From Casetext: Smarter Legal Research

Boskovich v. Utah Const. Co.

Supreme Court of Utah
Aug 7, 1953
259 P.2d 885 (Utah 1953)

Opinion

No. 7833.

Decided August 7, 1953.

Action for a balance alleged to be due plaintiff from defendant corporation for its use of a mucker, invented and patented by plaintiff, in excavating material from a mine shaft, under an alleged oral guarantee of payment based a specified quantity of material taken from the shaft. From a judgment of the Third District Court, Salt Lake County, A.H. Ellett, J., on a directed verdict for defendant, plaintiff appealed. The Supreme Court, McDONOUGH, J., held that there was no issue before the jury, in view of uncontroverted evidence that defendant had a license from plaintiff to use the machine before the date of a memorandum, on which plaintiff based his claim of a guarantee, and plaintiff's failure to present evidence of further consideration to support the parties' alleged agreement of such date.

Judgment affirmed.

1. TRIAL. Where there is no evidence on material part of plaintiff's claim, it is trial court's duty to direct verdict for defendant. 2. TRIAL. In deciding motion for directed verdict, court must consider evidence in light most favorable to party against whom motion is directed and resolve every controverted fact in his favor. 3. APPEAL AND ERROR. On appeal from judgment on directed verdict for defendant, inquiry must be directed toward whether reasonable minds could disagree on evidence presented, so as to provide a question for jury. 4. PATENTS. In action for balance due for defendant's use of mucker, invented and patented by plaintiff, in excavating material from mine shaft under plaintiff's direction and license, where evidence was uncontroverted that defendant had license to use machine before date of memorandum on which plaintiff based claim of guarantee of payment on basis of specified quantity of material taken from shaft and plaintiff presented no evidence of further consideration to support parties' alleged agreement of such date, question of such guarantee was one of law only and there was no issue for jury, so that trial court was under duty to direct verdict for defendant. 5. PATENTS. Where issues on trial of action for balance due for defendant's use of patented mucker under license from plaintiff for excavation of material from mine shaft were limited to terms of parties' contract and plaintiff did not claim that evidence offered by him as to construction of patented mucker used by defendant at another location, defendant's engineer's admission that such mucker was satisfactory, and replacement thereof by competitive machine at location involved in instant action, would have shown prior course of conduct or custom indicating intent to contract for payment of plaintiff on basis of guaranteed quantity of material excavated, trial court properly excluded such evidence. 6. APPEAL AND ERROR. Failure of order granting new trial to show grounds on which it was based, as required by civil procedure rule was not ground for reversal where record was corrected to show that verdict and judgment thereon were set aside and new trial ordered because of possible prejudice to defendant by errors in proceedings and particularly in wording of instructions and verdict. Rules of Civil Procedure, rule 59 (a, d). 7. APPEAL AND ERROR. Correction of record to show that jury's verdict for plaintiff and judgment thereon were set aside and new trial ordered because of possible prejudice to defendant by errors in proceedings and particularly in wording of instructions and verdict was proper under civil procedure rule, though not made until after transmission of record to Supreme Court on appeal from judgment on directed verdict for defendant in subsequent trial; rule being broad enough to cover any situation requiring remedial action to present complete and accurate record of proceedings below. Rules of Civil Procedure, rules 59(a, d), 75(h). 8. NEW TRIAL. The time prescribed by civil procedure rule that trial court may order new trial of its own initiative not later than ten days after entry of judgment cannot be enlarged. 9. NEW TRIAL. Where trial court instructed jury and had them retire, with both counsel's consent, before hearing defendant's motion for directed verdict, and on discovering, after jury retired, that reporter had left for day, continued hearing on motion, filing of judgment on verdict rendered by jury for plaintiff on following day was not entry of final judgment from which time to move for new trial would run, but there was no final judgment until after rulings on motions for directed verdict and judgment notwithstanding verdict, so that order granting new trial of court's own initiative on day of determination of such motions was within ten days' time stipulated in rule. Rules of Civil Procedure, rules 7(b) (3), 59(d). 10. APPEAL AND ERROR. In action for balance due plaintiff for defendant's use of plaintiff's patented machine under license from plaintiff, trial court's failure to instruct jury to deduct amount paid plaintiff by defendant from amount of verdict for plaintiff was cured by entry of judgment for amount guaranteed plaintiff by defendant, less amount so paid.

Jackson v. Colston, 116 Utah 295, 209 P.2d 566; Toomer's Estate v. Union Pac. R. Co., 121 Utah 37, 239 P.2d 163.

In re Bundy's Estate, 121 Utah 299, 241 P.2d 462.

See 69 C.J.S. Patents, sec. 272. New trial, time for filing of motion for. 39 Am.Jur., New Trial, sec. 185; 16 A.L.R., 1096.

Pugsley, Hayes Rampton, Salt Lake City, for appellant.

Edward G. Lindsley and Scott M. Matheson, Salt Lake City, for respondent.


This case is here on appeal from a directed verdict for the defendant. A motion for a new trial was granted in the first hearing of the case after the jury had returned a verdict for the plaintiff, on the grounds of probable prejudice to the defendant through the wording of the instructions and verdict.

Plaintiff-appellant is the inventor and patent holder of a machine known as the Boskovich Mucker, used in hard-rock mining operations. Defendant-respondent is a Utah corporation, which has constructed, under the direction and license of appellant, two of these machines, one for use at Bingham, Utah, and the second for use at Carlsbad, New Mexico. The dispute here involves the terms of the oral contract entered into by the parties with respect to the company's use of the appellant's rights in his invention in the second instance. Both parties agree that the company was to pay Mr. Boskovich 50¢ per cubic yard of material excavated by the machine at Carlsbad and further, that payment of $456.54 has been made on the amount actually taken from the shaft; however, appellant claims that the respondent guaranteed him payment on a total of 9,200 cubic yards.

The main question raised on appeal is whether there was sufficient evidence of the guarantee to go to the jury and thus, whether the trial erred in directing the verdict for the defendant.

It is fundamental that where there is no evidence upon a material part of the plaintiff's claim, it is the court's duty to direct a verdict. In deciding a motion for a directed verdict, the court must consider the evidence in the light most favorable to the party against whom the motion is 1-3 directed and must resolve every controverted fact in his favor. Jackson v. Colston, 116 Utah 295, 209 P.2d 566; Toomer's Estate v. Union Pac. R. Co., Utah 239 P.2d 163. The inquiry, then, must be directed toward whether reasonable minds could disagree in this case on the evidence presented so as to provide a question for the jury.

Appellant bases his claim of a guarantee upon a 4 memorandum which reads as follows:

"The Utah Construction Company, Salt Lake City District "Write it * * * Don't Say it "To Mike Boskovich "From George R. Putnam "Subject Quantities of excavation in International Shaft No. 3 "Date July 5, 1950 Shaft Excavation ..... 6500 cu. yd. Enlargements ......... 2700 cu. yd. ____________ Total .............. 9200 cu. yd." Appellant testifies that this was part of the inducement and terms of the contract. Admittedly, there are some slight contradictions in his testimony, but appellant is a man of foreign extraction and evidently has some difficulty in the use of the language. George R. Putnam, vice president and district manager of the respondent corporation, admits that there was a contract between his company and appellant, but testifies that the above memo was written to give Mike Boskovich an estimate of the material which would be taken from the Carlsbad mine at a time when operations had already begun and the contract was complete. This memo, it is to be noted, is unsigned. Respondent has introduced into evidence a letter signed by Mr. Boskovich, which reads:

"Midvale, Utah "June 21, 1950

"Geo. Putnam "Salt Lake City, Utah

"Dear Mr. Putnam:

"I understand that the Boskovich Muck Machine was built based on a 50¢ royalty which I agreed to accept.

"If the company pays my expense to go to Carlsbad and supervise the installing of the machine for 15 days, I'll be very glad to do so.

"On a 60¢ royalty basis, I would stand my own expenses.

"Yours truly, "/s/ M.N. Boskovich

"(P.S. Enclosed please find contract)"

The contract in blank which was enclosed also makes no mention of a guarantee. Appellant admits that the signature is his and attempts no explanation of the date of this letter, contending rather that his contract with the company became effective on July 5, the date of the memo.

Since it is apparent upon uncontroverted evidence that the respondent had license to use the machine before July 5 and since the appellant did not present evidence of further consideration to support the agreement of July 5, if the memo is so viewed for the benefit of appellant, the question was one of law only and there was no issue to go to the jury. The trial court was under a duty to direct the verdict for the defendant as plaintiff did not make out a claim upon which relief can be granted.

Appellant further contends that the court erred in excluding certain evidence. He offers the court no argument in his brief as to what particular exclusions he considers error nor what bearing the evidence if admitted would have on the findings of the case. After a search of the record, we find that 5 the evidence excluded pertained to the construction of the machine used at Bingham Canyon, which is not here in dispute; an admission by the construction company's engineer that the machine was satisfactory; the royalty paid on a competitive machine; and an offer of proof that the Boskovich Mucker was replaced at Carlsbad by a competitive machine. The issues of the trial were limited to the terms of the contract and appellant does not claim that this evidence would have shown a prior course of conduct or custom in this type of business which would have given rise to an intent to contract with a yardage guarantee. The trial court was correct in refusing to admit this evidence which would merely prolong the trial.

Appellant now objects that the granting of a new trial was improper, although he did not raise the issue until after the second trial and for purposes of this appeal. He objects that the court's order did not show the grounds upon which the order was based as required by Rule 59(a) and (d) of 6, 7 the Utah Rules of Civil Procedure; however, the record was corrected to show, as the court stated at the time of hearing, that the verdict and judgment were set aside and a new trial ordered because of possible prejudice to the defendant resulting from error in the proceedings and particularly in the wording of the instructions and verdict. The correction of the record was properly made, even though not made until after the record had been transmitted on appeal to this court, under the authority of Rule 75(h), which was purposely made broad enough by the Committee on the Rules to cover any situation requiring remedial action to present a complete and accurate record of the proceedings below. Dempsey v. Guaranty Trust Co. of New York, 7 Cir., 131 F.2d 103, certiorari denied, 318 U.S. 769, 63 S.Ct. 761, 87 L.Ed. 1139.

Appellant further objects that the motion for a new trial was not made within the 10 days prescribed by the 8, 9 Rules. Rule 59(d) states

"Not later than 10 days after entry of judgment the court of its own initiative may order a new trial * *"

and all interpretations under the Federal Rule 59(d) indicate that the time cannot be enlarged. Safeway Stores, Inc. v. Coe, 78 U.S.App.D.C. 19, 136 F.2d 771, 148 A.L.R. 782. Nachod U.S. Signal Co., Inc., v. Automatic Signal Corp., D.C., 26 F. Supp. 418. This is in accord with our own views. In re Bundy's Estate, Utah, 241 P.2d 462. The question then is whether the motion was made within ten days of the final judgment. On September 24, 1951, at the first hearing of this case, defendant moved the court for a directed verdict and the court, with the consent of both counsel, instructed the jury and had them retire before hearing the motion. It was discovered after the jury retired that the reporter had left for the day and thus the hearing on the motion was continued. A verdict was rendered in favor of the plaintiff and judgment on the verdict was filed, as a matter of course, the following day. To hold that this was an entry of final judgment from which the time for making a motion for a new trial would run would be to make a useless act of the hearing of the motions for directed verdict and judgment, notwithstanding the verdict on October 6; obviously, neither the court nor counsel who argued the motions contemplated a final judgment in that entry. Rule 7(b)(3) provides that when on the day fixed for the hearing of a motion, the judge before whom such motion is to be heard is unable to hear the parties, the matter shall stand continued until the further order of the court. Thus, there was no final judgment until after the rulings on the motions for a directed verdict and for a judgment notwithstanding the verdict. The court ordered the new trial of its own initiative on the day of the determination of the motions and well within the time stipulated in the Rules.

As to the grounds upon which the new trial was granted, we see no prejudice to the defendant in the wording of either the instructions or the verdict, which mentioned the lump sum payment of $4,600. If there was a guarantee of 9,200 yards at 50¢ per cubic yard, then the defendant was liable for 10 that amount and any other verdict for the plaintiff would have been inconsistent. The failure to instruct the jury to deduct the $456.54 already paid was cured by the judgment entered for $4,600 less that amount. However, the evidence on both trials was in all essentials the same, and the directed verdict on the second trial was proper and should have been granted in the first; hence, the judgment on the second trial will stand affirmed. Costs to the respondent.

WOLFE, C.J., and CROCKETT, HENRIOD and WADE, JJ., concur.


Summaries of

Boskovich v. Utah Const. Co.

Supreme Court of Utah
Aug 7, 1953
259 P.2d 885 (Utah 1953)
Case details for

Boskovich v. Utah Const. Co.

Case Details

Full title:BOSKOVICH v. UTAH CONST. CO

Court:Supreme Court of Utah

Date published: Aug 7, 1953

Citations

259 P.2d 885 (Utah 1953)
259 P.2d 885

Citing Cases

WILLARD M. MILNE INV. CO. v. COX

Kjar v. Brimley, supra.Finlayson v. Brady, 121 Utah 204, 240 P.2d 491 (1952); Boskovich v. Utah Constr. Co.,…

MFT Leasing v. Fillmore Products, Inc.

Hence, the Court's directed verdict was proper.Boskovich v. Utah Construction Co., 123 Utah 387, 259 P.2d 885…