From Casetext: Smarter Legal Research

Bilotto v. Webber

Appellate Division of the Supreme Court of New York, Second Department
Apr 15, 1991
172 A.D.2d 639 (N.Y. App. Div. 1991)

Opinion

April 15, 1991

Appeal from the judgment of the Supreme Court, Westchester County (Bowers, J.H.O.).


Ordered that the judgment is affirmed, with costs.

In June 1986 the defendant, a general contractor, entered into a contract with the plaintiffs to construct a single-family house on their property. The contract provided that there would be substantial completion of the construction by December 21, 1986, and that time was of the essence. The house was not completed by that date, and by letter dated March 17, 1987, the plaintiffs terminated the contract.

The trial court properly found that the plaintiffs were entitled to terminate the contract because of the defendant's breach (see, Zev v. Merman, 73 N.Y.2d 781; cf., Young v. Whitney, 111 A.D.2d 1013). By the completion date, there was only a partial foundation, partial roof, and no inside work done, such as the electrical wiring or the installation of plumbing fixtures. The defendant's contention that the delay was caused by the weather conditions and the existence of a "rock ledge" on the property is unavailing. There is no support in the record for the claimed adverse weather conditions, and the defendant admitted that he was aware of the "rock ledge" before the contract was executed.

In addition, there is no basis to disturb the trial court's determination, based on the testimony of the plaintiffs' expert (see, Epstein v. State of New York, 124 A.D.2d 544, 548), that the defendant was also in breach of the contract because of his defective workmanship. The plaintiffs' expert testified that the window openings were improperly sized; the structure was improperly reinforced, the support columns in the basement were improperly cut and placed, the I beams were improperly placed, steel support beams were improperly secured, and structural supports were improperly installed, causing the Building Department to issue a Stop Work Order. He also testified that headers were not installed, and "two-by-fours" were improperly used. In fact, the defendant admitted that the "two-by-fours" were inadequate.

Finally, the trial court's award of damages in this case was proper (see, Bellizzi v. Huntley Estates, 3 N.Y.2d 112; Annotation, Cost of Correction or Completion or Difference in Value, as Measure of Damages for Breach of Construction Contract, 76 ALR2d 805, 810). Sullivan, J.P., Lawrence, Eiber and Ritter, JJ., concur.


Summaries of

Bilotto v. Webber

Appellate Division of the Supreme Court of New York, Second Department
Apr 15, 1991
172 A.D.2d 639 (N.Y. App. Div. 1991)
Case details for

Bilotto v. Webber

Case Details

Full title:GERALD BILOTTO et al., Respondents, v. MICHAEL WEBBER, Appellant

Court:Appellate Division of the Supreme Court of New York, Second Department

Date published: Apr 15, 1991

Citations

172 A.D.2d 639 (N.Y. App. Div. 1991)
568 N.Y.S.2d 438

Citing Cases

Teramo Co. v. O'Brien-Sheipe Funeral Home

a contract depends upon the facts and circumstances of the particular case (see, Savasta v. 479 Newport…

Driscoll v. Mccarthy

There is simply no time frame language in the contract and, as discussed, none can be added by the Court. A…