From Casetext: Smarter Legal Research

Bd. of Educ. of Palmyra-Macedon Cent. Sch. Dist. v. Flower City Glass Co.

Supreme Court, Appellate Division, Fourth Department, New York.
Apr 27, 2018
160 A.D.3d 1497 (N.Y. App. Div. 2018)

Opinion

1333 CA 17–00433

04-27-2018

BOARD OF EDUCATION OF PALMYRA–MACEDON CENTRAL SCHOOL DISTRICT, Petitioner–Respondent, v. FLOWER CITY GLASS CO., INC., Flower City Glass Associates, LLC, Flower City Glass Co. of New York, LLC, Flower City Glass, Respondents–Appellants, et al., Respondent. (Appeal No. 1.)

OSBORN, REED & BURKE, LLP, ROCHESTER (JEFFREY P. DIPALMA OF COUNSEL), FOR RESPONDENTS–APPELLANTS. COSTELLO, COONEY & FEARON, PLLC, SYRACUSE (NICOLE MARLOW–JONES OF COUNSEL), FOR PETITIONER–RESPONDENT.


OSBORN, REED & BURKE, LLP, ROCHESTER (JEFFREY P. DIPALMA OF COUNSEL), FOR RESPONDENTS–APPELLANTS.

COSTELLO, COONEY & FEARON, PLLC, SYRACUSE (NICOLE MARLOW–JONES OF COUNSEL), FOR PETITIONER–RESPONDENT.

PRESENT: SMITH, J.P., CENTRA, CARNI, CURRAN, AND TROUTMAN, JJ.

MEMORANDUM AND ORDER

Memorandum:

Petitioner-plaintiff, Board of Education of the Palmyra–Macedon Central School District (District), contracted with respondent-defendant Flower City Glass Co., Inc. (Flower City) to perform certain work on a school building. After the work had been completed, the District noticed that the wall panels installed pursuant to the contract were defective. Thus, the District served Flower City and respondents-defendants Flower City Glass Associates, LLC, Flower City Glass Co. of New York, LLC, and Flower City Glass (collectively, Flower City defendants) with a demand for arbitration. When the Flower City defendants refused to arbitrate, the District filed a summons and complaint on September 11, 2015 (complaint) against, inter alia, the Flower City defendants. The District also filed an application seeking to compel the Flower City defendants to arbitrate or, in the alternative, seeking a determination that the complaint was timely pursuant to CPLR 204(b). In appeal No. 1, the Flower City defendants appeal from an order insofar as it granted the District's alternative relief. In determining that the complaint was timely, Supreme Court concluded that the District's demand for arbitration was timely and was not made in bad faith, and thus that the arbitration-related toll of CPLR 204(b) applied.

In appeal No. 2, the Flower City defendants appeal from an order insofar as it denied their motion to dismiss with respect to the first cause of action, for breach of contract, against them.

With respect to appeal No. 1, we note that the Flower City defendants admitted service of the District's application to compel arbitration and the supporting papers. The Flower City defendants also did not object to the court's hearing and deciding the District's application, and they opposed the application on the merits. We therefore reject their contention that, because the complaint was not served within the 120 days provided for in CPLR 306–b, the court lacked jurisdiction to adjudicate the District's application.

We agree with the Flower City defendants, however, that the court's determinations that the demand for arbitration was not made in bad faith, and that the action was timely commenced pursuant to CPLR 204(b), were improper advisory opinions (see Simon v. Nortrax N.E., LLC, 44 A.D.3d 1027, 1027, 845 N.Y.S.2d 85 [2d Dept. 2007] ). We therefore reverse the order in appeal No. 1 insofar as appealed from and deny the application in its entirety. With respect to appeal No. 2, we conclude that the court properly denied that part of the Flower City defendants' motion to dismiss with respect to the first cause of action, and we therefore affirm. CPLR 204(b) provides that "[w]here it shall have been determined that a party is not obligated to submit a claim to arbitration, the time which elapsed between the demand for arbitration and the final determination that there is no obligation to arbitrate is not a part of the time within which an action upon such claim must be commenced." The Flower City defendants contend that the demand for arbitration, served on September 30, 2014, was untimely because the claim for defects in material or labor accrued upon the completion of the physical work, which they unilaterally determined to be August 19, 2008. Thus, according to the Flower City defendants, the demand for arbitration was filed beyond the six-year statute of limitations (see CPLR 213[2] ; State of New York v. Lundin, 60 N.Y.2d 987, 989, 471 N.Y.S.2d 261, 459 N.E.2d 486 [1983] ). We reject that contention. The parties do not dispute that a cause of action for defective construction and design accrues upon actual physical completion of the work (see City Sch. Dist. of City of Newburgh v. Stubbins & Assoc., 85 N.Y.2d 535, 538, 626 N.Y.S.2d 741, 650 N.E.2d 399 [1995] ; Sears, Roebuck & Co. v. Enco Assoc., 43 N.Y.2d 389, 394, 401 N.Y.S.2d 767, 372 N.E.2d 555 [1977] ). Actual physical completion of the work is "when the contract in question was substantially completed" ( Town of Poughkeepsie v. Espie, 41 A.D.3d 701, 706, 840 N.Y.S.2d 600 [2d Dept. 2007], lv dismissed 9 N.Y.3d 1003, 849 N.Y.S.2d 30, 879 N.E.2d 170 [2007], lv denied 15 N.Y.3d 715, 2010 WL 5071209 [2010] ; see New York Cent. Mut. Fire Ins. Co. v. Glider Oil Co., Inc., 90 A.D.3d 1638, 1639, 936 N.Y.S.2d 815 [4th Dept. 2011] ).

Additionally, "parties may ... provide in their contract when the period of limitations will commence, and such a provision will govern in the absence of duress, fraud or misrepresentation" ( Matter of Oriskany Cent. Sch. Dist. [Booth Architects], 206 A.D.2d 896, 897, 615 N.Y.S.2d 160 [4th Dept. 1994], affd 85 N.Y.2d 995, 630 N.Y.S.2d 960, 654 N.E.2d 1208 [1995] ). Here, the parties agreed in their contract that the determination of when the work was substantially completed would be determined by the project architect, who in this case issued a "Certificate of Substantial Completion" on October 1, 2008. Thus, the unilateral determination of the Flower City defendants of when the "physical work" was complete is irrelevant.

Furthermore, the contract provided that, "[a]s to acts or failures to act occurring prior to the relevant date of Substantial Completion, ... any alleged cause of action shall be deemed to have accrued in any and all events not later than such date of Substantial Completion." Thus, pursuant to the contract, the parties agreed that substantial completion as determined by the project architect was the accrual event. We thus conclude that the breach of contract cause of action accrued on the date of substantial completion, which the architect determined to be October 1, 2008 (see Putrelo Constr. Co. v. Town of Marcy, 105 A.D.3d 1406, 1407, 964 N.Y.S.2d 812 [4th Dept. 2013] ).

We also reject the contention of the Flower City defendants that they met their burden of proof on their motion by establishing that the District made the demand for arbitration in bad faith (see Joseph Francese, Inc. v. Enlarged City Sch. Dist. of Troy, 95 N.Y.2d 59, 63, 710 N.Y.S.2d 315, 731 N.E.2d 1123 [2000] ). We therefore conclude that the CPLR 204(b) toll applied from the time the demand for arbitration was served, on September 30, 2014, until the final determination of nonarbitrability by the court on June 5, 2016. In addition, for the same reasons that the claim for arbitration did not accrue until the architect certified "Substantial Completion" of the work on October 1, 2008, we conclude that the breach of contract cause of action did not accrue until October 1, 2008. Applying the CPLR 204(b) toll, we further conclude that the District timely commenced the breach of contract cause of action in appeal No. 2 on September 11, 2015.

It is hereby ORDERED that the order insofar as appealed from is unanimously reversed on the law without costs, and the application is denied in its entirety.


Summaries of

Bd. of Educ. of Palmyra-Macedon Cent. Sch. Dist. v. Flower City Glass Co.

Supreme Court, Appellate Division, Fourth Department, New York.
Apr 27, 2018
160 A.D.3d 1497 (N.Y. App. Div. 2018)
Case details for

Bd. of Educ. of Palmyra-Macedon Cent. Sch. Dist. v. Flower City Glass Co.

Case Details

Full title:BOARD OF EDUCATION OF PALMYRA–MACEDON CENTRAL SCHOOL DISTRICT…

Court:Supreme Court, Appellate Division, Fourth Department, New York.

Date published: Apr 27, 2018

Citations

160 A.D.3d 1497 (N.Y. App. Div. 2018)
160 A.D.3d 1497
2018 N.Y. Slip Op. 3056

Citing Cases

U.S. Bank v. McCaffery

Interest Research Group v. Carey, 42 N.Y.2d 527, 531, 399 N.Y.S.2d 621, 369 N.E.2d 1155 ). Here, that branch…

Dienst v. Paik

They rely on an Appellate Division, Fourth Division decision wherein the Appellate Court held that the…