Opinion
2018-1871 K C
12-11-2020
ALL POWER ELECTRIC INSTALLATION CORP., Respondent, v. Jean-Michel APPOLON, Appellant.
Jean-Michel Appolon, appellant pro se. Alvin Dean, respondent pro se.
Jean-Michel Appolon, appellant pro se.
Alvin Dean, respondent pro se.
PRESENT: MICHELLE WESTON, J.P., DAVID ELLIOT, BERNICE D. SIEGAL, JJ.
ORDERED that the judgment is affirmed, without costs.
Plaintiff, an electrical contractor, commenced this commercial claims action to recover the principal sum of $5,000 for breach of contract, and defendant counterclaimed to recover the principal sum of $4,634.92, alleging that plaintiff had rendered its services in a defective manner. At a nonjury trial, the parties agreed that they had entered into a $13,000 contract, that defendant had paid plaintiff a total of $7,500, and that defendant had terminated the contract before the job was completed. Plaintiff presented testimony regarding the extent of the work completed and documentation that the work had passed inspection by the New York City Department of Buildings. Defendant appeals from a judgment of the Civil Court awarding plaintiff the principal sum of $5,000 and dismissing his counterclaim.
In a commercial claims action, our review is limited to a determination of whether "substantial justice has ... been done between the parties according to the rules and principles of substantive law" ( CCA 1807-A [a] ; see CCA 1804-A ; Ross v. Friedman , 269 AD2d 584 [2000] ; Williams v. Roper , 269 AD2d 125, 126 [2000] ). The determination of a trier of fact as to issues of credibility is given substantial deference, as a trial court's opportunity to observe and evaluate the testimony of the witnesses affords it a better perspective from which to assess their credibility (see Vizzari v. State of New York , 184 AD2d 564 [1992] ; Kincade v. Kincade , 178 AD2d 510, 511 [1991] ). This deference applies with greater force to judgments rendered in the Commercial Claims Part of the court (see Williams v. Roper , 269 AD2d at 126 ).
Here, there is support in the record for the conclusion that plaintiff had properly performed nearly all of the work required under the contract's terms before defendant prevented it from completing the contract. Thus, we find that substantial justice was done between the parties according to the rules and principles of substantive law and there is no basis for this court to disturb the Civil Court's determination (see CCA 1804-A, 1807-A [a] ).
Accordingly, the judgment is affirmed.
WESTON, J.P., ELLIOT and SIEGAL, JJ., concur.