The signing of this Decision & Order shall not constitute entry or filing under CPLR Rule 2220. Counsel is not relieved from the applicable provisions of that Rule respecting filing, entry and Notice of Entry. Dated: March 13, 2015

Albany, New York

/s/_________

RICHARD M. PLATKIN, A.J.S.C.


Summaries of

Capital Siding & Constr., LLC v. Alltek Energy Sys., Inc.

STATE OF NEW YORK SUPREME COURT COMMERCIAL DIVISION COUNTY OF ALBANY
Mar 13, 2015
2016 N.Y. Slip Op. 31043 (N.Y. Sup. Ct. 2015)
Case details for

Capital Siding & Constr., LLC v. Alltek Energy Sys., Inc.

Case Details

Full title:CAPITAL SIDING & CONSTRUCTION, LLC d/b/a ABAR CONSTRUCTION Petitioner, For…

Court:STATE OF NEW YORK SUPREME COURT COMMERCIAL DIVISION COUNTY OF ALBANY

Date published: Mar 13, 2015

Citations

2016 N.Y. Slip Op. 31043 (N.Y. Sup. Ct. 2015)

Citing Cases

Flintlock Constr. Servs., LLC v. Glob. Precast, Inc.

As the foregoing statute confers upon Global the right to initiate binding arbitration, the absence of a…