Ala. Admin. Code r. 335-7-4-.06

Current through Register Vol. 42, No. 11, August 30, 2024
Section 335-7-4-.06 - Permits Approval/Denial
(1) Upon receipt of a complete application, appropriate fees, and necessary information to evaluate the water quality, system facilities, and operational aspects, existing and proposed system facilities will be evaluated. Existing and proposed systems must demonstrate technical, managerial, and financial capabilities to reliably meet performance requirements on a long term basis and be self sustaining. After a determination has been made that the proposed water system or additions to the system are satisfactory and the existing system has technical, managerial and financial capacity and is in complete compliance with all regulations, a permit will be issued.
(2) If after the review of the application and information submitted shows water quality deficiencies, design problems or technical, managerial or financial capacity deficiencies, a formal request for additional information to clarify the problem areas will be made to the applicant. Upon failure to receive this additional information or if upon review of the supplemental information the proposal is still unsatisfactory, the permit will be denied. Permit denial will be made in writing to the applicant with reasons for the denial stated.

Authors: Joe Alan Power, Edgar K. Hughes

Ala. Admin. Code r. 335-7-4-.06

Repealed and Readopted: January 4, 1989; October 31, 1990. Revised: September 23, 1992; effective November 9, 1992. Amended: Filed May 2, 2000; effective June 6, 2000. Amended: Filed November 7, 2005; effective December 12, 2005.

Statutory Authority:Code of Ala. 1975, §§ 22-23-44, 22-23-49, 22-22A-5, 22-22A-6.