Opinion
2011-09-13
John P. Kingsley, P.C., Catskill, N.Y., for appellants-respondents.Edward H. Odesser, LLC, White Plains, N.Y. (Gary J. Langer of counsel), for respondents-appellants.
John P. Kingsley, P.C., Catskill, N.Y., for appellants-respondents.Edward H. Odesser, LLC, White Plains, N.Y. (Gary J. Langer of counsel), for respondents-appellants.
In an action, inter alia, to recover damages for breach of contract, the defendants appeal, on the ground of inadequacy, from a judgment of the Supreme Court, Dutchess County (Sproat, J.), dated June 23, 2009, which, upon a stipulation dated January 24, 2004, a stipulation dated January 19, 2006, a decision of the same court dated February 28, 2007, made after a nonjury trial on the issue of damages, a decision of the same court dated May 3, 2007, an order of the same court dated May 7, 2007, denying their motion pursuant to CPLR 4404(b) to set aside the decision dated February 28, 2007, and a decision of the same court dated November 21,
2007, is in favor of them and against the plaintiff on their counterclaim in the principal sums of only (a) $810,359.02, representing awards of $56,086 for repayment of capital investment, $250,000 for repayment of a 1994 loan, $210,000 for repayment of a separate loan, and $344,273.02 for repayment of another separate loan, (b) $289,355 for the value of excavation work performed by them, (c) $97,801.34 plus certain uncalculated prejudgment interest on that amount for reimbursement from a court-mandated, interest-bearing escrow fund, and (d) $150,000 for repayment of a 1993 promissory note, for a total sum of only $1,347,515.36 plus the uncalculated prejudgment interest on the award of $97,801.34, and awarded them only limited predecision interest on portions of the total sum; and the plaintiffs cross-appeal, as limited by their notice of cross appeal and brief, from so much of the same judgment as awarded the defendants the principal sums of $210,000, $344,273.02, $289,355, and $97,801. 34 plus certain uncalculated prejudgment interest on that sum.
ORDERED that the judgment is modified, on the law, (1) by deleting from the first decretal paragraph thereof the words “EIGHT HUNDRED TEN THOUSAND THREE HUNDRED FIFTY–NINE DOLLARS AND 02/100 ($810,359.02) without interest” and substituting therefor the words “SIX HUNDRED FIFTY THOUSAND THREE HUNDRED FIFTY–NINE DOLLARS AND 02/100 ($650,359.02) with prejudgment interest at the statutory rate of 9% per annum only from February 28, 2007, and TWO HUNDRED TEN THOUSAND and 00/100 ($210,000) with prejudgment interest at the contractual rate of 10% per annum from February 2, 2006,” (2) by deleting from the second decretal paragraph thereof the words “TWO HUNDRED SIXTY–THREE THOUSAND FIFTY DOLLARS AND 00/100 ($263,050.00) plus an additional ten percent with interest” and substituting therefor the words “TWO HUNDRED EIGHTY–NINE THOUSAND THREE HUNDRED FIFTY–FIVE DOLLARS AND 00/100 ($289,355) with prejudgment interest at the statutory rate of 9% per annum from February 2, 1998,” and (3) by deleting the third decretal paragraph thereof awarding the defendants $97,801.34 plus 4.89% of that sum, representing a certain portion of the interest accrued on a court-mandated, interest-bearing escrow account; as so modified, the judgment is affirmed insofar as appealed and cross-appealed from, without costs or disbursements, and the matter is remitted to the Supreme Court, Dutchess County, for calculation of the interest due in accordance herewith and the entry of an appropriate amended judgment thereafter.
On July 15, 1993, David Berry and Joseph Governale borrowed the principal sum of $150,000 from J & J Log & Lumber Corp. (hereinafter J & J) to purchase approximately 84 acres of vacant land in Ulster County (hereinafter the property). At that time, J & J was owned by James Williams and his son, Randolph Williams. The loan was secured by a mortgage on the property.
On April 1, 1994, Berry, Governale, James Williams, and Randolph Williams incorporated Willberry Corporation (hereinafter Willberry) for the purpose of developing an assisted-living facility on the property (hereinafter the Willberry project); they also executed a shareholders' agreement to govern the corporation (hereinafter the 1994 Agreement). Pursuant to the 1994 Agreement, Berry and Governale borrowed an additional $250,000 from James Williams and Randolph Williams, secured by a second mortgage on the property, and thereafter sold the property to Willberry, subject to the first and second mortgages. On March 12,
1998, James Williams and Berry amended the 1994 Agreement in certain respects by executing a document entitled “Modification of Distribution of Funds” (hereinafter the 1998 Modification Agreement).
In or about November 15, 2000, Berry, Governale, and Willberry commenced this action against Randolph Williams, individually and as a co-executor of the estate of James Williams, who had died on July 9, 1998, as well as against Irving Schwartz and Nancy Viola, as co-executors of the estate of James Williams. In essence, the plaintiffs contended that the defendants breached the 1994 Agreement, as amended by the 1998 Modification Agreement, by ceasing to contribute funds to develop the Willberry project.
On January 24, 2004, Randolph Williams and Berry entered into an oral stipulation of settlement that was placed on the record in open court, which, inter alia, provided that they would attempt to sell the property, which was Willberry's only asset, as quickly as possible, and then dissolve Willberry. On January 19, 2006, Randolph Williams and Berry entered into another oral stipulation of settlement that was placed on the record in open court, in which they agreed to, among other things, the actual sale of the property and to certain preliminary disbursements of the proceeds of the sale. On February 2, 2006, Willberry sold the property for the sum of $4.5 million. After the parties paid certain closing expenses, they distributed the sum of $1,410,043.08 to Randolph Williams, distributed the sum of $798,277.96 to Berry and Governale, and placed $2 million in an interest-bearing escrow account to await a final judicial determination on the disposition of the proceeds of the sale.
After protracted motion practice and five appeals, all of which were dismissed on various procedural grounds or for failure to prosecute, the defendants appeal from the judgment entered in the action, and the plaintiffs cross-appeal from portions of the judgment, which, among other things, awarded amounts that the defendants were entitled to receive from the proceeds of the sale. We modify.
Initially, CPLR 5019(a) permits this Court to cure any “mistake, defect or irregularity” in a judgment, including mathematical errors in calculation ( see Freedman v. City of New Rochelle, 274 A.D.2d 447, 448, 711 N.Y.S.2d 904). Here, the judgment recited that the Supreme Court had previously determined to award the defendants the principal sums of $56,086, $250,000, $210,000, and $344,273.02, and aggregated these awards in the first decretal paragraph, yet erroneously calculated the sum of these awards to be $810,359.02, rather than $860,359.02, which is the correct amount. Moreover, “[a] judgment ... must conform strictly to the court's decision. Where there is an inconsistency between a judgment ... and the decision upon which it is based, the decision controls” ( Curry v. Curry, 14 A.D.3d 646, 647, 789 N.Y.S.2d 307 [citations omitted] ). Here, in one of the posttrial decisions upon which the judgment was based, the Supreme Court recited, among other things, that the award of $210,000 was to be with interest from the date of the decision. The first decretal paragraph of the judgment, however, awarded the sum of $810,359.02—in which the award of $210,000 was subsumed—without interest. Accordingly, although we are ultimately required, under the circumstances of this case, to award different rates of interest over different periods of time in connection with the several components of the award of $860,359.02, we take as our starting point the ministerial correction of the first decretal paragraph of the judgment to reflect the decision of the Supreme Court to award the defendants
the sum of $860,359.02, with prejudgment interest at the statutory rate of 9% per annum on the entirety of that sum, only from February 28, 2007, the date of the decision ( see CPLR 5002).
That said, as a general rule, we do not consider an issue on a subsequent appeal which was raised or could have been raised on an earlier appeal which was dismissed for lack of prosecution, although the Court has the inherent jurisdiction to do so ( see Rubeo v. National Grange Mut. Ins. Co., 93 N.Y.2d 750, 697 N.Y.S.2d 866, 720 N.E.2d 86; Bray v. Cox, 38 N.Y.2d 350, 379 N.Y.S.2d 803, 342 N.E.2d 575). The issues the defendants raise could have been raised on the defendants' prior appeal from an order dated May 3, 2007, denying their motion pursuant to CPLR 4404(b) to set aside the decision dated February 28, 2007, which was dismissed by decision and order on motion of this Court dated March 4, 2008, for failure to prosecute in accordance with the rules of this Court. Nevertheless, under the circumstances of this case, we exercise our discretion to determine these issues on the instant appeal ( see Faricelli v. TSS Seedman's, 94 N.Y.2d 772, 774, 698 N.Y.S.2d 588, 720 N.E.2d 864; Rubeo v. National Grange Mut. Ins. Co., 93 N.Y.2d 750, 697 N.Y.S.2d 866, 720 N.E.2d 86; McMahan v. McMahan, 66 A.D.3d 969, 969, 888 N.Y.S.2d 133; cf. Utility Audit Group v. Apple Mac & R Corp., 59 A.D.3d 707, 708, 874 N.Y.S.2d 525).
As noted above, the Supreme Court erred in declining to include, in the judgment, interest in connection with the award of the principal sum of $860,359.02. Of that award, the sum of $650,359.02 should have accrued statutory interest at the rate of 9% per annum “from the date ... the decision was made to the date of entry of final judgment” (CPLR 5002). Accordingly, we modify the judgment to reflect the proper award of prejudgment interest on that sum. With respect to the remaining $210,000 subsumed in the award of $860,359.02, the Supreme Court also erred in declining to include, in the judgment, the proper prejudgment interest in connection with that award which, here, had been fixed pursuant to contract at a rate greater than the statutory rate. The sum of $210,000 reflected an amount loaned to the plaintiff David Berry by the defendants. Contrary to the plaintiffs' contention, the Supreme Court's determination of that principal sum “was supported by the evidence and should not be disturbed” ( Rockland Dev. Assoc. v. State of New York, 15 A.D.3d 381, 382, 790 N.Y.S.2d 169; see American Psych Sys. v. Options Ind. Practice Assn., 276 A.D.2d 654, 655, 715 N.Y.S.2d 856). Moreover, pursuant to the 1998 Modification Agreement, Berry was required to repay the loan, plus 10% interest, in the event that the property was sold. Consequently, the Supreme Court should have awarded the defendants prejudgment interest at the contractual rate of 10% per annum on the award of $210,000, from February 2, 2006, the date that the property was sold ( see Winter v. Brown, 85 A.D.3d 773, 924 N.Y.S.2d 555), and we modify the judgment accordingly.
The Supreme Court also erred in declining to award prejudgment interest in connection with the award of the principal sum of $289,355. That sum reflected the total amount owed by the plaintiffs pursuant to an agreement (hereinafter the cost-plus agreement), wherein the plaintiffs were provided with excavation services in exchange for payment of “the actual costs incurred ... plus ten (10%) percent.” Contrary to the plaintiffs' contention, the Supreme Court's determination of that principal sum “was supported by the evidence and should not be disturbed”
( Rockland Dev. Assoc. v. State of New York, 15 A.D.3d at 382, 790 N.Y.S.2d 169; see American Psych Sys. v. Options Ind. Practice Assn., 276 A.D.2d at 655, 715 N.Y.S.2d 856). However, the cost-plus agreement provided that payment was due in full upon completion of the work. Accordingly, the Supreme Court should have awarded the defendants interest at the statutory rate of 9% per annum from “the earliest ascertainable date the cause of action existed” (CPLR 5001[b]; see Tesser v. Allboro Equip. Co., 73 A.D.3d 1023, 1027–1028, 904 N.Y.S.2d 701) which, here, was February 2, 1998.
The provision in the judgment directing the plaintiffs to pay the defendants the total sum of $97,801.34 with certain prejudgment interest represented the amount to be paid to the defendants from a court-mandated, interest-bearing escrow fund, which held the remainder of the proceeds of the February 2, 2006, sale of the subject property. Since the calculation of this amount was based upon awards now modified by this decision and order, the third decretal paragraph of the judgment, awarding the defendants $97,801.34 plus certain prejudgment interest, must be deleted.
The parties' remaining contentions are without merit.
Accordingly, the matter must be remitted to the Supreme Court, Dutchess County, for calculation of the interest due on the awards in accordance herewith, and the entry of an appropriate amended judgment thereafter.