Aydin Corp. v. United States

8 Citing cases

  1. Bromley Contracting Co., v. United States

    794 F.2d 669 (Fed. Cir. 1986)   Cited 4 times
    Asking whether contracting officer had constructive knowledge of error in bid due to disparity between contractor's bid and other responsive bid

    The contractor must prove that the error is of the type that may be compensable, and that the contracting officer knew or should have known of the mistake at the time the bid was accepted. Aydin Corp. v. United States, 229 Ct.Cl. 309, 669 F.2d 681, 686 (1982); Wender Presses, Inc. v. United States, 170 Ct.Cl. 483, 343 F.2d 961, 962 (1965).Ruggiero v. United States, 190 Ct.Cl. 327, 420 F.2d 709, 713 (1970).

  2. Conner Brothers Construction Company v. U.S.

    No. 99-735 C (Fed. Cl. Jun. 10, 2005)   Cited 13 times
    Stating that "detailed measurements, tolerances, materials, and elaborate instructions as to how to perform the contract are of a design nature"

    Ruggiero, 420 F.2d at 713. In Aydin Corp. v. United States, 669 F.2d 681, 685 (Ct.Cl. 1982), the Court of Claims found that plaintiff's mistake in its estimate was nothing more than plaintiff underestimating the cost of materials, and hence, its bid. In that case, plaintiff did not show that its estimate was a clear cut clerical or arithmetical error, nor was there a claim of misreading specifications.

  3. Sulzer Bingham Pump v. Lockheed Missiles

    947 F.2d 1362 (9th Cir. 1991)   Cited 3 times

    It is apparently well settled government contract law that reformation, based upon a mistake in bidding, is available to correct only "clear cut clerical or arithmetical error, or misreading of specifications." Aydin Corp. v. United States, 229 Ct.Cl. 309, 314, 669 F.2d 681, 685 (1982) (quoting Ruggiero v. United States, 190 Ct.Cl. 327, 335, 420 F.2d 709, 713 (1970)). According to the district court's findings, errors in judgment predominated in this case.

  4. Giesler v. U.S.

    232 F.3d 864 (Fed. Cir. 2000)   Cited 22 times
    In Giesler, the Federal Circuit found that the contractor there failed to read the at-issue specification, and that it manifested an error in business judgment as a result.

    mistakes uniformly evaluates the duty only in instances where the alleged error was contained in a contractor's original bid, not in other subsequently submitted papers. See McClure Elec. Constructors, Inc. v. Dalton, 132 F.3d 709, 710 (Fed. Cir. 1997) (determining whether contracting officer discharged her duty to inform contractor of disparities between government estimate and contractor's estimate); Liebherr, 810 F.2d at 1155 (noting that the Navy immediately noted the wide disparity between contractor's bid and the range of the other responsive proposals); Bromley Contracting Co. v. United States, 794 F.2d 669, 671 (Fed. Cir. 1986) (asking whether contracting officer had constructive knowledge of error in bid due to disparity between contractor's bid and other responsive bid); Hamilton, 711 F.2d at 1044 (asking whether government buyer adequately informed contractor of discrepancy between government estimate of required manhours and manhours allocated to job in contractor's bid); Aydin Corp. v. United States, 229 Ct.Cl. 309, 669 F.2d 681, 683 (1982) (determining whether contracting officer had constructive knowledge of clerical oversights in bid); Ruggiero v. United States, 190 Ct.Cl. 327, 420 F.2d 709, 713 (1970) (inquiring whether contracting officer had constructive knowledge of improper designation in bid); Chernick v. United States, 178 Ct.Cl. 498, 372 F.2d 492, 495 (1967) (determining whether contracting officer had constructive knowledge of arithmetical mistake in bid); Wender Presses, Inc. v. United States, 170 Ct.Cl. 483, 343 F.2d 961, 962 (1965) (asking whether contracting officer had constructive knowledge of mistake in bid due to spread in submitted bids). We can discern no support through these cases that the government's duty to examine bids for mistakes also requires the government to examine the correctness of all of a contractor's subsequent filings.

  5. Edward E. Gillen Co. v. City of Lake Forest

    3 F.3d 192 (7th Cir. 1993)   Cited 66 times
    In Edward E. Gillen, the district court concluded that a construction company had conceded that all of its damages were delay damages by failing to clearly argue otherwise in its briefs.

    The very authorities on which Gillen relies emphasize that the error must be arithmetical, clerical, or a misreading of the contract specifications, as opposed to a mistake in judgment. Ruggiero, 420 F.2d at 713; see also C L Constr. Co., 6 Cl.Ct. at 801 n. 2; BCM Corp., 2 Cl.Ct. at 610; Aydin Corp. v. United States, 669 F.2d 681, 685, 229 Ct.Cl. 309 (1982). Gillen's mistaken assumption that Valders would be able to supply conforming stone was not this kind of scrivener's error. It cannot therefore be redressed through equitable reformation of the contract, even assuming that Lake Forest was aware of the mistake.

  6. Liebherr Crane Corp. v. United States

    810 F.2d 1153 (Fed. Cir. 1987)   Cited 16 times
    Holding that illegal action by the government in violation of a statute or regulation may support allegations of duress

    It is well established that an erroneous bid based, like this one, upon a mistake in judgment does not entitle the contractor to reformation of its contract. Hamilton, 711 F.2d at 1048; see also Aydin Corp. v. United States, 669 F.2d 681, 685, 229 Ct.Cl. 309, (1982); American Ship Building Co. v. United States, 654 F.2d 75, 80, 228 Ct.Cl. 220 (1981); National Line Co. v. United States, 607 F.2d 978, 984, 221 Ct.Cl. 673 (1979). On that basis we refuse to indulge Liebherr's attempt to take advantage of its own gross neglect and choice in failing properly to examine and follow the specifications.

  7. United States v. Hamilton Enterprises, Inc.

    711 F.2d 1038 (Fed. Cir. 1983)   Cited 13 times
    Finding error not of compensable type in mistake-in-bid case in absence of work papers showing the nature of mistake or what the bid would have been were it not for mistake

    A contract will not be reformed because of a unilateral mistake in a bid unless the contractor establishes that the error resulted from a "clear cut clerical or arithmetical error, or a misreading of the specifications." Aydin Corp. v. United States, 669 F.2d 681 (Ct.Cl. 1982); Ruggiero v. United States, 420 F.2d 709 (Ct.Cl. 1970). In such cases, the degree of proof demanded for reformation is higher than where rescission is requested.

  8. Hallwood Plaza, Inc. v. U.S.

    No. 06-589C (Fed. Cl. Dec. 5, 2008)   Cited 1 times

    Under the doctrine of unilateral mistake, "a contractor may obtain a remedy from the Government for a mistaken bid . . . only if the contracting officer knew or should have known of the contractor's unilateral mistake at the time the bid was accepted." Bromley Contracting Co. v. United States, 794 F.2d 669, 671-72 (Fed. Cir. 1986) (citing Aydin Corp. v. United States, 669 F.2d 681, 686 (Ct.Cl. 1982); Wender Presses, Inc. v. United States, 343 F.2d 961, 962-63 (Ct.Cl. 1965)). To succeed, plaintiff must satisfy a two-part test.