From Casetext: Smarter Legal Research

Byron v. Low

Court of Appeals of the State of New York
Apr 10, 1888
16 N.E. 45 (N.Y. 1888)

Summary

In Byron v. Low (109 N.Y. 294), where the provision in the contract was that his (the chief engineer's) determination was final and binding upon both parties, the court said: "Under this provision the certificate of the engineer became a condition precedent to the plaintiff's right of action.

Summary of this case from Del Genovese v. Third Avenue R.R. Co.

Opinion

Argued March 22, 1888

Decided April 10, 1888

William J. Groo for appellant.

L. Laflin Kellogg for respondent.



We are unable to deny the force of several propositions relied upon by the appellant. By the terms of the contract the chief engineer of the Construction Company was made the arbitrator between the parties to settle all differences arising out of the contract, to estimate the quantities and amounts of the several kinds of work and make monthly certificates for the same, reserving ten per cent thereof. The final payment to be made was provided for in these words: "But in case of the full completion of said work by the party of the first part, then, and upon the final estimate thereof by the said chief engineer, the said party of the second part agrees to pay, within ten days, to the party of the first part, the full amount then due, including the reserve of ten per cent." Under this provision the certificate of the engineer became a condition precedent to the plaintiff's right of action. The chosen arbitrator was to fix the amount of the final payment and the same was to become due in ten days after such final estimate was made. The provision comes clearly within the rule which makes such certificate a condition precedent to the right of recovery. ( Pres't, etc., D. H. Canal Co. v. Pa. Coal Co., 50 N.Y. 250.) The first answer made to this difficulty is, that the plaintiff demanded a certificate of the engineer after the close of the work, which was refused. There is no evidence either of such demand or refusal before the commencement of the action. On his direct examination the plaintiff claimed to have made such a demand, but on cross-examination he explains precisely what it was, and it turned out to be merely a repeated inquiry whether "the returns were in," that is, whether the estimates and measurements of the division engineers had been returned to the chief engineer, so that he could make the final estimate. There was no demand of the certificate and no refusal, even according to plaintiff's version of the facts, and no question upon that subject to be submitted to the jury. The claim made on the argument that the demand sworn to by plaintiff was different from the one explained on cross-examination, is entirely dispelled by a careful reading of the testimony. On the motion for a nonsuit the court expressly and correctly said, "there is no pretense that the certificate was furnished or demanded." It is then said, and that is the ground upon which the case was submitted to the jury, that the contract was broken by the defendant in refusing to allow plaintiff to do the mason work at Broadhead's Creek, and if that was found to be the fact no final certificate of the engineer was requisite or necessary.

This doctrine proceeds upon an erroneous view of the rights of the parties. The action was not brought upon a quantum meruit, upon the ground that the contract had been rescinded and no longer subsisted, or to rescind or annul it. On the contrary, it was brought to enforce it and necessarily affirmed it. ( Quinn v. Van Pelt, 56 N.Y. 417.) It went upon the theory that there had been a full and final performance, since the work not done was omitted by the defendant's direction, and not through the fault of plaintiff. As to that, readiness to perform was equivalent to performance, and the plaintiff came into court standing upon the contract, demanding payment according to its terms and damages for the work withdrawn. That he had a right to do. In McMaster v. The State ( 108 N.Y. 542) we held that a breach in one respect was not necessarily waived by a continued performance thereafter, but that the contractor could go on and complete his contract, so far as possible, and recover according to its terms with damages for the breach, but those damages themselves founded upon the stipulations of the agreement. That is what this plaintiff did. The part of his work at Broadhead's Creek was, without difficulty, severable from the body of the contract. The defendant wrongfully, as we must assume from the verdict of the jury, in September of 1881 gave that work to others. The plaintiff, notwithstanding, continued his performance of the contract for a year or more, obeying its requirements and taking payments according to its terms. He now sues upon the contract to compel the performance or its equivalent by the defendant, and necessarily stands upon and affirms it. He cannot, in the present form of action, affirm it for one purpose and repudiate it for another. He cannot recover upon it as binding upon the defendant and deny its obligations upon himself. Hence, the condition precedent of the engineer's certificate could not be disregarded. When the amount to which plaintiff is entitled for the work done is settled and fixed by the selected arbitrator, that amount becomes due in ten days thereafter, and when it has been recovered, together with the damages, if any, for the work withdrawn, the plaintiff gets his exact rights under the contract on which he sues, and both parties have been made to obey its substantial terms. As the case was tried, the contract was held to subsist for some purposes, but not for others, and to bind the defendant but not the plaintiff. The exceptions to such rulings must, therefore, be sustained.

The judgment should be reversed and a new trial granted, costs to abide the event.

All concur.

Judgment reversed.


Summaries of

Byron v. Low

Court of Appeals of the State of New York
Apr 10, 1888
16 N.E. 45 (N.Y. 1888)

In Byron v. Low (109 N.Y. 294), where the provision in the contract was that his (the chief engineer's) determination was final and binding upon both parties, the court said: "Under this provision the certificate of the engineer became a condition precedent to the plaintiff's right of action.

Summary of this case from Del Genovese v. Third Avenue R.R. Co.
Case details for

Byron v. Low

Case Details

Full title:JOHN H. BYRON, Respondent, v . HENRY R. LOW, Appellant

Court:Court of Appeals of the State of New York

Date published: Apr 10, 1888

Citations

16 N.E. 45 (N.Y. 1888)
16 N.E. 45
14 N.Y. St. Rptr. 823

Citing Cases

Jones v. Savage

The architects have so certified, and no fraud, mistake or corruption impeaches or countervails this…

Zimmerman v. German Luth. Church

The architect, being the chosen arbitrator, must determine the character of the work under the contract, and…