Opinion
Case No. 3:12-cv-01484 JST
05-01-2013
ARIBA, INC., Plaintiff/Counter-defendant, v. COUPA SOFTWARE INC., Defendant/Counterclaimant.
Robert T. Haslam Amy K. Van Zant Hyun S. Byun COVINGTON & BURLING LLP Robert D. Fram Christine Saunders Haskett Matthew D. Kellogg Tess A. Hamilton COVINGTON & BURLING LLP Attorneys for Plaintiff/Counter-defendant ARIBA, INC. Kelly C. Hunsaker Enrique D. Duarte FISH & RICHARDSON P.C. Attorneys for Defendant/Counterclaimant COUPA SOFTWARE INC.
Robert T. Haslam
Amy K. Van Zant
Hyun S. Byun
COVINGTON & BURLING LLP
Robert D. Fram
Christine Saunders Haskett
Matthew D. Kellogg
Tess A. Hamilton
COVINGTON & BURLING LLP
Attorneys for Plaintiff/Counter-defendant
ARIBA, INC.
Kelly C. Hunsaker
Enrique D. Duarte
FISH & RICHARDSON P.C.
Attorneys for Defendant/Counterclaimant
COUPA SOFTWARE INC.
[PROPOSED] STIPULATED CASE
MANAGEMENT ORDER
In light of the Court's April 9, 2013 Scheduling Order (Dkt. No. 34), Plaintiff/Counter-defendant Ariba, Inc. ("Ariba") and Defendant/Counterclaimant Coupa Software Inc. ("Coupa") hereby stipulate to the following claim construction schedule for this case:
+-----------------------------------------------------------------------------+ ¦Event ¦Date ¦ +-------------------------------------------------------------+---------------¦ ¦Joint Claim Construction Statement (Patent L.R. 4-3) (45 days¦Tuesday, May ¦ ¦before Opening Claim Construction Brief) ¦28, 2013 ¦ +-------------------------------------------------------------+---------------¦ ¦Last Day for Claim Construction Discovery (Patent L.R. 4-4) ¦Thursday, June ¦ ¦(30 days after Joint Claim Construction Statement) ¦27, 2013 ¦ +-------------------------------------------------------------+---------------¦ ¦Ariba's Opening Claim Construction Brief (Patent L.R. 4-5(a))¦Friday, July ¦ ¦(per April 9, 2013 Scheduling Order) ¦12, 2013 ¦ +-------------------------------------------------------------+---------------¦ ¦Coupa's Claim Construction Opposition Brief (Patent L.R. 4-5 ¦Friday, July ¦ ¦(b)) (14 days after Opening Brief) ¦26, 2013 ¦ +-------------------------------------------------------------+---------------¦ ¦Ariba's Claim Construction Reply Brief (Patent L.R. 4-5(c)) ¦ ¦ ¦(7 days after Opposition ¦Friday, August ¦ ¦ ¦2, 2013 ¦ ¦Brief) ¦ ¦ +-------------------------------------------------------------+---------------¦ ¦Technology Tutorial (per April 9, 2013 Scheduling Order) ¦Tuesday, August¦ ¦ ¦20, 2103 ¦ +-------------------------------------------------------------+---------------¦ ¦Claim Construction Hearing (per April 9, 2013 Scheduling ¦Tuesday, ¦ ¦Order) ¦September 3, ¦ ¦ ¦2013 ¦ +-----------------------------------------------------------------------------+
IT IS SO STIPULATED.
COVINGTON & BURLING LLP By: _______________
Amy K. Van Zant
Attorneys for Plaintiff/Counter-defendant
ARIBA, INC.
FISH & RICHARDSON PC. By: _______________
Enrique D. Duarte
Attorneys for Defendant/Counterclaimant
COUPA SOFTWARE INC.
IT IS SO ORDERED.
______________________
The Honorable Jon S. Tigar
United States District Judge