30 Miss. Code. R. 603-3.2

Current through October 18, 2024
Rule 30-603-3.2 - Cost Recovery Plan
1. Upon receipt of a request for wireless E9-1-1 service from a Mississippi Emergence Communication District or Districts (ECDs), the CMRS carrier will develop a comprehensive detailed plan for implementation of E9-1-1 service for the ECD, or the appropriate service area if the CMRS carriers switch serves more than one ECD.
2. The plan, complete with cost information, will be presented to the requesting ECD for concurrence. Upon acceptance of the plan and the associated cost structure by the ECD, the ECD (in person or by proxy) and CMRS carrier will present the plan to the Board for its approval. The CMRS carrier shall present in writing to the Board detailed coverage area and customer information to ensure expedient roll-out of wireless E9-1-1 service as requests are received and approved by the Board.
3. After initial acceptance of a CMRS carriers plan using a particular solution by the Board, the CMRS carrier need not make additional presentations to the Board as to that particular solution. Certified letters shall be sent to the Board with notification of additional serve implementation in the state and the resulting cost recovery represented.
4. The initial cost recovery plan presented to the Board is intended to allow for the recovery of a carriers cost on a one time basis (NRC) and/or recurring monthly basis (MRC). A list of anticipated MRCs and NRCs is set forth below, but the list will vary depending upon the CMRS carrier and the selected E911 solution:

Trunks:

Trunking

Connection fee to 9-1-1 Selective Router (per DSO)

Engineering & Network Costs:

Facilities; T-1's, selective router ports

Routing Charges

Operations

Engineering

Switch upgrades

Research & Development

Network design

Test plan development

Database Cost

P-ANI administration

Database management

Other

Reporting

Software

Other

5. The Board shall provide the CMRS carrier either approval or denial of the cost recovery plan in writing, and send by certified United States Mail or by any other express service requiring a delivery signature. If the Board denies a CMRS carriers cost recovery plan, the Board shall provide express reasons for the denial in writing within 3 days of the denial. The CMRS carrier may resubmit or revise cost recovery plans as soon as the Board approves an acceptable date. If the Board approves the cost recovery plan, then the CMRS carrier and the Board shall sign the model contract, attaching the cost recovery plan.