From Casetext: Smarter Legal Research

Avon Electrical Supplies, Inc. v. C.K. Electric, Inc.

Appellate Division of the Supreme Court of New York, Second Department
Oct 1, 2002
297 A.D.2d 768 (N.Y. App. Div. 2002)

Opinion

2001-04940

Argued May 16, 2002

October 1, 2002

In two related actions to foreclose mechanics' liens, Raimondo Sons Construction Co., Inc., Charles Raimondo, and W.K.T. Associates, Inc., defendants in Action Nos. 1 and 2, and RLI Insurance Company, a defendant in Action No. 2, appeal from so much of an order of the Supreme Court, Nassau County (Davis, J.), dated May 9, 2001, as denied those branches of their motion which were to dismiss both complaints insofar as asserted against them, and granted the motion of Schwing Electrical Supply Corp., the plaintiff in Action No. 2, for leave to amend its complaint to assert a cause of action to recover damages for breach of fiduciary duty.

Peckar Abramson, P.C., New York, N.Y. (Lynn D. Shavelson of counsel), for appellants in Action Nos. 1 and 2.

Goldberg, Weprin Ustin, LLP, New York, N.Y. (Elizabeth Smith of counsel), for respondent in Action No. 1.

Robert Robert, LLP, Melville, N.Y. (Clifford S. Robert of counsel), for respondent in Action No. 2.

Before: FRED T. SANTUCCI, J.P., NANCY E. SMITH, WILLIAM D. FRIEDMANN, SANDRA L. TOWNES, JJ.


ORDERED that the order is reversed insofar as appealed from, on the law, with one bill of costs, those branches of the appellants' motion which were to dismiss the complaints insofar as asserted against them are granted, the motion of Schwing Electrical Supply Corp. is denied as academic, the complaints insofar as asserted against the appellants are dismissed, and the action against the remaining defendant in Action No. 1 is severed.

WKT Associates, Inc. (hereinafter WKT), is a property owner which undertook to build an "Edward's Super Foodstore" on its property in New Hyde Park. To perform the construction, WKT engaged general contractor C. Raimondo Sons Construction Co., Inc. (hereinafter Raimondo), a defendant in Action Nos. 1 and 2. Raimondo, in turn, subcontracted with JTC Electric Service (hereinafter JTC). JTC purchased electrical materials from Avon Electrical Supplies (hereinafter Avon), the plaintiff in Action No. 1, and Schwing Electrical Supply Corp. (hereinafter Schwing), the plaintiff in Action No. 2, for which JTC did not pay.

Under its contract with WKT, Raimondo was obligated to have the foodstore ready to open on June 3, 1998, or be liable for liquidated damages. Notwithstanding that it was behind schedule and that Raimondo had warned it to complete the electrical installation by May 22, 1998, JTC cut its staff of electricians on the site from 14 to two on or about May 18, 1998. As the contract between Raimondo and JTC authorized, Raimondo discharged JTC and hired BG Electrical Contractors of New York (hereinafter BG) to complete the work. In June 1998 a municipal electrical inspection cited the supermarket for numerous deficiencies in its electrical installations. On June 18, 1998, Raimondo's own electrical consultant verified that the entire electrical job had been shoddily performed and would essentially have to be redone.

At the time of JTC's discharge on May 21, 1998, Raimondo had paid it $771,751.04 out of a total contract price of $894,017.45. This left Raimondo with a fund of only $122,266.41 to repair and complete JTC's work. By June 2, 1998, Raimondo had paid BG $388,740.67 in electrical repair and completion costs, and by the conclusion of the job in September 1998, Raimondo had paid BG a total of $618,700.67. JTC has defaulted in the underlying litigation, and Avon and Schwing, which filed their mechanics' liens on August 11, 1998, and June 2, 1998, respectively, are now seeking payment from Raimondo and WKT under Lien Law article 3-A.

Under the facts of this case, Avon and Schwing lack standing to bring these actions because they had no contractual relationship with either the property owner or the general contractor and, as such, are not beneficiaries of WKT's or Raimondo's Lien Law trust (see Equitable Life Assur. Socy. of U.S. v. Nico Constr. Co., 235 A.D.2d 222; Pile Found. Constr. Co. v. Berger, Lehman Assocs., 253 A.D.2d 484; Matter of ABJEN Props. v. Crystal Run Sand Gravel, 168 A.D.2d 783; Lien Law § 71,[3],[4]). In any event, by the time the plaintiffs filed their mechanics' liens, Raimondo's Lien Law trust was exhausted, because it had spent more to repair and complete JTL's work than remained unpaid on the underlying contract (see Van Cleif v. Van Vechten, 130 N.Y. 571; Philan Dept. of Borden Co. v. Foster-Lipkins Corp., 39 A.D.2d 633, affd 33 N.Y.2d 709; Lien Law §§ 4; 70-77), and, as such, nothing remained to satisfy the subcontractor's outstanding claims (see Lien Law § 71; 72 [1]; cf. Canron Corp. v. City of New York, 89 N.Y.2d 147).

SANTUCCI, J.P., SMITH, FRIEDMANN and TOWNES, JJ., concur.


Summaries of

Avon Electrical Supplies, Inc. v. C.K. Electric, Inc.

Appellate Division of the Supreme Court of New York, Second Department
Oct 1, 2002
297 A.D.2d 768 (N.Y. App. Div. 2002)
Case details for

Avon Electrical Supplies, Inc. v. C.K. Electric, Inc.

Case Details

Full title:AVON ELECTRICAL SUPPLIES, INC., etc., respondent, v. C.K. ELECTRIC, INC.…

Court:Appellate Division of the Supreme Court of New York, Second Department

Date published: Oct 1, 2002

Citations

297 A.D.2d 768 (N.Y. App. Div. 2002)
747 N.Y.S.2d 575

Citing Cases

Access Plumbing Corp. v. 1184 Brighton Dev.

As to plaintiff's diversion of trust claims pursuant to Lien Law article 3-A, Lien Law § 71 (3) (a) defines…

World-Wide Plumbing Supply Inc. v. Copper Servs.

Citing earlier authority the court held that without either a contract or a mechanic's lien "merely supplying…