605 Fifth Property Owner, LLC (“Owner”) has sued Abasic, S.A. (“Abasic”) to enforce a guarantee (the “Guarantee”) on a commercial lease held by Abasic's subsidiary. Owner has submitted a motion for summary judgment on its claims, and has requested that its complaint be deemed amended to allege damages incurred since the complaint was filed. For the following reasons, the plaintiff's motion is granted.
Background
This follows an action filed last year between the same parties regarding the same lease and guarantee agreements. The Court assumes familiarity with its Opinion granting summary judgment to the plaintiff in that case, and incorporates its findings and reasoning here. See 605 Fifth Property Owner, LLC v. Abasic, S.A., No. 21CV00811, 2022 WL 683746 (S.D.N.Y. Mar. 8, 2022). Owner brought this case to enforce an unconditional guarantee agreement (the “Guarantee”) with Abasic, in which Abasic agreed to guarantee its subsidiary's obligations under a commercial lease (the “Lease”). Abasic's subsidiary, NTS W. USA Corp. (“NTS”), had intended to use the leased property to open a retail outlet. Unfortunately, its plans coincided with the COVID-19 pandemic. NTS was unable to profitably operate a retail establishment, and after several months, it declared bankruptcy, having made no rental payments.
During bankruptcy proceedings, NTS rejected the Lease, and initiated an adversary proceeding seeking to avoid its obligations under the Lease. The Bankruptcy Court, however, ruled against NTS in the adversary proceeding, and its ruling was affirmed by the District Court. See In re NTS W. USA Corp., No. 20CV06692, 2021 WL 4120676 (S.D.N.Y. Sept. 9, 2021). That decision is currently on appeal before the Second Circuit. In re NTS W. USA Corp., No. 21-2240.
On February 1, 2021, Owner filed a lawsuit (the “Prior Action”) in the Southern District of New York, seeking to enforce the Guarantee. The action was transferred to this Court on September 9, 2021. The parties submitted cross-motions for summary judgment. The plaintiff sought to enforce the Guarantee, while Abasic asserted several defenses, including an argument that the Guarantee was discharged during NTS's bankruptcy proceedings. The March 8, 2022 Opinion granted summary judgment to the plaintiff, finding that the Guarantee was enforceable, that it had not been discharged during NTS's bankruptcy, and that Abasic's remaining defenses were unavailing. Final judgment was entered in favor of the plaintiff on April 27. That judgment is currently on appeal. 605 Fifth Property Owner, LLC v. Abasic, S.A., No. 22-945.
Owner filed this action on June 2, seeking damages that have accrued under the Guarantee since it filed for summary judgment in the Prior Action. Abasic answered the complaint on June 27, asserting the same defenses as it asserted in the Prior Action. The action was transferred to this Court on August 12.
Owner filed a motion for summary judgment on August 19, including an accounting of rent and other expenses that have accrued under the Guarantee since the end of January, when it submitted its motion for summary judgment in the Prior Action. Abasic opposed the motion on September 9. Instead of contesting its liability under the Guarantee, however, Abasic argued in its opposition only that the case should be stayed pending the resolution of its appeal of the Prior Action. Owner submitted its reply on September 23, including an updated accounting of its damages.
Discussion
I. Stay
“The power to stay proceedings is incidental to the power inherent in every court to control the disposition of the causes on its docket with economy of time and effort for itself, for counsel, and for litigants.” Louis Vuitton Malletier S.A. v. LY USA, Inc., 676 F.3d 83, 96 (2d Cir. 2012) (quoting Landis v. N. Am. co., 299 U.S. 248, 254 (1936)). “The person seeking a stay bears the burden of establishing its need.” Id. at 97 (citation omitted). When considering whether to stay a case pending the resolution of related proceedings, courts in this District generally consider five factors:
(1) the private interests of the plaintiffs in proceeding expeditiously with the civil litigation as
balanced against the prejudice to the plaintiffs if delayed; (2) the private interests of and burden on the defendants; (3) the interests of the courts; (4) the interests of persons not parties to the civil litigation; and (5) the public interest.Loftus v. Signpost Inc., 464 F.Supp.3d 524, 526 (S.D.N.Y. 2020).
Owner argues that the four-factor test articulated in Hilton v. Braunskill, 481 U.S. 770 (1987) should apply. Under that test, a court must consider:
(1) whether the stay applicant has made a strong showing that he is likely to succeed on the merits; (2) whether the applicant will be irreparably injured absent a stay; (3) whether issuance of the stay will substantially injure the other parties interested in the proceeding; and (4) where the public interest lies.Id. at 776. This test, however, applies to the stay of an “order pending appeal.” Id.; see also Nken v. Holder, 556 U.S. 418, 426 (2009). Because Abasic seeks a stay of proceedings, not a stay of an order, this four-factor test does not apply. Regardless, Abasic's request for a stay must be denied. Abasic has not satisfied even the more lenient test for a stay of proceedings. And, as this Court explained in denying Abasic's request to waive the supersedeas bond requirement pending appeal of the Prior Action, Abasic is unlikely to succeed on the merits of its appeal, cannot establish irreparable harm, and has not shown that a stay would serve the parties or the public interest. See 605 Fifth Property Owner, LLC v. Abasic, S.A., 21CV00811, 2022 WL 1422821, at *2-4 (S.D.N.Y. May 5, 2022).
Abasic has not shown that a stay is warranted. Owner has an interest in expeditiously proceeding with the present action, so that it can recover the money it is owed under the Guarantee. Abasic argues that Owner will not receive its money any sooner because it can post a supersedeas bond. But that bond also benefits the plaintiff, because it helps to “ensure that the prevailing party will recover in full.” In re Nassau County Strip Search Cases, 783 F.3d 414, 417 (2d Cir. 2015) (citation omitted). Abasic, by contrast, has an interest in delaying proceedings. A stay would help Abasic avoid the costs of filing a second appeal and allow it to further delay payments owed under the Guarantee.
With respect to the remaining factors, judicial efficiency is not served by delaying a decision on this action when it could easily be resolved now. And although the parties have not identified specific other persons with an interest in litigation either way, the public interest is served by the certain and efficient enforcement of unconditional guarantee agreements.
This is the third time that Abasic has requested a stay from this Court while it pursues appeals that are unlikely to succeed. See 605 Fifth Property Owner, LLC, 2022 WL 683746, at *5; 605 Fifth Property Owner, LLC, 2022 WL 1422821, at *2-4. Delay was unwarranted then, and it is unwarranted now. Abasic's request for a stay is denied.
II. Amendment
Owner moves to deem the complaint amended to allege additional damages accrued since the complaint was filed. “The decision of whether to allow such an amendment is left to the discretion of the district court judge.” Vermont Plastics, Inc. v. Brine, Inc., 79 F.3d 272, 279 (2d Cir. 1996). Amendment is inappropriate, however, when it would prejudice the other party. Gussack Realty Co. v. Xerox Corp., 224 F.3d 85, 94 (2d Cir. 2000).
Here, Owner seeks to amend only to allege damages for rent that has become payable since the complaint was filed. The Prior Action has put Abasic on notice that it continues to be liable for payments under the Guarantee, and Abasic provides no argument that this amendment would prejudice it. Accordingly, the complaint is deemed amended to allege $1,254,729.07 in damages for unpaid rent.
III. Summary Judgment
Summary judgment may only be granted when “the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). “To present a genuine issue of material fact sufficient to defeat a motion for summary judgment, the record must contain contradictory evidence such that a reasonable jury could return a verdict for the nonmoving party.” Horror Inc. v. Miller, 15 F.4th 232, 241 (2d Cir. 2021) (citation omitted). Material facts are those facts that “might affect the outcome of the suit under the governing law.” Choi v. Tower Rsch. Cap. LLC, 2 F.4th 10, 16 (2d Cir. 2021) (citation omitted). In considering a motion for summary judgment, a court must “construe the facts in the light most favorable to the nonmoving party and must resolve all ambiguities and draw all reasonable inferences against the movant.” Kee v. City of New York, 12 F.4th 150, 158 (2d Cir. 2021) (citation omitted).
When a case involves a matter that has previously been litigated, its outcome may be determined by the related doctrines of res judicata (claim preclusion) or collateral estoppel (issue preclusion). “The doctrine of res judicata, or claim preclusion, holds that a final judgment on the merits of an action precludes the parties or their privies from relitigating issues that were or could have been raised in that action.” In re Motors Liquidation Co., 943 F.3d 125, 130 (2d Cir. 2019) (citation omitted). The doctrine of collateral estoppel, or issue preclusion, prevents the relitigation of issues rather than claims. Specifically, it “bars successive litigation of an issue of fact or law actually litigated and resolved in a valid court determination essential to a prior judgment.” United States v. Jones, 43 F.4th 94, 101 (2d Cir. 2022) (citation omitted). “[A] judgment's preclusive effect is generally immediate, notwithstanding any appeal.” Coleman v. Tollefson, 575 U.S. 532, 539 (2015).
Owner seeks to enforce the same Guarantee at issue in the Prior Action. Both actions involve the same parties, the same claims, and the same defenses. Abasic has pointed to no issue relevant to the case that was not resolved in the Prior Action, or that was not essential to the final judgment. Indeed, Abasic states that it “does not currently seek to refute the allegations” in Owner's motion for summary judgment, and it does not contest Owner's calculation of damages. Abasic also acknowledges that the resolution of this action is “entirely depend[e]nt on the outcome of the [a]ppeal” of the Prior Action. The judgment in the Prior Action, however, has preclusive effect even pending appeal. Id. The judgment in the Prior Action therefore controls. And even if it did not, the reasoning of the March 8 Opinion granting summary judgment to the plaintiff in the Prior Action would compel the same result here. Accordingly, summary judgment is granted to the plaintiff on its claims for breach of contract and attorney's fees, and on each of Abasic's defenses.
Conclusion
Owner's August 19 motion to amend its complaint and for summary judgment on its claims and the defendant's defenses is granted. Defendant is liable to the plaintiff for $1,254,729.07, as well as attorney's fees and legal costs. The plaintiff shall submit a proposed judgment no later than November 18, 2022.