From Casetext: Smarter Legal Research

Burton v. Campbell Coal Co.

Court of Appeals of Georgia
Feb 27, 1957
97 S.E.2d 924 (Ga. Ct. App. 1957)

Opinion

36480.

DECIDED FEBRUARY 27, 1957. REHEARING DENIED MARCH 19, 1957.

Action on contract; recoupment. Before Judge Parker. Fulton Civil Court. October 4, 1956.

Wilson, Branch Barwick, John W. Wilcox, Jr., John E. Branch, for plaintiff in error.

Moise, Post Gardner, R. Emerson Gardner, Charles F. Barnwell, contra.


The trial court erred in denying the motion for new trial.

DECIDED FEBRUARY 27, 1957 — REHEARING DENIED MARCH 19, 1957.


R. F. Burton, trading as R. F. Burton Company, brought an action against Campbell Coal Company to recover a balance of $3,018.79 allegedly due for services rendered beginning March 11, 1955, for the defendant in connection with the construction of a "Ready Mix Concrete Plant" at East Point, Georgia. The defendant denied that it was indebted to the plaintiff, and by way of a plea of recoupment alleged, that while it was engaged in the construction of a concrete mixing plant the plaintiff contracted with it to install a conveyor system to be used in the removal of sand, gravel, and other like products from railroad cars to bins from which the same could be removed to an elevated receptacle where such products would be converted into ready mixed concrete, that prior to March 11, 1955, the defendant entered into an agreement with the plaintiff for the complete erection and installation of such conveyor system, but that because of the unskillful and improper manner in which the plaintiff did certain of the work in connection with the construction of such conveyor system, the system was damaged in the amount of $2,696.63. On the trial the plaintiff made an oral motion to strike the "plea of recoupment" because it did not set up a cause of action upon which a recovery could be had by recoupment and by way of defense against his action. The trial judge, who heard the case without the intervention of a jury, denied this motion and entered judgment for the defendant. The plaintiff filed a motion for new trial on the usual general grounds, which he later amended so as to include several special grounds. The amended motion for new trial was denied, and it is to this judgment that he excepts, as well as to the judgment denying his oral motion to dismiss the defendant's plea of recoupment.


1. Code § 20-1311 defines recoupment as: "Recoupment is a right of the defendant to have a deduction from the amount of the plaintiff's damages, for the reason that the plaintiff has not complied with the cross-obligations or independent covenants arising under the same contract," and under Code § 20-1312 recoupment is confined to the contract on which the plaintiff's suit is brought, and does not include all mutual debts and liabilities as does setoff. Code § 20-1314 sets forth the actions in which recoupment may be pleaded: "Recoupment may be pleaded in all actions ex contractu, where from any reason the plaintiff under the same contract is in good conscience liable to defendant. In all cases where recoupment may be pleaded, if the damages of the defendant shall exceed in amount those of the plaintiff, the defendant shall recover of the plaintiff the amount of such excess."

Therefore, since the defendant's plea of recoupment in the present case seeks to recoup against the plaintiff's action on the contract with a plea that it, the defendant, was forced to spend a certain amount of money to have the conveyor system, which the plaintiff erected under the contract, repaired due to the unskillful and improper manner in which the plaintiff did certain of the work, the trial court did not err in denying the motion to strike the plea of recoupment. See Allied Enterprises v. Brooks, 93 Ga. App. 832 ( 93 S.E.2d 392).

2. Special ground 4 of the motion for new trial complains of a ruling on pleadings and is not a proper ground of a motion for new trial. Ray v. Woods, 93 Ga. App. 763 ( 92 S.E.2d 820), and citations.

3. Special grounds 2 and 3 complain of the rejection of certain documentary evidence offered by the plaintiff. An examination of these special grounds shows that the evidence in one special ground was the preliminary specifications of the work to be done by the plaintiff, but not the specifications on which the contract between the parties was finally entered into, and the other evidence was an excerpt from a manual mentioned in the preliminary specifications but not in the final specifications on which the contract was based, nor was there any evidence that the excerpt from the manual was such a custom that would have authorized its introduction in evidence.

This evidence would have had no bearing on the actual contract between the parties and was therefore irrelevant to the issue tried, and the trial judge did not err in sustaining the objections to its introduction.

4. Special ground 1 assigns error on the admission in evidence of a statement of the wind velocity measured at the Weather Bureau Airport Station, Atlanta, Georgia, on April 2, 1955. There was other evidence that the site of the construction was two miles from the weather station.

It has long been the rule in this State that where the relevancy or competency of evidence is doubtful, it should be admitted and its weight left to the jury. See Lovejoy v. Tidwell, 212 Ga. 750, 751 ( 95 S.E.2d 784). In cases where the judge hears the case without the intervention of a jury the rules as to admission of evidence are less strict. Ward v. State, 26 Ga. App. 61 ( 105 S.E. 373). However, as will be shown in dealing with the general grounds of the motion for new trial this evidence was irrelevant.

5. It was admitted that, if the plaintiff was not responsible for the "cars" installed on the conveyor system falling, the defendant was indebted to the plaintiff in the full amount sued for.

The defendant introduced in evidence the statement of the wind velocity, and stated through its counsel that it was relying on the doctrine of res ipsa loquitur to make out its plea of recoupment. In order for the doctrine of res ipsa loquitur to be applicable in a case such as this it must be shown that the defendant (here the plaintiff, where the defendant sought to rely on such doctrine to support its plea of recoupment), had control of the premises. See Sinkovitz v. Peters Land Co., 5 Ga. App. 788 ( 64 S.E. 93); Candler v. Automatic Heating Inc., 40 Ga. App. 280 ( 149 S.E. 287), and Spruell v. Ga. Automatic Gas c. Co., 84 Ga. App. 657, 665 ( 67 S.E.2d 178). The evidence as to who was in control of the construction shows conclusively that the defendant was engaged in building a concrete mixing plant, that the plaintiff was contracted with for the sole purpose of erecting the conveyor system in conjunction with the mixing plant, that the defendant, after the plaintiff had left the job due to a shortage of parts, employed other help to install reinforcing bars on the frames on which the conveyor system was installed, that the plaintiff had no knowledge of this until after the "cars" had fallen, and that other "crafts" employed by the defendant were working all over the system while the plaintiff was erecting the conveyor system. Therefore, since the plaintiff did not have control of the premises, and since the defendant did not prove that while the plaintiff was away from the job waiting on a supply of materials or parts no other persons did anything which within the realm of reason could have caused the fixture to be so changed from the condition in which the plaintiff left it as to result in the damage to the conveyor system complained of (see Macon Coca-Cola Bottling Co. v. Crane, 55 Ga. App. 573, 190 S.E. 879), the doctrine of res ipsa loquitur has no application in the present case, and since there was no evidence to support the allegations of the plea of recoupment the judgment for the defendant was not authorized by the evidence and was without evidence to support it.

Moreover, the case is distinguishable from those cases where a contractor is employed to completely erect a building and such building is destroyed before it is completed, inasmuch as the plaintiff was employed to do only one segment of the entire construction. 9 Am. Jur. 45, § 63.

Accordingly, the trial court erred in denying the plaintiff's motion for new trial on the usual general grounds.

Judgment reversed. Felton, C. J., and Quillian, J., concur.

ON MOTION FOR REHEARING.

Counsel for the Campbell Coal Company on motion for rehearing contends that even though during the trial of the case it was stated that the doctrine of res ipsa loquitur was being relied on to support its contention that the plaintiff was liable on the defendant's plea of recoupment that this should not exclude the defendant from making out its plea of recoupment by circumstantial evidence. With this contention of the defendant the court agrees; however, the evidence in the present case failed to support the defendant's plea of recoupment either under the doctrine of res ipsa loquitur or under the rules as to circumstantial evidence, and there was no direct evidence that any alleged negligence of the plaintiff caused the cars to fall from the elevated tracks of the conveyor system. Accordingly, the motion for rehearing is denied.


Summaries of

Burton v. Campbell Coal Co.

Court of Appeals of Georgia
Feb 27, 1957
97 S.E.2d 924 (Ga. Ct. App. 1957)
Case details for

Burton v. Campbell Coal Co.

Case Details

Full title:BURTON v. CAMPBELL COAL COMPANY

Court:Court of Appeals of Georgia

Date published: Feb 27, 1957

Citations

97 S.E.2d 924 (Ga. Ct. App. 1957)
97 S.E.2d 924

Citing Cases

Augusta Roofing c., Inc. v. Clemmons

On the trial of a case before a judge without the intervention of a jury the rules as to the admission of…

Monroe v. C. S. Nat. Bank

The relevancy of this evidence having been conceded, its admissibility was at least no more than doubtful,…