Opinion
2:23-cv-01737-BJR
12-07-2023
OGLETREE, DEAKINS, NASH, SMOAK & STEWART, P.C. By: Adam T. Pankratz Adam T. Pankratz WSBA # 50951 OGLETREE, DEAKINS, NASH, SMOAK & STEWART, P.C. Mathew A. Parker, OSBA #0093231 (appearing pro hac vice) The KeyBank Building Attorneys for Defendant Washington Fine Wine & Spirits, LLC EMERY | REDDY PLLC By: PatrickB. Reddy Timothy W. Emery, WSBA #34078 Patrick B. Reddy, WSBA #34092 Paul Cipriani Jr., WSBA #59991 Attorneys for Plaintiff Jacob Atkinson
OGLETREE, DEAKINS, NASH, SMOAK & STEWART, P.C.
By: Adam T. Pankratz
Adam T. Pankratz WSBA # 50951
OGLETREE, DEAKINS, NASH, SMOAK & STEWART, P.C.
Mathew A. Parker, OSBA #0093231
(appearing pro hac vice)
The KeyBank Building
Attorneys for Defendant Washington Fine Wine & Spirits, LLC
EMERY | REDDY PLLC
By: PatrickB. Reddy
Timothy W. Emery, WSBA #34078
Patrick B. Reddy, WSBA #34092
Paul Cipriani Jr., WSBA #59991
Attorneys for Plaintiff Jacob Atkinson
ORDER GRANTING JOINT STIPULATED MOTION TO SET BRIEFING SCHEDULE
BARBARA J. ROTHSTEIN UNITED STATES DISTRICT JUDGE
Plaintiff Jacob Atkinson and Defendant Washington Fine Wine & Spirits, LLC have filed their Joint Stipulated Motion to Set Briefing Schedule related to Defendant Washington Fine Wine & Spirits, LLC's Combined Motion to Dismiss Pursuant to FRCP Rule 12(b)(6) and Motion to Strike Pursuant to FRCP Rule 12(f) (“Combined Motions to Dismiss and Strike”) [Dkt. 8].
IT IS HEREBY ORDERED that the briefing schedule related to Defendant Washington Fine Wine & Spirits, LLC's Combined Motion to Dismiss and to Strike is as follows:
Event | Original Deadline | Extended Deadline |
Plaintiff's Response | 12/11/2023 | 01/19/2024 |
Defendant's Reply | 12/26/2023 | 02/02/2024 |
IT IS HEREBY FURTHER ORDERED that the early case deadlines, including the Fed.R.Civ.P. 26(f) Conference, Initial Disclosures, and the submission of the Joint Status Report be set as follows:
Event | Original Deadline | Extended Deadline |
FRCP 26(f) Conference | 12/19/2023 | 01/26/2024 |
Initial Disclosures Pursuant to FRCP 26(a)(1) | 12/26/2023 | 02/02/2024 |
Combined Joint Status Report and Discovery Plan as Required by FRCP 26(f) and Local Civil Rule 26(f) | 01/02/2024 | 02/09/2024 |