Iowa Code § 476A.1

Current through March 29, 2024
Section 476A.1 - Definitions

As used in this subchapter, unless the context otherwise requires:

1."Agency" means an agency as defined in section 17A.2, subsection 1.
2."Board" means the utilities board.
3."Certificate" means a certificate of public convenience, use and necessity issued pursuant to section 476A.6.
4."Commence to construct" means significant alteration of a site to install permanent equipment or structures but does not include activities incident to preliminary engineering, environmental studies or acquisition of a site for a facility.
5."Facility" means any electric power generating plant, electric storage unit, or a combination of plants or units at a single site, owned by any person, with a total capacity of twenty-five or more megawatts of electricity for plants or twenty-five or more megawatt hours of electricity for electric storage units, and those associated transmission lines connecting the generating plant or electric storage unit to either a power transmission system or an interconnected primary transmission system or both. Transmission lines subject to the provisions of this subchapter shall not require a franchise under chapter 478.
6."Regulatory agency" means an agency which issues licenses or permits required for the construction, operation or maintenance of a facility pursuant to statutes or rules in effect on the date on which an application for a certificate is accepted by the utilities board.

Iowa Code § 476A.1

90 Acts, ch 1252, §41; 2001 Acts, 1st Ex, ch 4, §35, 36; 2023 Acts, ch 19, § 2681

Amended by 2024 Iowa, ch Chapter 1108,s 4, eff. 7/1/2024.
Amended by 2023 Iowa, ch 19, s 2681, eff. 7/1/2023.
C77, 79, 81, §476A.1 90 Acts, ch 1252, §41; 2001 Acts, 1st Ex, ch 4, §35, 36

Subsection 2 amended