From Casetext: Smarter Legal Research

Beys Gen. Constr. Corp. v. Hill Int'l, Inc.

Supreme Court, Appellate Division, First Department, New York.
Feb 2, 2012
92 A.D.3d 407 (N.Y. App. Div. 2012)

Opinion

2012-02-2

BEYS GENERAL CONSTRUCTION CORP., Plaintiff–Respondent, v. HILL INTERNATIONAL, INC., Defendant–Appellant.

LePatner & Associates, LLP, New York (Barry B. LePatner and Jeffrey W. Kleiner of counsel), for appellant. Milber Makris Plousadis & Seiden, LLP, Woodbury (Joseph J. Cooke of counsel), for respondent.


LePatner & Associates, LLP, New York (Barry B. LePatner and Jeffrey W. Kleiner of counsel), for appellant. Milber Makris Plousadis & Seiden, LLP, Woodbury (Joseph J. Cooke of counsel), for respondent.

GONZALEZ, P.J., SAXE, MOSKOWITZ, ACOSTA, FREEDMAN, JJ.

Judgment, Supreme Court, New York County (Charles Edward Ramos, J.), entered November 8, 2010, awarding plaintiff the principal amount of $271,602.71 plus interest, unanimously affirmed, with costs. Appeal from order, same court and Justice, entered June 11, 2010, which granted plaintiff's motion for partial summary judgment, unanimously dismissed, without costs, as subsumed in the appeal from the judgment.

Plaintiff-subcontractor made a prima facie showing of entitlement to judgment as a matter of law by submitting a Certificate of Substantial Completion, a Final Inspection Report, and the affidavit of its secretary stating that the claimed amounts were owed and that all remaining work had been completed in accordance with the terms and conditions of the parties' contracts.

In response, defendant-general contractor failed to raise a triable issue of fact ( see Alvarez v. Prospect Hosp., 68 N.Y.2d 320, 324, 508 N.Y.S.2d 923, 501 N.E.2d 572 [1986] ). In particular, the opposition papers failed to connect undated New York City Engineering Audit Office (EAO) item adjustments, setting forth a total adjustment of $82,537 sought to be deducted by defendant herein, to the specific payment requisitions under which plaintiff made its claims. In addition, defendant's engineer did not affirmatively state in his affidavit that those specific EAO item adjustments were still outstanding at the time plaintiff submitted the final requisitions. Moreover, the opposition papers failed to address why the Certificate of Substantial Completion and the Final Inspection Report, signed by both defendant and the City, were not dispositive.

We reject defendant's argument that plaintiff did not proffer adequate documentation in support of the payment requisitions. The alleged documentation requirements largely emanated from the prime contract between defendant and the City. Although the prime contract clauses were incorporated by reference into the construction subcontracts between plaintiff and defendant, plaintiff is not bound by the documentation requirements in the prime contract, as they do not relate to the “scope, quality, character, and manner of the work to be preformed by [plaintiff]” ( Bussanich v. 310 E. 55th St. Tenants, 282 A.D.2d 243, 244, 723 N.Y.S.2d 444 [2001] ).

We have reviewed defendant's remaining contentions and find them unavailing.


Summaries of

Beys Gen. Constr. Corp. v. Hill Int'l, Inc.

Supreme Court, Appellate Division, First Department, New York.
Feb 2, 2012
92 A.D.3d 407 (N.Y. App. Div. 2012)
Case details for

Beys Gen. Constr. Corp. v. Hill Int'l, Inc.

Case Details

Full title:BEYS GENERAL CONSTRUCTION CORP., Plaintiff–Respondent, v. HILL…

Court:Supreme Court, Appellate Division, First Department, New York.

Date published: Feb 2, 2012

Citations

92 A.D.3d 407 (N.Y. App. Div. 2012)
940 N.Y.S.2d 14
2012 N.Y. Slip Op. 710

Citing Cases

Zimmcor (1993) Inc. v. Permasteelisa North America Corp.

In the present matter, unlike Dart Mechanical Corp., Clause 7 of the Secondary Subcontract and Appendix B…