Accadia Site Contracting, Inc. v. Erie Cnty. Water Auth.

Supreme Court, Appellate Division, Fourth Department, New York.
Mar 28, 2014
115 A.D.3d 1351 (N.Y. App. Div. 2014)

Opinion

2014-03-28

ACCADIA SITE CONTRACTING, INC., Plaintiff–Appellant, v. ERIE COUNTY WATER AUTHORITY, Defendant–Respondent.

Lipsitz Green Scime Cambria LLP, Buffalo (Andrew O. Miller of Counsel), for Plaintiff–Appellant. Damon Morey LLP, Buffalo (Amber E. Storr of Counsel), for Defendant–Respondent.



Lipsitz Green Scime Cambria LLP, Buffalo (Andrew O. Miller of Counsel), for Plaintiff–Appellant. Damon Morey LLP, Buffalo (Amber E. Storr of Counsel), for Defendant–Respondent.
PRESENT: SMITH, J.P., FAHEY, CARNI, AND SCONIERS, JJ.

MEMORANDUM:

In this action for breach of contract and related relief, plaintiff appeals from an order and judgment granting defendant's motion for summary judgment dismissing the complaint. Initially, we note that plaintiff does not raise any issues concerning the dismissal of the third cause of action and has therefore abandoned any contentions with respect to that cause of action ( see Ciesinski v. Town of Aurora, 202 A.D.2d 984, 984, 609 N.Y.S.2d 745). In addition, we do not address plaintiff's contention, raised for the first time on appeal, that Supreme Court erred in granting summary judgment in defendant's favor because defendant failed to plead the defense of failure to comply with a condition precedent with sufficient specificity ( seeCPLR 3015 [a] ). “An issue may not be raised for the first time on appeal ... where it ‘could have been obviated or cured by factual showings or legal countersteps' in the trial court” (Oram v. Capone, 206 A.D.2d 839, 840, 615 N.Y.S.2d 799, quoting Telaro v. Telaro, 25 N.Y.2d 433, 439, 306 N.Y.S.2d 920, 255 N.E.2d 158,rearg. denied26 N.Y.2d 751, 309 N.Y.S.2d 1031, 257 N.E.2d 296). Here, defendant could have attempted to cure that alleged deficiency by seeking leave to amend the answer ( see generally Smith v. Besanceney, 61 A.D.3d 1336, 1336–1337, 877 N.Y.S.2d 538). In any event, defendant's failure to plead that defense in its answer with sufficient specificity does not preclude an award of summary judgment based on that defense. “ ‘[A] court may grant summary judgment based upon an unpleaded defense where[, as here,] reliance upon that defense neither surprises nor prejudices the plaintiff’ ” (Schaefer v. Town of Victor, 77 A.D.3d 1346, 1347, 909 N.Y.S.2d 258).

Contrary to plaintiff's further contention, the court properly granted defendant's motion on the ground that plaintiff failed to satisfy a condition precedent. “[A] condition precedent is ‘an act or event, other than a lapse of time, which, unless the condition is excused, must occur before a duty to perform a promise in the agreement arises' ” (MHR Capital Partners LP v. Presstek, Inc., 12 N.Y.3d 640, 645, 884 N.Y.S.2d 211, 912 N.E.2d 43, quoting Oppenheimer & Co. v. Oppenheim, Appel, Dixon & Co., 86 N.Y.2d 685, 690, 636 N.Y.S.2d 734, 660 N.E.2d 415). Here, paragraph 10.05 of the contract mandated that plaintiff provide the project engineer with “[w]ritten notice stating the general nature of each Claim, dispute, or other matter” within 20 days of the event giving rise to the claim. It is well settled that “[c]ontract clauses that ‘require the contractor to promptly notice and document its claims made under the provisions of the contract governing the substantive rights and liabilities of the parties ... are ... conditions precedent to suit or recovery’ ” (Rifenburg Constr., Inc. v. State of New York, 90 A.D.3d 1498, 1498, 935 N.Y.S.2d 406, quoting A.H.A. Gen. Constr. v. New York City Hous. Auth., 92 N.Y.2d 20, 30–31, 677 N.Y.S.2d 9, 699 N.E.2d 368,rearg. denied92 N.Y.2d 920, 680 N.Y.S.2d 461, 703 N.E.2d 273). We conclude that “defendant established as a matter of law that plaintiff was obligated to seek compensation for the extra work pursuant to the terms of the contract when it learned that the [relocation of the lateral lines] constituted extra work and that plaintiff failed to do so in a timely manner” (Adonis Constr., LLC v. Battle Constr., Inc., 103 A.D.3d 1209, 1210, 959 N.Y.S.2d 346). Consequently, defendant met its burden on the motion by establishing that plaintiff did not timely comply with the notice and reporting requirements of the contract, and plaintiff failed to raise a triable issue of fact in opposition ( see generally Zuckerman v. City of New York, 49 N.Y.2d 557, 562, 427 N.Y.S.2d 595, 404 N.E.2d 718).

Plaintiff further contends that it was excused from compliance with the notice and reporting requirements of paragraph 10.05 based on defendant's breach of the contract; that such compliance was prevented or hindered because of misconduct by defendant; and that such compliance would have been futile. Those contentions are unavailing. First, it is well settled that a “party's obligation to perform under a contract is only excused where the other party's breach of the contract is so substantial that it defeats the object of the parties in making the contract” (Frank Felix Assoc., Ltd. v. Austin Drugs, Inc., 111 F.3d 284, 289;see Robert Cohn Assoc., Inc. v. Kosich, 63 A.D.3d 1388, 1389, 881 N.Y.S.2d 235), and plaintiff failed to raise a triable issue of fact whether defendant's actions defeated the parties' objectives in entering into the contract. With respect to plaintiff's remaining two contentions, we conclude that “there is no evidence to support [plaintiff]'s contention[s] that [defendant's misconduct] frustrated its ability to comply with the applicable notice provision or that notice to [the engineer] would have been futile” (Matter of Brenda DeLuca Trust [Elhannon, LLC], 108 A.D.3d 902, 904, 969 N.Y.S.2d 568). We note in any event with respect to plaintiff's second contention that, although “it is undisputedly the rule that one who frustrates another's performance cannot hold that party in breach” (Water St. Dev. Corp. v. City of New York, 220 A.D.2d 289, 290, 632 N.Y.S.2d 544,lv. denied88 N.Y.2d 809, 647 N.Y.S.2d 714, 670 N.E.2d 1346;see Young v. Hunter, 6 N.Y. 203, 207), plaintiff failed to raise a triable issue of fact whether its performance with the notice and reporting requirements was prevented or hindered by defendant's alleged misconduct ( see A.H.A. Gen. Constr., 92 N.Y.2d at 34, 677 N.Y.S.2d 9, 699 N.E.2d 368;DiPizio Constr. Co., Inc. v. Niagara Frontier Transp. Auth., 107 A.D.3d 1565, 1566, 968 N.Y.S.2d 288;cf. Turbo Carpentry Corp. v. Brancadoro, 21 A.D.3d 479, 480, 800 N.Y.S.2d 566).

It is hereby ORDERED that the order and judgment so appealed from is unanimously affirmed without costs.


Summaries of

Accadia Site Contracting, Inc. v. Erie Cnty. Water Auth.

Supreme Court, Appellate Division, Fourth Department, New York.
Mar 28, 2014
115 A.D.3d 1351 (N.Y. App. Div. 2014)
Case details for

Accadia Site Contracting, Inc. v. Erie Cnty. Water Auth.

Case Details

Full title:ACCADIA SITE CONTRACTING, INC., Plaintiff–Appellant, v. ERIE COUNTY WATER…

Court:Supreme Court, Appellate Division, Fourth Department, New York.

Date published: Mar 28, 2014

Citations

115 A.D.3d 1351 (N.Y. App. Div. 2014)
115 A.D.3d 1351
2014 N.Y. Slip Op. 2194

Citing Cases

Fahs Constr. Grp., Inc. v. State

According to the contract, the contractor's failure to supply the required notice and submit the required…

Doyle v. George A. Nole & Son, Inc.

With respect to the remaining claims, we conclude that defendant met its initial burden on the motion (see…