From Casetext: Smarter Legal Research

Alpha Interiors, Inc. v. Tulger Constr. Corp.

Supreme Court, Appellate Division, Second Department, New York.
Dec 5, 2012
101 A.D.3d 660 (N.Y. App. Div. 2012)

Summary

describing the scope of the public policy doctrine

Summary of this case from BAT, LLC v. TD Bank

Opinion

2012-12-5

ALPHA INTERIORS, INC., respondent, v. TULGER CONSTRUCTION CORPORATION, appellant.

Dunnington, Batholow & Miller, LLP, New York, N.Y. (Carol A. Sigmond and Eva Adaszko of counsel), for appellant. Wasserman Grubin & Rogers, LLP, New York, N.Y. (Michael T. Rogers and Douglas J. Lutz of counsel), for respondent.



Dunnington, Batholow & Miller, LLP, New York, N.Y. (Carol A. Sigmond and Eva Adaszko of counsel), for appellant. Wasserman Grubin & Rogers, LLP, New York, N.Y. (Michael T. Rogers and Douglas J. Lutz of counsel), for respondent.
REINALDO E. RIVERA, J.P., RUTH C. BALKIN, JOHN M. LEVENTHAL, and CHERYL E. CHAMBERS, JJ.

In an action to recover damages for breach of contract and on an account stated, the defendant appeals from so much of an order of the Supreme Court, Queens County (Kitzes, J.), dated April 12, 2011, as denied those branches of its motion which were for summary judgment dismissing the complaint and to impose sanctions pursuant to 22 NYCRR 130–1.1.

ORDERED that the order is modified, on the law, by deleting the provision thereof denying that branch of the defendant's motion which was for summary judgment dismissing the complaint, and substituting therefor a provision granting that branch of the motion; as so modified, the order is affirmed insofar as appealed from, with costs to the defendant.

The defendant, Tulger Construction Corporation (hereinafter Tulger), was the general contractor on a construction project for additions and alterations to a golf activities center in Lake Success. The plaintiff, Alpha Interiors, Inc. (hereinafter Alpha), was a subcontractor on the project. The subcontract between Tulger and Alpha provided, inter alia, that Alpha must “comply with all laws, ordinances, rules, regulations and orders of any public authority bearing on the performance of the Work under the Subcontract.” This provision required, among other things, that Alpha comply with Labor Law § 220, which requires payment of “the prevailing rate of wage” and “supplements” to workers on public works contracts. “Supplements” is defined as “all remuneration for employment paid in any medium other than cash, or reimbursement for expenses, or any payments which are not ‘wages' within the meaning of the law, including, but not limited to, health, welfare, non-occupational disability, retirement, vacation benefits, holiday pay[,] life insurance, and apprenticeship training” (Labor Law § 220[5][b] ). Over the course of the construction project, multiple change orders were issued. After the work was completed, Alpha commenced this action to recover damages for breach of contract and on an account stated, alleging that Tulger had failed to pay money owed under the subcontract. Eventually, Tulger moved, inter alia, for summary judgment dismissing the complaint and to impose sanctions pursuant to 22 NYCRR 130–1.1. Tulger argued that Alpha had breached a material term of the contract by requiring its workers to kick back money they received for supplements. In support of its motion, Tulger submitted evidence that Alpha and its president had pleaded guilty to a wilful violation of Labor Law § 220 ( seeLabor Law § 220[3][d][i][1], [2] ). In opposition to the motion, Alpha did not deny its wilful violation of the law, but contended that it had performed the work under the contract and should be paid the amounts it claimed to be due. The Supreme Court, inter alia, denied those branches of Tulger's motion which were for summary judgment dismissing the complaint and to impose sanctions pursuant to 22 NYCRR 130–1.1.

A party's illegal acts in the performance of a legal contract may, under certain circumstances, vitiate its right to recover on the contract ( see McConnell v. Commonwealth Pictures Corp., 7 N.Y.2d 465, 470, 199 N.Y.S.2d 483, 166 N.E.2d 494). In order for such a forfeiture to occur, “[t]here must at least be a direct connection between the illegal transaction and the obligation sued upon. Connection is a matter of degree” ( id. at 471, 199 N.Y.S.2d 483, 166 N.E.2d 494). Moreover, forfeiture is limited to “cases in which the illegal performance of a contract originally valid takes the form of commercial bribery or similar conduct and in which the illegality is central to or a dominant part of the plaintiff's whole course of conduct in performance of the contract” ( see id. at 471, 199 N.Y.S.2d 483, 166 N.E.2d 494;R.A.C. Group, Inc. v. Board of Educ. of City of N.Y., 21 A.D.3d 243, 249, 799 N.Y.S.2d 559).

Here, Tulger established its prima facie entitlement to judgment as a matter of law. Tulger demonstrated that Alpha's admitted illegal conduct in forcing its workers to kick back amounts received for supplements had a direct connection to the amounts Alpha claimed were due under the contract ( see FCI Group, Inc. v. City of New York, 54 A.D.3d 171, 177, 862 N.Y.S.2d 352). Additionally, because the kickback scheme took place repeatedly during Alpha's performance of the subcontract, “the illegality [was] central to or a dominant part of the plaintiff's whole course of conduct in performance of the contract” ( McConnell v. Commonwealth Pictures Corp., 7 N.Y.2d at 471, 199 N.Y.S.2d 483, 166 N.E.2d 494). Under such circumstances, public policy precludes Alpha from recovering the amounts it claims are due ( McConnell v. Commonwealth Pictures Corp., 7 N.Y.2d at 470, 199 N.Y.S.2d 483, 166 N.E.2d 494). In opposition, Alpha failed to raise a triable issue of fact ( see Persaud v. Bovis Lend Lease, Inc., 93 A.D.3d 831, 833, 941 N.Y.S.2d 208). Accordingly, the Supreme Court should have granted that branch of Tulger's motion which was for summary judgment dismissing the complaint.

However, the Supreme Court properly denied that branch of Tulger's motion which was to impose sanctions against Alpha ( see22 NYCRR 130–1.1; Karnes v. City of White Plains, 237 A.D.2d 574, 576, 655 N.Y.S.2d 615).


Summaries of

Alpha Interiors, Inc. v. Tulger Constr. Corp.

Supreme Court, Appellate Division, Second Department, New York.
Dec 5, 2012
101 A.D.3d 660 (N.Y. App. Div. 2012)

describing the scope of the public policy doctrine

Summary of this case from BAT, LLC v. TD Bank
Case details for

Alpha Interiors, Inc. v. Tulger Constr. Corp.

Case Details

Full title:ALPHA INTERIORS, INC., respondent, v. TULGER CONSTRUCTION CORPORATION…

Court:Supreme Court, Appellate Division, Second Department, New York.

Date published: Dec 5, 2012

Citations

101 A.D.3d 660 (N.Y. App. Div. 2012)
956 N.Y.S.2d 67
2012 N.Y. Slip Op. 8270

Citing Cases

Tutor Perini Corp. v. State

Connection is a matter of degree’ " ( Alpha Interiors, Inc. v. Tulger Constr. Corp., 101 A.D.3d 660, 661, 956…

Tutor Perini Corp. v. State

Defendant's claims regarding Perini's fraudulent performance of the contract fare no better. While a party's…