From Casetext: Smarter Legal Research

Betancur v. Lincoln Ctr. for the Performing Arts, Inc.

Supreme Court, Appellate Division, First Department, New York.
Dec 6, 2012
101 A.D.3d 429 (N.Y. App. Div. 2012)

Summary

In Betancur v Lincoln Ctr. for the Performing Arts, Inc., 101 AD3d 429, 430, the existence of "factual issues [with respect to] whether the temporary flooring contributed to plaintiff's accident" were sufficient to deny summary resolution of indemnification and contribution claims between defendants, but irrelevant to the question of liability pursuant to section 240[1]), as claimant's summary judgment motion was started notwithstanding the unresolved issue.

Summary of this case from Gravanis v. State

Opinion

2012-12-6

Celene BETANCUR, Plaintiff, v. LINCOLN CENTER FOR THE PERFORMING ARTS, INC., et al., Defendants–Appellants, JDP Mechanical, Inc., Defendant–Respondent. Lincoln Center for the Performing Arts, Inc., et al., Third–Party Plaintiffs–Appellants, v. Star–Delta Electric, LLC, Third–Party Defendant–Respondent. Lincoln Center for the Performing Arts, Inc., et al., Second Third–Party Plaintiffs–Appellants, v. JDP Mechanical, Inc., Second Third–Party Defendant–Respondent. [And a Third Third–Party Action].

Mauro Lilling Naparty LLP, Woodbury (Anthony F. DeStefano of counsel), for appellants. Ahmutty, Demers & McManus, Albertson (Glenn A. Kaminska of counsel), for JDP Mechanical, Inc., respondent.



Mauro Lilling Naparty LLP, Woodbury (Anthony F. DeStefano of counsel), for appellants. Ahmutty, Demers & McManus, Albertson (Glenn A. Kaminska of counsel), for JDP Mechanical, Inc., respondent.
Murphy & Higgins LLP, New Rochelle (Richard S. Kaye of counsel), for Star–Delta Electric, LLC, respondent.

McGaw, Alventosa & Zajac, Jericho (Joseph Horowitz of counsel), for Par Specialty Contracting Corp., respondent.

GONZALEZ, P.J., SWEENY, RICHTER, ROMÁN, CLARK, JJ.

Order, Supreme Court, New York County (Doris Ling–Cohan, J.), entered January 11, 2012, which, to the extent appealed from as limited by the briefs, granted plaintiff's motion for summary judgment as to liability under Labor Law § 240(1) as against defendants Lincoln Center for the Performing Arts, Inc. and Lincoln Center Development Project Inc. (together, Lincoln Center) and Integrated Building Controls, Inc. (IBC), granted defendant JDP Mechanical, Inc.'s (JDP) motion for summary judgment dismissing the complaint and all cross claims against it, denied Lincoln Center and the City's motion for summary judgment on their cross claims for contractual indemnification against JDP, and granted third-party defendant Star–Delta Electric, LLC's motion for summary judgment dismissing Lincoln Center and the City's cross claims for contractual indemnification against it, unanimously modified, on the law, to deny JDP's motion for summary judgment as to the common-law negligence cause of action and the cross claims for common-law and contractual indemnification and contribution against it, to reinstate JDP's third third-party action, and to grant Lincoln Center and the City's cross motion to the extent of awarding them conditional summary judgment on their contractual indemnification claim against JDP, and otherwise affirmed, without costs.

Plaintiff testified that the ladder she stood on inexplicably wobbled beneath her, causing her to fall and be injured, and there is no evidence in the record from which it could reasonably be inferred that she was the sole proximate cause of her injuries ( see Harrison v. V.R.H. Constr. Corp., 72 A.D.3d 547, 901 N.Y.S.2d 590 [1st Dept. 2010] ).

The record does not support a finding that JDP was a statutory agent for purposes of Labor Law § 240(1) ( see Blake v. Neighborhood Hous. Servs. of N.Y. City, 1 N.Y.3d 280, 292–293, 771 N.Y.S.2d 484, 803 N.E.2d 757 [2003] ). JDP's contract with Lincoln Center Development Project Inc. (Development) limited its responsibilities and potential liability to the work it was hired to perform and/or oversee, which did not include plaintiff's work; plaintiff's work was performed under a separate contract between Development and IBC. Nor is there evidence that JDP controlled the means and methods of plaintiff's work or that it assumed overall authority to correct unsafe work conditions at the project site. However, there is evidence that the temporary flooring on which the ladder rested was a “floating system” and therefore could move, and that JDP was responsible, in part, for selecting the materials for the flooring. Since factual issues exist whether the temporary flooring contributed to plaintiff's accident and whether JDP was negligent in selecting the materials for the flooring, the cause of action for common-law negligence and the cross claims for indemnification and contribution should not be dismissed as against JDP. There is also evidence that Development approved the installation of the flooring. Thus, Lincoln Center and the City are entitled to conditional summary judgment on their contractual indemnification claim against JDP.

Star–Delta is not contractually obligated to indemnify Lincoln Center and the City for claims arising out of any negligence on its part. While Star–Delta's subcontract with IBC incorporates the “General Conditions” of IBC's contract with Development, which include an indemnification provision, it does not contain an express agreement by Star–Delta to indemnify Lincoln Center and the City ( see Bussanich v. 310 E. 55th St. Tenants, 282 A.D.2d 243, 723 N.Y.S.2d 444 [1st Dept. 2001] ).


Summaries of

Betancur v. Lincoln Ctr. for the Performing Arts, Inc.

Supreme Court, Appellate Division, First Department, New York.
Dec 6, 2012
101 A.D.3d 429 (N.Y. App. Div. 2012)

In Betancur v Lincoln Ctr. for the Performing Arts, Inc., 101 AD3d 429, 430, the existence of "factual issues [with respect to] whether the temporary flooring contributed to plaintiff's accident" were sufficient to deny summary resolution of indemnification and contribution claims between defendants, but irrelevant to the question of liability pursuant to section 240[1]), as claimant's summary judgment motion was started notwithstanding the unresolved issue.

Summary of this case from Gravanis v. State
Case details for

Betancur v. Lincoln Ctr. for the Performing Arts, Inc.

Case Details

Full title:Celene BETANCUR, Plaintiff, v. LINCOLN CENTER FOR THE PERFORMING ARTS…

Court:Supreme Court, Appellate Division, First Department, New York.

Date published: Dec 6, 2012

Citations

101 A.D.3d 429 (N.Y. App. Div. 2012)
956 N.Y.S.2d 7
2012 N.Y. Slip Op. 8405

Citing Cases

Williams v. Graf

Aiello v. Burns Intl. Sec. Servs. Corp., 110 A.D.3d at 248; Gap, Inc. v. Fisher Dev., Inc., 27 A.D.3d at 212;…

Valle v. Port Auth. of N.Y.

However, given the above-mentioned issues of fact, the third-party claims for common-law indemnification and…